Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD19-02413 BLD-Aging Inspection6/5/20206/5/20206/8/2020 11:54:23 AM PEND
no inspections requested
MIS18-00257 MIS-Aging Inspection6/5/20206/5/20206/8/2020 11:53:46 AM DONE
no activity
BLD18-01140 BLD-Aging Inspection6/5/20206/5/20206/8/2020 11:52:46 AM PEND
BLD19-00535 BLD-Framing/Rough-in6/5/20206/5/20206/5/2020 3:11:51 PMPPART
Sturctural inspection on trusses and hardware. Would also like to look at riser room on A to insulate and rock Phone #: ###-#### Inspection requested via web by Travis Blackburn//add scab to C3G trusses per truss docs//other trusses ok//
BLD20-01341 BLD-Footing6/4/20206/5/20206/5/2020 2:45:19 PMPPART
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo aggregate constru //WIP//pins set to measure 2' setback per the plat//met Ricardo and measured earlier today--crew will set strings at 2' setback for foundation inspection to confirm setbacks//
BLD20-01340 BLD-Footing6/4/20206/5/20206/5/2020 2:45:04 PMPPART
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo aggregate constru //WIP//pins set to measure 2' setback per the plat//met Ricardo and measured earlier today--crew will set strings at 2' setback for foundation inspection to confirm setbacks//
BLD20-01339 BLD-Footing6/4/20206/5/20206/5/2020 2:44:49 PMPPART
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo aggregate constru //WIP//pins set to measure 2' setback per the plat//met Ricardo and measured earlier today--crew will set strings at 2' setback for foundation inspection to confirm setbacks//
BLD20-01279 BLD-Footing6/4/20206/5/20206/5/2020 2:44:31 PMPPART
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo aggregate constru //WIP//pins set to measure 2' setback per the plat//met Ricardo and measured earlier today--crew will set strings at 2' setback for foundation inspection to confirm setbacks//
BLD20-01361 BLD-Conference6/4/20206/5/20206/5/2020 2:44:15 PMPPART
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo //WIP//pins set to measure 2' setback per the plat//met Ricardo and measured earlier today--crew will set strings at 2' setback for foundation inspection to confirm setbacks//
BLD20-01360 BLD-Footing6/4/20206/5/20206/5/2020 2:43:58 PMPPART
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo //WIP//pins set to measure 2' setback per the plat//met Ricardo and measured earlier today--crew will set strings at 2' setback for foundation inspection to confirm setbacks//
BLD20-01359 BLD-Footing6/4/20206/5/20206/5/2020 2:43:43 PMPPART
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo //WIP//pins set to measure 2' setback per the plat//met Ricardo and measured earlier today--crew will set strings at 2' setback for foundation inspection to confirm setbacks//
BLD20-01358 BLD-Footing6/4/20206/5/20206/5/2020 2:43:25 PMPPART
Phone #: 2089109404 >> Inspection requested via mobile web by Ricardo //WIP//pins set to measure 2' setback per the plat//met Ricardo and measured earlier today--crew will set strings at 2' setback for foundation inspection to confirm setbacks//
BLD19-00526 BLD-Framing/Rough-in6/5/20206/5/20206/5/2020 2:29:17 PMPPART
Riser room approval for cover Phone #: ###-#### Inspection requested via web by Travis Blackburn//plans show 2x4 framing with R21 insulation--need architect to clarify//
BLD20-01282 BLD-Footing6/5/20206/5/20206/5/2020 12:23:36 PMPFAIL
Pat Phone #: ###-####//west side setback measures 4'-plans show 5'//talked with Sue at zoning 5' setback on new constrution needs to be maintained//will provide change to plan review//
BLD20-01715 BLD-Framing/Rough-in6/4/20206/5/20206/5/2020 11:11:53 AMAPART
Late AM inspection requested if at all possible please. Footing inspection requested simultaneously. Phone #: ###-#### Inspection requested via web by David Dexter//a35s and a34s installed//
BLD20-01715 BLD-Footing6/4/20206/5/20206/5/2020 11:11:26 AMAPART
Late AM inspection requested if at all possible please. Phone #: ###-#### Inspection requested via web by David Dexter//ok per plans when holes are cleaned out//
BLD20-00337 BLD-Footing6/4/20206/5/20206/5/2020 10:10:27 AMAPART
screened // Chase Phone #: ###-####//area B footings-partial//ok eonding all special inspection approvals//
BLD20-01397 BLD-Foundation6/4/20206/5/20206/5/2020 10:10:26 AMAPART
stem- Dustin *screened* Phone #: ###-####//WIP-still installing rebar in wall//setbacks still appear to be ok based on front pin being in line with existing fence//
BLD19-02700 BLD-Conference5/27/20206/5/20206/4/2020 7:11:42 AMACANC
follow up on easement// Brandon ###-####//