Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC17-01126 General Inspection1/24/20201/27/20201/31/2020 1:11:34 PMPPEND
No discharges. More clean up needed, site needs to dry out.
ESC19-00292 General Inspection1/27/20201/27/20201/28/2020 5:05:26 PMPFAIL
Observed a visible plume at the outfall of the receiving storm drain east of 2nd street on Myrtle.
Notified RP to clean up Myrtle and 2nd asap and install additional sediment control BMPs and frequent clean up
ESC17-01104 General Inspection1/27/20201/27/20201/28/2020 12:26:57 PM CANC
ESC19-00324 General Inspection1/27/20201/27/20201/27/2020 4:24:23 PMPFAIL
Corrections needed:

- clean up captured mud behind gravel gutter check bags
- do maintenance on DI bags
- need to install slope diversion berm on lots above the retention pond along Warm Springs.
- need to repair retention berm that has broke on the inside of the curve. Add addional controls.

Will coordinate onsite meeting with Granite to plan corrections after Track Utilities has completed work at the site.
ESC19-00926 Site Final1/27/20201/27/20201/27/2020 4:10:21 PMPPASS
Project is located behind a gated area. Call me if you would like access to the site. Project is complete. Phone #: ###-#### Inspection requested via web by Eldon Oyadomari
ESC18-01535 Site Final1/27/20201/27/20201/27/2020 4:07:55 PMPPASS
Multiple substations locations throughout Boise. All complete. Call me if you would like to review the locations. Phone #: ###-#### Inspection requested via web by Eldon Oyadomari
ESC18-00251 Aging Inspection1/27/20201/27/20201/27/2020 4:07:17 PM CANC
ESC19-00797 Conference1/27/20201/27/20201/27/2020 3:59:49 PMPDONE
Notified by Anne w/ Micron that this project has not yet been started nor completed, but is still being planned for 2020
ESC18-00251 Site Final1/27/20201/27/20201/27/2020 3:58:42 PMPPASS
Project complete. No ESC requests. Stormwater management to be monitored by Micron environmental compliance team.
ESC18-01005 Site Final1/27/20201/27/20201/27/2020 3:58:31 PMPPASS
Project complete. No ESC requests. Stormwater management to be monitored by Micron environmental compliance team.
ESC19-00584 General Inspection1/27/20201/27/20201/27/2020 3:32:04 PMPFAIL
Trackout at Hope's Well. Dumping dirt in very muddy area, construction entrance is compacted.

Request to extend rock to dumping zone or block off.
ESC19-01312 Site Final1/27/20201/27/20201/27/2020 2:07:16 PMPPASS
Project complete. Call me if you would like to meet at the site. Phone #: ###-#### Inspection requested via web by Eldon Oyadomari
ESC19-01706 Site Preparation1/27/20201/27/20201/27/2020 1:49:52 PMPPASS
WIP on site development. Permit sign posted. Using existing paved access. No trackout at time of inspection. Storm drains on Boise have sediment protection
ESC18-01615 Site Final1/27/20201/27/20201/27/2020 1:47:07 PMPPASS
Demo phase complete. Subdivision development now active under ESC19-01706 for Latigo Place.
ESC17-00018 General Inspection1/27/20201/27/20201/27/2020 1:46:23 PM PASS
ESC18-00893 General Inspection1/27/20201/27/20201/27/2020 1:35:26 PM CANC
ESC18-00164 General Inspection1/27/20201/27/20201/27/2020 12:12:36 PMPPART
No trackout. No offsite discharges to MS4. Stockpile has been temporarily tackified. Post rainfall inspection conducted this morning by Granite.

Corrections needed:
- need to repare areas of silt fence that are no longer trenched and conduct maintenance One section has let mud slip under. Clean up and reinstall requested - noted in site's self inspection as well.
- up slope controls needed where water was able to run down slope - will discuss with RP for possible correction alternatives. Appears a diversion berm was graded on the lower terrace this morning.

Follow up pending
ESC20-00066 Site Preparation1/27/20201/27/20201/27/2020 11:07:05 AMPPASS
Modular building. No trackout, no activity at time of inspection. Muddy condition around building. Storm drains on Kennedy have sediment bags installed.
ESC19-01028 Site Final1/24/20201/27/20201/27/2020 11:05:38 AMAPASS
Steve Phone #: ###-####

Work complete. No temporary BMPs on site. DI bags at south end of Kennedy are for ESC20-00066
ESC18-01312 Aging Inspection1/27/20201/27/20201/27/2020 9:53:36 AM PASS
BLD finaled, no ESC issues. Permit closed
ESC18-01312 DOC - Permit Finaled1/27/20201/27/20201/27/2020 9:53:21 AMPPASS
ESC18-00164 General Inspection1/27/20201/27/20201/27/2020 8:29:01 AMPCANC
ESC18-00106 Aging Inspection1/27/20201/27/20201/27/2020 8:27:46 AM DONE
Permit closed. No exterior disurbance. No construciton activity on BLD permit since 2018
ESC18-00106 DOC - Permit Finaled1/27/20201/27/20201/27/2020 8:27:06 AMPPASS
ESC18-01106 Aging Inspection1/27/20201/27/20201/27/2020 8:25:41 AM PASS
WIP on structure. Access via alley. No issues
ESC18-01053 General Inspection1/27/20201/27/20201/27/2020 8:14:06 AM CANC