BLD19-00538
| BLD-Footing | 2/21/2020 | 2/21/2020 | 2/21/2020 3:34:40 PM | P | PART |
|
|
Pouring the footings for garage 6 at 1pm also Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok pending specials//one area needed heated prior to pour--discussed with special inspector onsite//
|
BLD19-00529
| BLD-Foundation | 2/21/2020 | 2/21/2020 | 2/21/2020 3:33:55 PM | P | PART |
|
|
Pouring walls at 1pm Phone #: ###-#### Inspection requested via web by Travis Blackburn//ok pending specials//
|
BLD19-03873
| BLD-Framing/Rough-in | 2/21/2020 | 2/21/2020 | 2/21/2020 3:13:28 PM | P | PART |
|
|
Eddy Phone #: ###-####//need to add 1 nmore jamb stud per plans//let Ed know onsite//header per plans//header over new counter area only//
|
BLD19-04625
| BLD-Final | 2/20/2020 | 2/21/2020 | 2/21/2020 3:12:38 PM | P | NR |
|
|
john ###-####//walk through for temp occupancy//would like to see flooring installed for transitions noted on plans//
|
BLD19-03422
| BLD-Wall Bracing | 2/20/2020 | 2/21/2020 | 2/21/2020 2:02:30 PM | P | NR |
|
|
Phone #: ###-#### Inspection requested via web by John Cloninger//need to nails with 8d nails per plans//provide engineers approval of wedge type anchors for hold downs in place of cast in place anchors//block all edges//will call for shear nailing//
|
BLD19-03372
| BLD-Final | 2/20/2020 | 2/21/2020 | 2/21/2020 1:16:40 PM | A | FAIL |
|
|
Phone #: ###-#### Inspection requested via web by Jordan Williams//no access to roof//contractor will need to meet onsite for roof access//
|
BLD20-00032
| BLD-Footing | 2/20/2020 | 2/21/2020 | 2/21/2020 10:53:23 AM | A | FAIL |
|
|
re-inspect pour around 12//ground is still frozen in a good portion of the footings//some of the flatwork sub grade is also frozen//
|
BLD19-03259
| BLD-Final | 2/20/2020 | 2/21/2020 | 2/21/2020 10:40:52 AM | A | FAIL |
|
|
Please call 30 minutes prior to arrival Phone #: ###-#### Inspection requested via web by Kenneth Lamm//smoke detector missing in bedroom//smoke/co combl needed in hallway//need to be interconnected//left CN oniste//all other trades passed//will need re-inspection//
|
BLD19-04887
| BLD-Foundation | 2/20/2020 | 2/21/2020 | 2/21/2020 10:13:51 AM | A | PART |
|
|
Brett- foundation wall inspection Phone #: ###-####//wall rebar installed//blankets onsite--frost protection will need to be maintained//still working//setbacks tight on three sides//
|
MIS20-00051
| BLD-Conference | 2/14/2020 | 2/21/2020 | 2/21/2020 9:31:14 AM | A | DONE |
|
|
follow up....//all trades have posted notices//cotractor made contact with me yesterday--advised him to contact plan review to start process for permits//appears to be a plumbing permit issued//check back 5 days//
|
BLD19-04324
| BLD-Footing | 2/20/2020 | 2/21/2020 | 2/21/2020 9:20:51 AM | A | PART |
|
|
Inspection for first thing in morning please.... and thank you Phone #: ###-#### Inspection requested via web by Candyce Moss//no frost observed in holes//frost protection will be required//depth ok per plans//
|
BLD19-01808
| BLD-Aging Inspection | 2/21/2020 | 2/21/2020 | 2/21/2020 8:42:55 AM | | CANC |
|
|
|
BLD18-00954
| BLD-Aging Inspection | 2/21/2020 | 2/21/2020 | 2/21/2020 8:42:37 AM | | DONE |
|
|
Expires: 04/07/20
|