Inspections for the day of: Tuesday, October 10, 2017.
Number of inspections: 17
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC16-00435 General Inspection10/10/201710/10/201710/12/2017 4:19:21 PM CANC
ESC17-00774 General Inspection9/28/201710/10/201710/12/2017 4:17:58 PMAPEND
WIP on installing TRM and ECBs on channel. No violations observed in staging areas. Water leaving creeek area is clear. Will check back on installation specs for TRM/ECBSs
ESC16-01742 Site Final10/5/201710/10/201710/12/2017 10:27:25 AMAPASS
Demo complete. No sediment or material leaving site. Site prepped for new SFHs. No ESC corrections.
MIS17-00334 ESC-Conference10/5/201710/10/201710/12/2017 8:17:54 AMPPEND
ESC permit to be obtained with GRD retaining wall permit and hillside review. BLD inspector also issued warning.
ESC16-01290 DOC - Permit Finaled10/10/201710/10/201710/10/2017 3:26:13 PMPPASS
ESC16-01289 DOC - Permit Finaled10/10/201710/10/201710/10/2017 3:25:48 PMPPASS
ESC16-01288 DOC - Permit Finaled10/10/201710/10/201710/10/2017 3:25:31 PMPPASS
ESC16-00878 Aging Inspection10/10/201710/10/201710/10/2017 3:22:09 PM CANC
ESC16-01081 Aging Inspection10/10/201710/10/201710/10/2017 3:21:31 PM CANC
ESC16-00970 Aging Inspection10/10/201710/10/201710/10/2017 3:21:16 PM PASS
ESC16-01607 General Inspection10/10/201710/10/201710/10/2017 3:21:04 PM CANC
ESC16-01606 General Inspection10/10/201710/10/201710/10/2017 3:20:57 PM CANC
ESC16-01605 General Inspection10/10/201710/10/201710/10/2017 3:20:52 PM CANC
ESC15-00762 General Inspection10/10/201710/10/201710/10/2017 3:20:09 PM PASS
ESC17-00404 Complaint Inspection10/10/201710/10/201710/10/2017 12:10:05 PMPPART
No trackout or discharges. Trash containment onsite is being used.

Correction requests:
- clean gutter and change out DI bag
- provide temporary dust control/water truck for drive road to staging area as well as stockpile.
- once stockpile is removed; initiate temporary or permanent stabilization. RP stated will do hydroseed or fiber mulch.
ESC17-00011 General Inspection10/10/201710/10/201710/10/2017 12:09:30 PMPPART
No trackout or discharges. Trash containment onsite is being used.

Correction requests:
- clean gutter and change out DI bag
- provide temporary dust control/water truck for drive road to staging area as well as stockpile.
- once stockpile is removed; initiate temporary or permanent stabilization. RP stated will do hydroseed or fiber mulch.
ESC17-00138 Conference10/9/201710/10/201710/10/2017 11:40:02 AMPPASS
Jeremy ###-####

Preconstruction conference with Biltmore RP at site. Grading to begin within 2-3 weeks, permit not yet issued.

Will install heavy duty construction entrance on Owyhee @ SW corner of parcel. Fiber mat protection on two storm drains on Pasadena and 1 DI bag on Owyhee. Fugitive dust control and water truck must be onsite with designated driver. Okay to wait on perimeter controls after initial grading begins.

CGP filed, eNOI tracking # IDR1000B2. Post SWPPP info and Boise ESC permit sign.