MEC18-02752
| Conference | 6/14/2018 | 6/18/2018 | 6/18/2018 5:53:14 PM | P | DONE |
|
|
I work during the day, so if we can push this to the last appointment - around 4:15/4:30, that would be much appreciated. Please text or call at 719.271.9124 to confirm. Thanks! Phone #: ###-#### Inspection requested via web by Daniel Grover - talked with home owner about re routing all ducting that was once in the crawl and is now going to be ran in basement ceiling
|
MEC18-02776
| Final | 6/14/2018 | 6/18/2018 | 6/18/2018 3:59:04 PM | P | FAIL |
|
|
INSTALLER BRIAN ###-#### Phone #: ###-#### Inspection requested via web by Aaron Alandt- 5 lb flue test fail couldnt hold pressure- call back in when ready
|
MEC18-01668
| Rough-in | 6/18/2018 | 6/18/2018 | 6/18/2018 3:27:29 PM | P | PASS |
|
|
ceiling ducting, please call 30 mins ahead - Tom Phone #: ###-####- ceiling tile cover ok- need balance dampers at each branch on exhaust for nail stations
|
MEC17-03987
| Final | 6/15/2018 | 6/18/2018 | 6/18/2018 2:59:25 PM | P | PASS |
|
|
Please call the tenant to let them know when you''re on the way. Leave a message if the don''t answer. Marika ###-#### Phone #: ###-#### Inspection requested via web by Krista Boss - breaker size is correct- final ok
|
MEC18-01779
| Final | 6/18/2018 | 6/18/2018 | 6/18/2018 2:38:06 PM | P | FAIL |
|
|
Late PM please. Eric ###-#### Phone #: ###-#### Inspection requested via web by Krista Boss- need air balance report onsite and duct blast report onsite- everything else looks ok
|
MEC18-01776
| Final | 6/11/2018 | 6/18/2018 | 6/18/2018 2:03:14 PM | P | FAIL |
|
|
Please call the customer when on way: John ###-#### Phone #: ###-#### Inspection requested via web by Krista Boss - gas line penetration needs to be sealed- Line set needs to be supported and lifted 3.5 inches off the ground at outdoor unit
|
MEC18-02736
| Final | 6/13/2018 | 6/18/2018 | 6/18/2018 10:51:30 AM | A | PASS |
|
|
Please call Deborah at ###-#### to coordinate Phone #: ###-#### Inspection requested via web by Sabrina DeHority- furnace ac coil co ok
|
MEC18-02736
| Pressure Test | 6/13/2018 | 6/18/2018 | 6/18/2018 10:51:14 AM | A | CANC |
|
|
Please call Deborah at ###-#### to coordinate Phone #: ###-#### Inspection requested via web by Sabrina DeHority- no flue pressure test needed
|
MEC16-04910
| Mec-Aging Inspection | 6/18/2018 | 6/18/2018 | 6/18/2018 9:58:58 AM | | NR |
|
|
home onwer was home and said he was leaving on vacation and he would get an inspection scheduled as soon as possible
|
MEC17-04370
| Final | 6/14/2018 | 6/18/2018 | 6/18/2018 9:56:16 AM | A | PASS |
|
|
9am inspection david son chris should be home for inspection ; Phone #: ###-#### - furnace ac coil co ok
|
MEC18-00206
| Final | 6/15/2018 | 6/18/2018 | 6/18/2018 9:37:34 AM | A | PART |
|
|
Contact Name: Jason Davidson Phone #: ###-#### Inspection requested via web by RM Mechanical- 1st floor east side mini splits condensates are supported
|
MEC18-01647
| Conference | 6/15/2018 | 6/18/2018 | 6/18/2018 8:38:33 AM | A | PART |
|
|
T bar Grid inspection - for cover Phone #: ###-#### Inspection requested via web by Dave Sorensen- ceiling tile ok for cover
|