Inspections for the day of: Wednesday, June 3, 2020.
Number of inspections: 19
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTell Riley
TitleBLD-COM/RES INSPECTOR
Phone #830-2752
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD19-02609 BLD-Aging Inspection6/3/20206/3/20206/4/2020 7:11:11 AM PEND
BLD19-02583 BLD-Aging Inspection6/3/20206/3/20206/4/2020 7:10:55 AM PEND
BLD19-00535 BLD-Framing/Rough-in6/3/20206/3/20206/4/2020 7:10:26 AMPCANC
BLD20-00230 BLD-Wall Bracing6/3/20206/3/20206/3/2020 3:22:59 PMPNR
Phone #: ###-#### Inspection requested via web by Andy Thompson//need approved plans onsite//will re-schedule//
BLD20-00906 BLD-Conference6/3/20206/3/20206/3/2020 3:14:52 PMPPART
screened // Aaron Phone #: ###-####//shear inspeciton completed as well//roof ok//walls ok--add hot dip nails if pt plate requires hot dip otherwise ok//
BLD19-04013 BLD-Wall cover6/3/20206/3/20206/3/2020 2:24:42 PMPPART
screened // Matt Phone #: ###-####//3rd set of 2nd floor units for pre-rock areas//need to fire caulk areas discussed//looked at gyp on first 4 units--need to extend down walls on rated wall side and exterior walls, or provide detail from architect//
MIS20-00157 BLD-Conference5/20/20206/3/20206/3/2020 1:10:45 PMPCANC
10 day follow up//3rd correction notice posted//no permit has bee obtained for roof//someone was onsite but didnt answer door when i knocked//notice to obtain permit in 5 days or notice of violation will be issed//
MIS20-00183 BLD-Conference6/3/20206/3/20206/3/2020 12:38:15 PMPDONE
work/demo without permit Phone #: ###-####//CN issued to obtain permits for demo and or construction//talked with GC onsite, detailed partial roof collapse from 2017//advised to obtain demo permit asap//follow up in 10 days//
BLD20-00599 BLD-Final6/2/20206/3/20206/3/2020 12:20:32 PMAPASS
Please call Sid ###-#### Phone #: ###-#### Inspection requested via web by Carissa Mattison//inspections complete for project//occupancy permit required prior to occupancy of suite//
BLD20-00599 DOC - Permit Finaled6/3/20206/3/20206/3/2020 12:19:39 PMPPASS
BLD20-00522 BLD-Final6/2/20206/3/20206/3/2020 12:19:22 PMAPASS
Please call Sid ###-#### Phone #: ###-#### Inspection requested via web by Carissa Mattison//inspection requirements complete for vanilla//will need occupancy certificate prior to occupancy//
BLD20-00522 DOC - Permit Finaled6/3/20206/3/20206/3/2020 12:18:41 PMPPASS
BLD19-00535 BLD-Framing/Rough-in6/2/20206/3/20206/3/2020 11:48:36 AMACANC
Inspection of truss bracing and plate fastening/HD''s Phone #: ###-#### Inspection requested via web by Travis Blackburn
BLD19-04013 BLD-Wall cover6/2/20206/3/20206/3/2020 11:04:42 AMACANC
screened // Matt Phone #: ###-####//moved to pm//no one onsite//
BLD20-00337 BLD-Foundation6/2/20206/3/20206/3/2020 10:26:33 AMAPART
screened - Chase Phone #: ###-####//continued foundation area A//appears ok//pend all specials//
BLD20-00337 BLD-Footing6/2/20206/3/20206/3/2020 10:26:00 AMAPART
screened - Chase Phone #: ###-####//contiued footings area A//appears to be ok//pend specials//
BLD20-00219 BLD-Framing/Rough-in6/2/20206/3/20206/3/2020 9:53:26 AMAFAIL
Phone #: ###-#### Inspection requested via web by Ted Perry//cn left onsite with contracor//see details for framing//add nails and a35s for shear per plan//need alt design for stairs and landing as they do not reflect plans//
BLD18-01837 BLD-Final6/2/20206/3/20206/3/2020 9:24:14 AMANR
after 830 if possible // Darwin Phone #: ###-####//let owner know, electrical needs finaled//need to contact plan reviewer to remove requirement for mechanical s no mechanical was don per the owner//will let me know and re-schedule//
BLD19-04946 BLD-Framing/Rough-in6/2/20206/3/20206/3/2020 9:23:12 AMAPART
cody Phone #: ###-####//need to add header over door per engineering//need insulation values specified and installed//all trades to face mount on rated walls/ceilings//need plumbing approval prior to cover//