BLD20-02388
| BLD-Final | 7/27/2020 | 7/28/2020 | 7/29/2020 9:19:22 AM | P | PASS |
|
|
Inspection on a completed asphalt roofing project. Phone #: ###-#### Inspection requested via web by Michael La Pointe
|
BLD20-01009
| BLD-Footing | 7/27/2020 | 7/28/2020 | 7/28/2020 5:00:24 PM | P | NR |
|
|
Need Soil subgrade submitted and approved by PW...
|
BLD19-04204
| BLD-Conference | 7/28/2020 | 7/28/2020 | 7/28/2020 4:59:42 PM | P | DONE |
|
|
Prefinal walk thru...
|
BLD20-01780
| BLD-Foundation | 7/28/2020 | 7/28/2020 | 7/28/2020 4:59:16 PM | P | PASS |
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion
|
BLD20-01782
| BLD-Framing/Rough-in | 7/27/2020 | 7/28/2020 | 7/28/2020 4:59:07 PM | P | PEND |
|
|
Provide truss Engineering... No other issues...
|
BLD20-01779
| BLD-Energy code compliance | 7/27/2020 | 7/28/2020 | 7/28/2020 4:58:34 PM | P | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Rob Johnson
|
BLD20-01783
| BLD-Footing | 7/28/2020 | 7/28/2020 | 7/28/2020 4:58:21 PM | P | CANC |
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion
|
BLD20-01785
| BLD-Footing | 7/28/2020 | 7/28/2020 | 7/28/2020 4:57:02 PM | P | PASS |
|
|
Work in progress...
|
BLD20-02391
| BLD-Final | 7/27/2020 | 7/28/2020 | 7/28/2020 1:52:41 PM | P | PASS |
|
|
Inspection on a completed asphalt roofing project. Phone #: ###-#### Inspection requested via web by Michael La Pointe
|
BLD20-02391
| DOC - Permit Finaled | 7/28/2020 | 7/28/2020 | 7/28/2020 1:51:18 PM | P | PASS |
|
|
|
BLD19-03812
| BLD-Wall Bracing | 7/27/2020 | 7/28/2020 | 7/28/2020 11:50:17 AM | A | PASS |
|
|
Screened // Les Phone #: ###-####
|
BLD20-01416
| BLD-Wall Bracing | 7/27/2020 | 7/28/2020 | 7/28/2020 11:50:07 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Aron Mock
|
BLD20-01271
| BLD-Framing/Rough-in | 7/27/2020 | 7/28/2020 | 7/28/2020 11:49:56 AM | A | PASS |
|
|
SCREENED // Daniel Phone #: ###-####
|
BLD20-02024
| BLD-Final | 7/27/2020 | 7/28/2020 | 7/28/2020 11:49:47 AM | A | PASS |
|
|
Inspection requested via web by Hans Weikl
|
BLD20-02024
| DOC - Permit Finaled | 7/28/2020 | 7/28/2020 | 7/28/2020 11:49:40 AM | P | PASS |
|
|
|
BLD20-01670
| BLD-Framing/Rough-in | 7/27/2020 | 7/28/2020 | 7/28/2020 11:49:31 AM | A | PASS |
|
|
Call Rob 2089418575 for access Phone #: ###-#### Inspection requested via web by JANET TATILIAN
|
BLD20-02498
| BLD-Final | 7/27/2020 | 7/28/2020 | 7/28/2020 11:49:18 AM | A | PASS |
|
|
Inspection on a completed asphalt roofing project. Phone #: ###-#### Inspection requested via web by Michael La Pointe
|
BLD20-02498
| DOC - Permit Finaled | 7/28/2020 | 7/28/2020 | 7/28/2020 11:49:05 AM | P | PASS |
|
|
|
BLD19-04781
| BLD-Footing | 7/27/2020 | 7/28/2020 | 7/28/2020 11:48:36 AM | A | PART |
|
|
Speciakl inspector to be on site for rebar and concrete pour...
|
BLD19-03400
| BLD-Aging Inspection | 7/28/2020 | 7/28/2020 | 7/28/2020 8:17:00 AM | | DEFR |
|
|
|
BLD19-03400
| Extend Permit 90/180 days | 7/28/2020 | 7/28/2020 | 7/28/2020 8:16:51 AM | P | DONE |
|
|
|