BLD20-00381
| BLD-Wall Bracing | 5/27/2020 | 5/27/2020 | 5/27/2020 4:13:51 PM | P | PART |
|
|
Randy Phone #: ###-####//ok when nails added per discussion//
|
BLD16-01125
| BLD-Conference | 5/27/2020 | 5/27/2020 | 5/27/2020 3:01:10 PM | P | DONE |
|
|
owner stated project is in litigation with previous contractor//let supervisor know what is going on//
|
MIS20-00174
| BLD-Conference | 5/27/2020 | 5/27/2020 | 5/27/2020 2:56:59 PM | P | CANC |
|
|
not needed per Daryl
|
BLD20-00381
| BLD-Other | 5/27/2020 | 5/27/2020 | 5/27/2020 1:57:20 PM | P | PASS |
|
|
separation wall between units ok per plans//previously inspected prior to wall being stood in place//
|
BLD19-03873
| BLD-Final | 5/26/2020 | 5/27/2020 | 5/27/2020 1:56:47 PM | P | NR |
|
|
Eddie Phone #: ###-####//need city approved plans for final//need zoning final sign off//reviewed special inspection reports, missing special inspection for bolts and racking//let Eddie know he will be getting back with me//
|
BLD20-01494
| BLD-Framing/Rough-in | 5/27/2020 | 5/27/2020 | 5/27/2020 12:52:40 PM | P | PART |
|
|
Hoping for AM! Phone #: ###-#### Inspection requested via web by David Dexter//ok when all the screws have been installed per plans//they were adding the screws when I left//this inspections was of mechanical connections at existing truss tails//
|
BLD19-02700
| BLD-Conference | 4/29/2020 | 5/27/2020 | 5/27/2020 11:16:22 AM | A | DONE |
|
|
follow up on easement//###-####//Brandon//approved by council, waiting on signed resolution and ok from zoning//will follow up//
|
BLD19-03180
| BLD-Energy code compliance | 5/27/2020 | 5/27/2020 | 5/27/2020 11:14:43 AM | A | PART |
|
|
Inspection requested via web by Carl Funk//add hangers to area above stairs as discussed//add VB at areas discussed//add truss bracing//add r20 min inuslation in areas r19 was installed//framing that is different than plans is in accordance with engineers site walk though and accepted by him on the first eight units, same framing used on this unit//
|
BLD19-03181
| BLD-Energy code compliance | 5/27/2020 | 5/27/2020 | 5/27/2020 11:14:26 AM | A | PART |
|
|
Inspection requested via web by Carl Funk//add hangers to area above stairs as discussed//add VB at areas discussed//add truss bracing//add r20 min inuslation in areas r19 was installed//framing that is different than plans is in accordance with engineers site walk though and accepted by him on the first eight units, same framing used on this unit//
|
BLD19-03187
| BLD-Energy code compliance | 5/27/2020 | 5/27/2020 | 5/27/2020 11:14:11 AM | A | PART |
|
|
Inspection requested via web by Carl Funk//add hangers to area above stairs as discussed//add VB at areas discussed//add truss bracing//add r20 min inuslation in areas r19 was installed//framing that is different than plans is in accordance with engineers site walk though and accepted by him on the first eight units, same framing used on this unit//
|
BLD19-03188
| BLD-Energy code compliance | 5/27/2020 | 5/27/2020 | 5/27/2020 11:13:52 AM | A | PART |
|
|
Inspection requested via web by Carl Funk//add hangers to area above stairs as discussed//add VB at areas discussed//add truss bracing//add r20 min inuslation in areas r19 was installed//framing that is different than plans is in accordance with engineers site walk though and accepted by him on the first eight units, same framing used on this unit//
|
BLD20-00337
| BLD-Footing | 5/26/2020 | 5/27/2020 | 5/27/2020 10:09:22 AM | A | PART |
|
|
asked for between 9-11 if possible // Jason Phone #: ###-####//more area A footings for gym//footing sizes ok per plans//pending all special inspections//
|
BLD19-01221
| BLD-Energy code compliance | 5/26/2020 | 5/27/2020 | 5/27/2020 9:33:51 AM | A | PASS |
|
|
screened // Dave Phone #: ###-####//shear was previously inspected, just not noted//energy ok//deck framinng ok per plans//
|