BLD19-00497
| BLD-Aging Inspection | 6/13/2019 | 6/13/2019 | 6/14/2019 9:42:54 AM | | DONE |
|
|
needs mechanical permit and inspection for final occupancy.
|
BLD18-03837
| BLD-Aging Inspection | 6/13/2019 | 6/13/2019 | 6/14/2019 8:37:37 AM | | NR |
|
|
waiting for final inspection. //not ready as of 06/14/2019//
|
BLD19-01923
| BLD-Framing/Rough-in | 6/13/2019 | 6/13/2019 | 6/13/2019 3:52:27 PM | P | PASS |
|
|
Bret 1.480.798.0255 for access//egress windows installed per plans// discussed requirements for window wells//will need ladder//
|
MIS18-00198
| MIS-Aging Inspection | 6/13/2019 | 6/13/2019 | 6/13/2019 3:49:21 PM | | DONE |
|
|
5/29/2018 5/29/2018 5/29/2018 P PASS DetailsTom Saunders closing permit...no work has been done on hot tub...no electrical
|
BLD18-02788
| BLD-Aging Inspection | 6/13/2019 | 6/13/2019 | 6/13/2019 3:48:00 PM | | DONE |
|
|
Expires: 07/28/19
|
MIS18-00206
| MIS-Aging Inspection | 6/13/2019 | 6/13/2019 | 6/13/2019 3:20:57 PM | | DONE |
|
|
plumbing and electrical//no strutural listed on permit or activity.//
|
BLD19-00833
| BLD-Framing/Rough-in | 6/13/2019 | 6/13/2019 | 6/13/2019 3:03:09 PM | P | FAIL |
|
|
Kii Phone #: ###-####//fill hole under tub in East bathroom//truss bracing and hanger nailing see circled areas on truss plans.//provide engineering for damaged and/or site built jack truss in master// call for re-inspection.//
|
BLD18-00172
| BLD-Footing | 6/11/2019 | 6/13/2019 | 6/13/2019 2:05:26 PM | P | PART |
|
|
Jana Phone #: ###-####//south stair cover only// holes per engineering// setbacks at 5'//
|
BLD19-01891
| BLD-Wall Bracing | 6/13/2019 | 6/13/2019 | 6/13/2019 1:11:09 PM | P | PART |
|
|
Kaleb Phone #: ###-####//add blocking at braced locations. nail all edges at blocking.//
|
BLD19-00754
| BLD-Footing | 6/13/2019 | 6/13/2019 | 6/13/2019 12:35:20 PM | P | PART |
|
|
as early as possible // Jim Phone #: ###-####//setbacks, getting surveyed point installed prior to wall inspection.// rebar installed in footings// work in progress.//
|
BLD18-02416
| BLD - Request for Extension | 6/13/2019 | 6/13/2019 | 6/13/2019 12:01:34 PM | P | PASS |
|
|
Project nearing completion. I just need a few more weeks to wrap up the fireplace and get insulation in to be ready for final inspection. Requesting one month extension. Phone #: ###-#### Inspection requested via web by Tyler Stewart//Talked with Tyler and granted extension.//
|
BLD18-02416
| BLD - Resubmittal Approved | 6/12/2019 | 6/13/2019 | 6/13/2019 11:58:05 AM | A | CANC |
|
|
Project nearing completion. I just need a few more weeks to wrap up the fireplace and get insulation in to be ready for final inspection. Requesting one month extension. Phone #: ###-#### Inspection requested via web by Tyler Stewart
|
BLD19-01584
| BLD-Foundation | 6/13/2019 | 6/13/2019 | 6/13/2019 10:29:00 AM | P | PASS |
|
|
work in progress//rebar installed per plans.//
|
BLD19-01584
| BLD-Wall Bracing | 6/12/2019 | 6/13/2019 | 6/13/2019 10:27:09 AM | A | CANC |
|
|
late morning 11 // Willie Phone #: ###-####
|
BLD15-01171
| BLD-Framing/Rough-in | 6/12/2019 | 6/13/2019 | 6/13/2019 10:06:29 AM | A | PASS |
|
|
Dan Phone #: ###-####//corrections made// framing ok per plans.//call for energy inspection.//
|
BLD18-03484
| BLD-Final | 6/12/2019 | 6/13/2019 | 6/13/2019 9:25:01 AM | A | PASS |
|
|
Bill Phone #: ###-####//ok per approved plans//
|