Inspections for the day of: Friday, April 3, 2020.
Number of inspections: 18
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTell Riley
TitleBLD-COM/RES INSPECTOR
Phone #830-2752
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD19-01648 BLD-Aging Inspection4/3/20204/3/20204/7/2020 7:15:58 AM PEND
BLD19-03949 BLD-Final4/3/20204/3/20204/3/2020 4:26:47 PMPPASS
screened // Christina Phone #: ###-####
BLD19-03949 DOC - Permit Finaled4/3/20204/3/20204/3/2020 4:26:38 PMPPASS
BLD19-03507 BLD-Wall Bracing4/3/20204/3/20204/3/2020 4:12:14 PMPPART
screened // Eber Phone #: ###-####//need to add hot dip galvanized nails at pt plates//nailing ok otherwise//soffit detail shows two layers gyp on west of garage, need to add 1 layer//
BLD20-00059 BLD-Foundation4/3/20204/3/20204/3/2020 3:51:44 PMPPASS
cleared // Edgar Phone #: ###-####
BLD19-03949 BLD-Blower Door Test Results4/3/20204/3/20204/3/2020 3:01:23 PMPDONE
3.32 ACH 50
BLD19-04970 BLD-Final4/3/20204/3/20204/3/2020 2:42:17 PMPPASS
virtual inspection only // Scott Phone #: ###-####//appears to be complete, video conference was used for final inspection du to pandemic/
BLD19-04970 DOC - Permit Finaled4/3/20204/3/20204/3/2020 2:41:37 PMPPASS
final completed via videoconference due to pandemic//
BLD19-00532 BLD-Wall Bracing4/2/20204/3/20204/3/2020 2:10:48 PMPPART
Shear panels only on exterior of bldg. Hardware next week Phone #: ###-#### Inspection requested via web by Travis Blackburn//need to add hot dip galvanized nails at coridors, and areas marked//will check hardware in next inspection//
BLD19-04013 BLD-Wall Bracing4/3/20204/3/20204/3/2020 1:07:37 PMPPART
*cleared* Please call ahead so site can cleared Pat Phone #: ###-####///second story interior shear walls prior to gyp cover//
BLD20-00478 BLD-Final4/2/20204/3/20204/3/2020 12:34:22 PMAPART
derek Phone #: ###-####//onsite ok looking from exterior//need to add interconnected smoke and smoke/co detectors//Derek will video call when installed//
BLD19-04304 BLD-Foundation4/3/20204/3/20204/3/2020 11:00:15 AMAPART
Pour scheduled for 12 o’clock Phone #: ###-#### Inspection requested via web by Edgar Sanchez//WIP//discussed pouring frost wall at garage per details on foundation plans//was not set at time of inspection//
BLD20-00059 BLD-Foundation4/3/20204/3/20204/3/2020 10:59:24 AMANR
Pour scheduled for 12 o’clock Phone #: ###-#### Inspection requested via web by Edgar Sanchez
MIS20-00100 BLD-Conference4/2/20204/3/20204/3/2020 10:47:51 AMADONE
due to no inpections on occupied residential during the pandemic, a visual from street of the shed, appears to be in the 200 sq ft or under allowed by code with no permit, no cantact with owner was made//
BLD20-00651 BLD-Final3/9/20204/3/20204/3/2020 9:52:59 AMAPASS
jon ###-####//signed card, advised Jon that any changes to the floor plan, ie new offices, layout etc, would require a permit, he stated they would be getting a permit for remodel//
BLD20-00159 BLD-Final4/2/20204/3/20204/3/2020 9:10:17 AMAPASS
Tom **stated no one is sick or has traveled. That the house is not lived in** Phone #: ###-####//complete per description, minor interior improvements//
BLD20-00159 DOC - Permit Finaled4/3/20204/3/20204/3/2020 9:09:43 AMPPASS
BLD20-00467 BLD-Final4/2/20204/3/20204/3/2020 8:49:56 AMANR
Please call Darren one hour in advance if you would like him to be there for inspection. Thanks! Phone #: ###-#### Inspection requested via web by Sarah Schuller//need to have fire setback on east side approved, panels extend to the edge of the eave, plans show a 36" setback from eave for access//