ESC17-01104
| General Inspection | 10/25/2019 | 10/25/2019 | 10/29/2019 3:08:08 PM | | CANC |
|
|
|
ESC19-00780
| General Inspection | 10/25/2019 | 10/25/2019 | 10/25/2019 12:18:14 PM | P | PEND |
|
|
Met with RP-GC Ken.
Corrective actions to occur: - install wattle around stockpiles along 5th street sidewalk. Will need to be weighed down in areas where staking is not possible. - install wattle at low point between sidewalk and alley (NW corner of lot) to treat runoff flowing to the Sherman street gutter - install snake bag check dam on Sherman gutter - clean Sherman gutter - if stockpiles can not be backfill by end on November, will need to cover with tarps.
|
ESC19-00444
| General Inspection | 10/25/2019 | 10/25/2019 | 10/25/2019 12:14:55 PM | P | PEND |
|
|
No washout on site for pump truck at site. Request to RP to have a washout built. RP had on site foreman begin to build a washout containment as I was on site. Will follow up Monday.
|
ESC19-00372
| General Inspection | 10/25/2019 | 10/25/2019 | 10/25/2019 12:13:28 PM | P | PASS |
|
|
|
ESC19-01120
| General Inspection | 10/25/2019 | 10/25/2019 | 10/25/2019 12:13:12 PM | P | PASS |
|
|
No activity. Permit posted, BMPs installed. No dirt on street/gutter
|
ESC18-00164
| Complaint Inspection | 10/25/2019 | 10/25/2019 | 10/25/2019 11:28:45 AM | P | PASS |
|
|
dust complaint
No dust at time of inspection. Spoke with onsite crew manager Alfredo about keeping dust down. Water truck is coming to site so work can continue on the lower swale adjacent to homes below. No major activity, finishing up sewer work,
No trackout or discharges.Silt fence BMP installed at bottom of site. Graded slope has been tracked:
Corrections: - stockpile has been on site for over a month, much of it is inactive and past stabillization deadline. - need to have graded areas hydroseeded before end of November
|
ESC18-01238
| Site Final | 10/24/2019 | 10/25/2019 | 10/25/2019 9:55:39 AM | A | PASS |
|
|
Construction complete. No disturbed area, no temporary BMPs left on site.
|
ESC17-01196
| General Inspection | 10/25/2019 | 10/25/2019 | 10/25/2019 9:51:20 AM | | CANC |
|
|
rescheduled for site final
|
ESC18-01645
| Aging Inspection | 10/25/2019 | 10/25/2019 | 10/25/2019 9:47:13 AM | | CANC |
|
|
|
ESC18-01178
| Site Final | 10/24/2019 | 10/25/2019 | 10/25/2019 8:30:38 AM | P | NR |
|
|
need to pull storm drain sediment bags downhill from site
|
ESC18-00171
| General Inspection | 10/25/2019 | 10/25/2019 | 10/25/2019 8:22:39 AM | | CANC |
|
|
rescheduled
|