BLD18-03121
| BLD-Framing/Rough-in | 6/25/2019 | 6/25/2019 | 6/25/2019 4:11:46 PM | P | FAIL |
|
|
bill Phone #: ###-####//see corrections list onsite with Bill//call for re-inspection//
|
BLD19-01431
| BLD-Wall Bracing | 6/25/2019 | 6/25/2019 | 6/25/2019 3:04:17 PM | P | PASS |
|
|
Kerry Phone #: ###-####//nailing and bracing ok per plans//
|
BLD19-01434
| BLD-Foundation | 6/25/2019 | 6/25/2019 | 6/25/2019 1:44:06 PM | P | PASS |
|
|
|
BLD19-01686
| BLD-Foundation | 6/25/2019 | 6/25/2019 | 6/25/2019 1:43:52 PM | P | PASS |
|
|
|
BLD19-01434
| BLD-Wall Bracing | 6/25/2019 | 6/25/2019 | 6/25/2019 1:42:37 PM | P | CANC |
|
|
Mark Phone #: ###-####
|
BLD19-01686
| BLD-Wall Bracing | 6/25/2019 | 6/25/2019 | 6/25/2019 1:42:26 PM | P | CANC |
|
|
Mark Phone #: ###-####
|
BLD19-02046
| BLD-Final | 6/25/2019 | 6/25/2019 | 6/25/2019 1:04:03 PM | P | PASS |
|
|
TIM Phone #: ###-####//correcitons made//final is complete//
|
BLD19-02046
| DOC - Permit Finaled | 6/25/2019 | 6/25/2019 | 6/25/2019 1:03:39 PM | P | PASS |
|
|
|
BLD19-00682
| BLD-Final | 6/25/2019 | 6/25/2019 | 6/25/2019 12:25:06 PM | P | PASS |
|
|
john Phone #: ###-####//final complete per plans//
|
BLD19-00245
| BLD-Final | 6/25/2019 | 6/25/2019 | 6/25/2019 11:52:44 AM | P | PASS |
|
|
Rescheduled with mechanical finalized. Phone #: ###-#### Inspection requested via web by James McGuire///HVAC final complete//final complete per plans// CC issued//
|
BLD19-00245
| DOC - Permit Finaled | 6/25/2019 | 6/25/2019 | 6/25/2019 11:52:05 AM | P | PASS |
|
|
|
BLD19-00245
| BLD-Conference | 6/25/2019 | 6/25/2019 | 6/25/2019 11:50:56 AM | P | CANC |
|
|
Rescheduled with mechanical finalized. Phone #: ###-#### Inspection requested via web by James McGuire
|
BLD19-00245
| BLD-Conference | 6/24/2019 | 6/25/2019 | 6/25/2019 11:49:17 AM | P | CANC |
|
|
Rescheduled with mechanical finalized. Phone #: ###-#### Inspection requested via web by James McGuire
|
BLD19-02226
| BLD-Footing | 6/25/2019 | 6/25/2019 | 6/25/2019 11:42:14 AM | P | FAIL |
|
|
Tim Phone #: ###-####//correction notice//footing/foundation needs to extend 24" below grade for frost depth//
|
BLD19-00943
| BLD-Energy code compliance | 6/24/2019 | 6/25/2019 | 6/25/2019 10:49:14 AM | A | PASS |
|
|
Phone #: ###-#### Inspection requested via web by Justin Hone
|
BLD18-04321
| BLD-Foundation | 6/24/2019 | 6/25/2019 | 6/25/2019 10:21:47 AM | A | PASS |
|
|
Greg- foundation wall inspection Phone #: ###-####//foundation ok per plans//
|
BLD19-01643
| BLD-Footing | 6/21/2019 | 6/25/2019 | 6/25/2019 9:46:21 AM | A | PASS |
|
|
Jim Phone #: ###-####//footings ok per plans///pending special inspections as reported on the special inspections statement with the plans located onsite...//called Jim and let him know...///
|
BLD19-01062
| BLD-Footing | 6/24/2019 | 6/25/2019 | 6/25/2019 8:55:16 AM | A | PART |
|
|
Thank you! Phone #: ###-#### Inspection requested via web by Candyce Moss//work in progress.......
|
MIS18-00297
| MIS-Aging Inspection | 6/25/2019 | 6/25/2019 | 6/25/2019 8:12:09 AM | | DONE |
|
|
PLM-Conference 8/6/2018 8/7/2018 8/7/2018 A PASS DetailsDan Ediger Met with the tenant. A new direct vent water heater was installed by Idaho Energy Solutions. Bill spoke to contractor and directed t pull a permit.
|
BLD18-02896
| BLD-Aging Inspection | 6/25/2019 | 6/25/2019 | 6/25/2019 8:10:07 AM | | DONE |
|
|
Expires: 08/10/19
|