Inspections for the day of: Monday, February 3, 2020.
Number of inspections: 23
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTell Riley
TitleBLD-COM/RES INSPECTOR
Phone #830-2752
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD19-00527 BLD-Framing/Rough-in2/3/20202/3/20202/3/2020 4:27:44 PMPNR
Verify truss fixes and other misc. pre cover inspection items Phone #: ###-#### Inspection requested via web by Travis Blackburn//see truss engineering for fixes//
BLD19-00534 BLD-Framing/Rough-in2/3/20202/3/20202/3/2020 4:26:51 PMPPART
Walk prerock areas in K for insulation Phone #: ###-#### Inspection requested via web by Travis Blackburn//will be ok after hold downs installed//
BLD20-00085 BLD-Framing/Rough-in2/3/20202/3/20202/3/2020 3:59:26 PMPFAIL
steve - call for access Phone #: ###-####//no trades permits pulled//not able to make contact, not able to leave voicemail//will need trades inspected and passed prior to framing//
BLD19-02932 BLD-Conference1/27/20202/3/20202/3/2020 2:45:25 PMPDONE
Graciela Phone #: ###-####//shear ok//truss issues were discussed//
BLD19-03074 BLD-Final2/3/20202/3/20202/3/2020 2:29:28 PMPPASS
Garage code 3162 Phone #: ###-#### Inspection requested via web by Kelly Stover//corrections made//
BLD19-03074 DOC - Permit Finaled2/3/20202/3/20202/3/2020 2:29:08 PMPPASS
BLD19-03074 BLD-Blower Door Test Results2/3/20202/3/20202/3/2020 2:28:02 PMPDONE
3.82 ACH 50
BLD19-04318 BLD-Final2/3/20202/3/20202/3/2020 2:09:57 PMPPASS
call ahead // Russell Phone #: ###-####//corrections made//
BLD19-04318 DOC - Permit Finaled2/3/20202/3/20202/3/2020 2:09:39 PMPPASS
BLD19-01804 BLD-Final2/3/20202/3/20202/3/2020 1:54:39 PMPFAIL
Vinnie Phone #: ###-####//CN posted//
BLD19-04412 BLD-Framing/Rough-in2/3/20202/3/20202/3/2020 12:27:36 PMPPART
lAURENCE Phone #: ###-####//beam ok//door on east side ok//do not cover any walls with electrical//
BLD19-03701 BLD-Framing/Rough-in1/31/20202/3/20202/3/2020 12:16:23 PMAPART
Mark Phone #: ###-####//see red marks for corrections//need mech permit for FP//no access to garage 2n floor//ok to insulate house only//
BLD19-04363 BLD-Framing/Rough-in2/3/20202/3/20202/3/2020 11:34:35 AMPPASS
Kevin Phone #: ###-####//per plans//
BLD19-03229 BLD-Wall cover1/31/20202/3/20202/3/2020 11:17:58 AMACANC
Phone #: ###-#### firewall Inspection requested via web by Carl Funk
BLD19-03253 BLD-Wall cover1/31/20202/3/20202/3/2020 11:17:46 AMACANC
Phone #: ###-#### firewall Inspection requested via web by Carl Funk
BLD19-03247 BLD-Wall cover1/31/20202/3/20202/3/2020 11:17:36 AMACANC
Phone #: ###-#### fire wall Inspection requested via web by Carl Funk
BLD19-03248 BLD-Wall cover1/31/20202/3/20202/3/2020 11:17:18 AMACANC
Phone #: ###-#### Inspection requested via web by Carl Funk
BLD19-03249 BLD-Wall cover1/31/20202/3/20202/3/2020 11:17:07 AMACANC
Phone #: ###-#### firewall Inspection requested via web by Carl Funk
BLD19-03250 BLD-Wall cover1/31/20202/3/20202/3/2020 11:16:56 AMACANC
Phone #: ###-#### fire wall Inspection requested via web by Carl Funk
BLD19-03251 BLD-Wall cover1/31/20202/3/20202/3/2020 11:16:45 AMACANC
Phone #: ###-#### firewall Inspection requested via web by Carl Funk
BLD19-03252 BLD-Wall cover1/31/20202/3/20202/3/2020 11:16:31 AMACANC
Phone #: ###-#### fire wall Inspection requested via web by Carl Funk
BLD19-04693 BLD-Footing1/31/20202/3/20202/3/2020 11:16:19 AMAPASS
12:00PM - Pour Time Phone #: ###-#### Inspection requested via web by Laurie Hoelscher
BLD19-04625 BLD-Framing/Rough-in1/31/20202/3/20202/3/2020 10:39:27 AMAPASS
John Phone #: ###-####//need to add backing for grab bars--wood will need to be fire treated//will take photos as installed//all other framing ok per plans//