Inspections for the day of: Monday, July 6, 2020.
Number of inspections: 28
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
InspectorTell Riley
TitleBLD-COM/RES INSPECTOR
Phone #830-2752
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
MIS19-00014 MIS-Aging Inspection7/6/20207/6/20207/7/2020 7:34:02 AM PEND
BLD20-01289 BLD-Framing/Rough-in7/6/20207/6/20207/6/2020 4:57:01 PMPPASS
Phone #: ###-#### Inspection requested via web by Joel Hirtle//add truss bracing//ok to insulate//
BLD20-01287 BLD-Framing/Rough-in7/6/20207/6/20207/6/2020 4:56:28 PMPPART
Phone #: ###-#### Inspection requested via web by Joel Hirtle//add truss bracing, provide engineering for drilled floor truss//add truss blocking//ok to insulate//
BLD20-01286 BLD-Framing/Rough-in7/6/20207/6/20207/6/2020 4:55:37 PMPPASS
Phone #: ###-#### Inspection requested via web by Joel Hirtle
BLD20-01283 BLD-Framing/Rough-in7/6/20207/6/20207/6/2020 4:55:19 PMPPASS
Phone #: ###-#### Inspection requested via web by Joel Hirtle//add truss brace, ok to insulate//
BLD19-02703 BLD-Final7/6/20207/6/20207/6/2020 4:41:35 PMPPART
Kyle Phone #: ###-####//project appears to be completed per the drawing and scope//railings/guards installed in locations required on plans//need special inspection report for complete final//
BLD20-01281 BLD-Wall Bracing7/5/20207/6/20207/6/2020 3:32:09 PMPPASS
Phone #: ###-#### Inspection requested via web by Joel Hirtle
BLD20-01278 BLD-Wall Bracing7/5/20207/6/20207/6/2020 3:31:52 PMPPASS
Phone #: ###-#### Inspection requested via web by Joel Hirtle
BLD20-01341 BLD-Wall Bracing7/5/20207/6/20207/6/2020 3:20:53 PMPPASS
Phone #: ###-#### Inspection requested via web by Joel Hirtle
BLD20-01340 BLD-Wall Bracing7/6/20207/6/20207/6/2020 3:20:41 PMPPASS
BLD20-01339 BLD-Wall Bracing7/5/20207/6/20207/6/2020 3:20:29 PMPPASS
Phone #: ###-#### Inspection requested via web by Joel Hirtle
BLD20-01279 BLD-Wall Bracing7/5/20207/6/20207/6/2020 3:20:17 PMPPASS
Phone #: ###-#### Inspection requested via web by Joel Hirtle
BLD20-01361 BLD-Wall Bracing7/5/20207/6/20207/6/2020 3:20:03 PMPPASS
Phone #: ###-#### Inspection requested via web by Joel Hirtle
BLD20-01360 BLD-Wall Bracing7/5/20207/6/20207/6/2020 3:19:49 PMPPASS
Phone #: ###-#### Inspection requested via web by Joel Hirtle
BLD20-01359 BLD-Wall Bracing7/5/20207/6/20207/6/2020 3:19:36 PMPPASS
Phone #: ###-#### Inspection requested via web by Joel Hirtle
BLD20-01358 BLD-Wall Bracing7/5/20207/6/20207/6/2020 3:19:21 PMPPASS
Phone #: ###-#### Inspection requested via web by Joel Hirtle
BLD19-04013 BLD-Framing/Rough-in7/6/20207/6/20207/6/2020 1:46:24 PMPFAIL
SCREENED // Matt Phone #: ###-####//2nd six units still need corridor fire wall to meet listing on plans//3rd six units correction notice issued for framing corrections, see Matt onsite for list--also corridor fire wall on these six units needs to meet listing on plans//
BLD20-02090 BLD-Final7/2/20207/6/20207/6/2020 12:41:45 PMADONE
Inspection on a completed asphalt re-roof project Phone #: ###-#### Inspection requested via web by Michael La Pointe
BLD20-02090 DOC - Permit Finaled7/6/20207/6/20207/6/2020 12:41:35 PMPPASS
roof appears to be completed within code requirements//new roof flashing around vents were installed//no access to back//
BLD19-03873 BLD-Final7/6/20207/6/20207/6/2020 12:40:22 PMPPASS
screened // Ed Phone #: ###-####//no inspection card to sign//information requested was provided--special inspection report for psot installed anchors/ plans via drop box//zoning approval and other inspection requirements hav been completed//final is complete per the scope of project//
BLD19-03923 BLD-Final7/2/20207/6/20207/6/2020 12:25:23 PMPCANC
Phone #: ###-#### >> Inspection requested via web by Ron Ramza Inspection cancelled from web by: Ron Ramza
BLD20-00640 BLD-Framing/Rough-in7/2/20207/6/20207/6/2020 11:52:15 AMAFAIL
Jack Phone #: ###-####//correction notice issued for framing corrections//see structural details on plans for areas marked in red that need to be completed//
BLD19-02986 BLD-Final7/2/20207/6/20207/6/2020 11:52:14 AMACANC
Gate on Ridenbaugh will be open Phone #: ###-#### Inspection requested via web by Edward Cavey//let contact know zoning sign off is needed//discussed possible virtual inspection for final as home is occupied//
BLD20-00704 BLD-Energy code compliance7/6/20207/6/20207/6/2020 10:01:25 AMAPASS
ok when insulation is installed back in areas that were opened up//
BLD20-00704 BLD-Framing/Rough-in7/2/20207/6/20207/6/2020 10:00:39 AMAPASS
Phone #: ###-#### Inspection requested via web by Kelly Stover
BLD20-00857 BLD-Final7/2/20207/6/20207/6/2020 9:50:42 AMACANC
Call prior to going Phone #: 2088905010 >> Inspection requested via mobile web by Myles//moved to 7/7/20 per contractor//
BLD20-01248 BLD-Footing7/2/20207/6/20207/6/2020 9:31:05 AMAPART
Dustin *screened* Phone #: ###-####//WIP//will need to sleeve waste line through footer//
BLD20-00376 BLD-Other7/2/20207/6/20207/6/2020 12:00:00 AMACANC
pour at 11 rebar // Jay Phone #: ###-####