Inspections for the day of: Friday, July 12, 2019.
Number of inspections: 24
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTell Riley
TitleBLD-COM/RES INSPECTOR
Phone #830-2752
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD19-02367 BLD-Final7/11/20197/12/20197/12/2019 4:01:37 PMPPASS
Inspection requested via web by BRS Permitting//ok per plans//electrical final complete//
BLD19-02367 DOC - Permit Finaled7/12/20197/12/20197/12/2019 4:00:57 PMPPASS
BLD18-04337 BLD-Final7/10/20197/12/20197/12/2019 3:59:01 PMPNR
Mac Phone #: ###-####//need blower door test completed and results posted//
BLD19-00556 BLD-Footing7/12/20197/12/20197/12/2019 3:21:24 PMPFAIL
need to string easment line for canal//NE corner of house will be on easment line//call for re-inspection//
BLD19-00556 BLD-Conference7/12/20197/12/20197/12/2019 3:19:32 PMPCANC
damion Phone #: ###-####
BLD19-02086 BLD-Final7/11/20197/12/20197/12/2019 2:48:51 PMPPASS
Phone #: ###-#### Inspection requested via web by Michael La Pointe//roof appears to be installed within code requirements//
BLD19-02086 DOC - Permit Finaled7/12/20197/12/20197/12/2019 2:48:20 PMPPASS
BLD19-01724 BLD-Foundation7/12/20197/12/20197/12/2019 2:36:58 PMPPASS
Jerry- foundation wall Phone #: ###-####
BLD19-01806 BLD-Foundation7/12/20197/12/20197/12/2019 2:08:10 PMPCANC
Jerry- foundation wall Phone #: ###-####
BLD19-01154 BLD-Wall Bracing7/12/20197/12/20197/12/2019 1:52:38 PMPFAIL
shear // shawn Phone #: ###-####//correction notice posted//finish portal frame// verify portal frame over windows//add blocking per plans//
BLD19-02258 BLD-Footing7/12/20197/12/20197/12/2019 12:48:06 PMPPASS
Brian Phone #: ###-####//setbacks per approved plans//tight on 3' garage side//verify 3' at wall inspection//
BLD19-00228 BLD-Framing/Rough-in7/11/20197/12/20197/12/2019 11:44:44 AMAPASS
Tell we have all the other inspector coming also to sign off on hv/ac and plumbing rough in. Maybe give me a call before your arrival. Phone #: ###-#### Inspection requested via web by Russell Valline//rough ins all passed//ok to cover framing//
BLD18-03121 BLD-Framing/Rough-in7/11/20197/12/20197/12/2019 11:05:12 AMAPASS
Matt Phone #: ###-####//corrections made//rough-ins passed//105,106,205,206,305,306//
BLD19-01620 BLD-Final7/11/20197/12/20197/12/2019 10:29:33 AMAPASS
Phone #: ###-#### Inspection requested via web by Michael La Pointe//previously passed//maybe wasnt Fast Finaled??//roof complete//
BLD19-01620 DOC - Permit Finaled7/12/20197/12/20197/12/2019 10:28:50 AMPPASS
BLD19-01856 BLD-Footing7/10/20197/12/20197/12/2019 10:22:34 AMAPART
Structural inspection on rebar in swimming pool in back yard. Plans and permits are on site and in a PVC pipe secured to T post near pool. Phone #: ###-#### Inspection requested via web by Brandy McConkey//maintain rebar clearances per plans///Dobies on side near house fell in//re-attach//
BLD19-01431 BLD-Framing/Rough-in7/12/20197/12/20197/12/2019 10:04:14 AMAPART
Add hangers to jack trusses in front room on small hip//ok to insulate
BLD19-01431 BLD-Energy code compliance7/11/20197/12/20197/12/2019 10:02:16 AMACANC
vinnie Phone #: ###-####
BLD19-01694 BLD-Footing7/11/20197/12/20197/12/2019 9:30:43 AMAPASS
Phone #: 2086971241 >> Inspection requested via mobile web by Heron//set back issues corrected//
BLD19-00244 BLD-Blower Door Test Results7/12/20197/12/20197/12/2019 9:30:09 AMADONE
4.01 ACH 50
1280cfm @ 50 pa
BLD19-00244 BLD-Final7/11/20197/12/20197/12/2019 9:28:38 AMAPASS
Willie Phone #: ###-####//corrections made//
BLD19-00244 DOC - Permit Finaled7/12/20197/12/20197/12/2019 9:28:15 AMPPASS
BLD19-00839 BLD-Energy code compliance7/11/20197/12/20197/12/2019 8:55:57 AMAPASS
Phone #: ###-#### Inspection requested via web by Aron Mock
BLD19-00125 BLD-Framing/Rough-in7/11/20197/12/20197/12/2019 8:46:22 AMAFAIL
Vaugh Phone #: ###-####//add straps per plans//HDU anchors need 5" in concrete//need truss plans//correction notice posted..//