Inspections for the day of: Wednesday, August 7, 2019.
Number of inspections: 21
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorTell Riley
TitleBLD-COM/RES INSPECTOR
Phone #830-2752
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD19-00362 BLD-Other8/6/20198/7/20198/7/2019 3:55:48 PMPPART
roof sheeting // Jeff Phone #: ###-####//area b roof sheathing//
BLD19-00362 BLD-Footing8/6/20198/7/20198/7/2019 3:53:41 PMPPART
rebar and vapor barrier concrete // Jeff Phone #: ###-####//slab vapor barrier ok pending specials//
BLD19-01686 BLD-Wall Bracing8/7/20198/7/20198/7/2019 3:02:00 PMPPASS
Mark- Phone #: ###-####3
MIS19-00236 BLD-Conference8/7/20198/7/20198/7/2019 3:00:03 PMPDONE
Home owner contacted me and verified shed does not require a permit. He verified with zoning that no issues were existing. No violations exist at this time.
MIS19-00236 DOC - Permit Finaled8/7/20198/7/20198/7/2019 2:58:51 PMPPASS
BLD19-02382 BLD-Footing8/7/20198/7/20198/7/2019 2:22:08 PMPPASS
Sergio Phone #: ###-####
BLD19-00228 BLD-Ceiling Grid Inspection8/7/20198/7/20198/7/2019 1:35:44 PMPPASS
Please give me a call if you cant make it by 3:00 Phone #: ###-#### Inspection requested via web by Russell Valline//trades passed for grid cover//grid ok per plans//
BLD19-00228 BLD-Other8/7/20198/7/20198/7/2019 1:34:26 PMPDONE
Please give me a call if you cant make it by 3:00 Phone #: ###-#### Inspection requested via web by Russell Valline
MIS19-00236 BLD-Conference8/7/20198/7/20198/7/2019 12:25:37 PMPDONE
possible addition being done without permits//shed being built next to home//talked with owner about setbacks and separation//advised to call permit counter//will check back 2 weeks//
BLD19-01778 BLD-Final8/6/20198/7/20198/7/2019 11:21:53 AMAPASS
Mandy Phone #: ###-####//demo has been completed and new development work has begun//
BLD19-01778 DOC - Permit Finaled8/7/20198/7/20198/7/2019 11:21:19 AMPPASS
BLD19-02226 BLD-Framing/Rough-in8/6/20198/7/20198/7/2019 11:03:17 AMAPASS
Tim Phone #: ###-####//electrical passed//framing ok//
BLD19-02544 BLD-Framing/Rough-in8/6/20198/7/20198/7/2019 10:47:08 AMAPASS
John Phone #: ###-####//framing ok per plans//one doorway framed in//
BLD19-02174 BLD-Framing/Rough-in8/6/20198/7/20198/7/2019 9:53:16 AMAPASS
Tayler Phone #: ###-####//framing ok when anchor bolts and mechanical connections are complete at pier pads//window in stairwell will need to be safety glazed prior to final inspection//
BLD17-03117 DOC - Permit Finaled8/7/20198/7/20198/7/2019 9:28:14 AMPPASS
BLD15-00572 BLD-Final8/6/20198/7/20198/7/2019 9:20:05 AMAPASS
BLD15-00922 is for new construction of home and finaled. This demo permit has not been finaled yet. //demo was complete and new home installed and finaled//
BLD15-00572 DOC - Permit Finaled8/7/20198/7/20198/7/2019 9:19:39 AMPPASS
BLD19-02291 BLD-Footing8/6/20198/7/20198/7/2019 9:11:55 AMAPASS
Mark Phone #: ###-####//property lines have been pinned and setbacks are ok per approved plans//footings installed per plans//
BLD19-01687 BLD-Framing/Rough-in8/6/20198/7/20198/7/2019 8:45:25 AMAPASS
Fred Meyers, work area is nearest the garden center entrance. Phone #: ###-#### Inspection requested via web by Clifford Butler//electrical is existing,all new electrical will be mounted on finish wall//wall framing ok per plans//
MIS18-00385 MIS-Aging Inspection8/7/20198/7/20198/7/2019 8:23:59 AM PASS
See previous inspection completed by jim Sly
BLD19-00912 BLD-Aging Inspection8/7/20198/7/20198/7/2019 8:23:01 AM PASS
Expires: 09/22/19