Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
BLD19-03244 BLD-Framing/Rough-in9/6/20199/9/20199/10/2019 8:01:51 AMPCANC
Contact is Brian Prussia. Thanks! Phone #: ###-#### Inspection requested via web by BRS Permitting
MIS19-00130 BLD-Conference9/9/20199/9/20199/9/2019 3:43:43 PMPDONE
late pm // working continued without permit Phone #: ###-####-George ###-#### would like a call before you head that way so he can meet you.//two awnings both are 9x16 and structurally independant from each other or the home//
MIS19-00130 DOC - Permit Finaled9/9/20199/9/20199/9/2019 3:42:52 PMPPASS
BLD19-01888 BLD-Framing/Rough-in9/6/20199/9/20199/9/2019 3:42:27 PMPNR
If no one there, there is a lock box by the back door with a key in it for back door. Code is 1957 Phone #: ###-#### Inspection requested via web by Loren Dahl//call in for mechanical inspection and have completed--then call for re-inspection//
BLD19-01380 BLD-Foundation9/7/20199/9/20199/9/2019 3:26:12 PMPPART
Phone #: ###-#### Inspection requested via web by Braden Holbrook//WIP///
BLD19-02593 BLD-Wall Bracing9/9/20199/9/20199/9/2019 3:03:03 PMPPART
Party wall inspection. Please call Nic a half hour before inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic Van Diepen//party wall construciton ok per plans//
BLD19-02592 BLD-Wall Bracing9/9/20199/9/20199/9/2019 3:02:36 PMPPART
Party wall inspection. Please call Nic a half hour before inspection. Thanks, Phone #: ###-#### Inspection requested via web by Nic Van Diepen//party wall construction ok per plans//
BLD19-02383 BLD-Wall Bracing9/9/20199/9/20199/9/2019 2:23:32 PMPFAIL
Phone #: ###-#### Inspection requested via web by James Jackson//nail portal frame 3" oc per plans//add straps, add washers and nuts to portal frame//nail all holddowns//add shear blocking//discussed onsite//call for re-inspection//
BLD19-03142 BLD-Framing/Rough-in9/5/20199/9/20199/9/2019 1:58:11 PMPPASS
Phone #: ###-#### Inspection requested via web by Kirsten Dallmann//wall cover only for dance room an practice rooms//
BLD18-04157 BLD-Blower Door Test Results9/9/20199/9/20199/9/2019 1:31:05 PMPDONE
4.2 ACH 50
1114 cfm @ 50 pa
BLD18-04157 BLD-Final9/9/20199/9/20199/9/2019 1:29:37 PMPFAIL
Phone #: ###-#### Inspection requested via web by Scott Asin//add pipe bollard//insulate crawl access door//seal penetrations in garage wall//awning over front door is not installed//correction issued//
BLD19-01279 BLD-Framing/Rough-in9/9/20199/9/20199/9/2019 12:33:46 PMPPASS
wITNEY Phone #: ###-####//per plans//
BLD19-03104 BLD-Final9/9/20199/9/20199/9/2019 12:01:41 PMPPASS
Roof appears to be installed within code requirements//
BLD19-03104 DOC - Permit Finaled9/9/20199/9/20199/9/2019 12:01:11 PMPPASS
BLD19-03411 BLD-Final9/8/20199/9/20199/9/2019 11:29:29 AMAPASS
Phone #: ###-#### Inspection requested via web by Steve Confalone//roof appears to be installed within code requirements//
BLD19-03411 DOC - Permit Finaled9/9/20199/9/20199/9/2019 11:29:03 AMPPASS
BLD18-03863 BLD-Final9/6/20199/9/20199/9/2019 11:07:37 AMAFAIL
Call ahead for garage code // Vince Phone #: ###-####//need blower door test completed//
BLD18-03822 BLD-Final9/6/20199/9/20199/9/2019 11:07:13 AMAFAIL
Call ahead for garage code // Vince Phone #: ###-####//need blower door test completed//
BLD19-02803 BLD-Final9/5/20199/9/20199/9/2019 10:39:16 AMPPASS
Phone #: ###-#### Inspection requested via web by Michael La Pointe///roof appears to be installed within code requirements//
BLD19-02803 DOC - Permit Finaled9/9/20199/9/20199/9/2019 10:38:52 AMPPASS
BLD18-03928 BLD-Final9/6/20199/9/20199/9/2019 10:26:07 AMAPASS
Vince Phone #: ###-####
BLD18-03928 DOC - Permit Finaled9/9/20199/9/20199/9/2019 10:25:50 AMPPASS
BLD19-03104 BLD-Final9/9/20199/9/20199/9/2019 9:44:30 AMPCANC
Inspection requested via web by Ira Rutledge
BLD18-01756 BLD-Blower Door Test Results9/9/20199/9/20199/9/2019 9:43:08 AMPDONE
duplex

4.49 ACH 50
1001 cfm @ 50 pa

4.34 ACH 50
934 cfm @ 50 pa
BLD19-02174 BLD-Final9/6/20199/9/20199/9/2019 9:41:06 AMAPASS
tAILOR Phone #: ###-####//corrections made//final complete//
BLD19-02174 DOC - Permit Finaled9/9/20199/9/20199/9/2019 9:40:39 AMPPASS
BLD18-01756 BLD-Final9/6/20199/9/20199/9/2019 9:15:51 AMAPASS
Barb Phone #: ###-####//corrections made//
BLD18-01756 DOC - Permit Finaled9/9/20199/9/20199/9/2019 9:15:30 AMPPASS
BLD19-02794 BLD-Final9/5/20199/9/20199/9/2019 8:39:04 AMAPASS
Phone #: ###-#### Inspection requested via web by Michael La Pointe//roof appears to be installed within code requirements//
BLD19-02794 DOC - Permit Finaled9/9/20199/9/20199/9/2019 8:38:30 AMPPASS
MIS16-00058 MIS-Aging Inspection9/9/20199/9/20199/9/2019 8:04:24 AM DONE
BLD permit was issued in 2016.
MIS16-00058 DOC - Permit Finaled9/9/20199/9/20199/9/2019 8:03:56 AMPPASS