ESC16-00430
| Tracking Control | 10/26/2016 | 10/27/2016 | 10/28/2016 2:03:49 PM | A | CANC |
|
|
|
ESC16-00208
| General Inspection | 10/27/2016 | 10/27/2016 | 10/27/2016 5:02:38 PM | | PASS |
|
|
|
ESC16-01457
| Site Preparation | 10/27/2016 | 10/27/2016 | 10/27/2016 3:19:05 PM | P | PEND |
|
|
Approved for ESC related construction to stabilize new drivewaet material base and upper wall. Homeowner to install sediment controls (ie: wattle) and erosion control blanket material as well as further compaction of road and road mix
Work to occur this weekend, will re-inspect next week
|
ESC16-00938
| General Inspection | 10/27/2016 | 10/27/2016 | 10/27/2016 1:53:30 PM | P | PASS |
|
|
WIP on large landscaping project at hillside home. No trackout from access road to Strata Via. No materials or staging on Table Rock. Sediment controls wattles installed at bottom of slope to prevent runoff to Strata Via, MS4 has inlet protection. No corrections requested.
|
ESC16-01317
| Site Preparation | 10/27/2016 | 10/27/2016 | 10/27/2016 12:44:54 PM | P | PASS |
|
|
David Phone #: ###-####
BMPs installed; utilities and earthwork already completed under ESC15-00976 for main Idaho Street Townhomes project.
Approved for construction. 9 permits open, only 4 starting at this time..
|
ESC16-01318
| Site Preparation | 10/27/2016 | 10/27/2016 | 10/27/2016 12:44:38 PM | P | PASS |
|
|
David Phone #: ###-####
BMPs installed; utilities and earthwork already completed under ESC15-00976 for main Idaho Street Townhomes project.
Approved for construction. 9 permits open, only 4 starting at this time..
|
ESC16-01324
| Site Preparation | 10/27/2016 | 10/27/2016 | 10/27/2016 12:44:06 PM | P | PASS |
|
|
David Phone #: ###-####
BMPs installed; utilities and earthwork already completed under ESC15-00976 for main Idaho Street Townhomes project.
Approved for construction. 9 permits open, only 4 starting at this time..
|
ESC16-01319
| Site Preparation | 10/27/2016 | 10/27/2016 | 10/27/2016 12:43:40 PM | P | PASS |
|
|
David Phone #: ###-####
BMPs installed; utilities and earthwork already completed under ESC15-00976 for main Idaho Street Townhomes project.
Approved for construction. 9 permits open, only 4 starting at this time..
|
ESC16-01320
| Site Preparation | 10/27/2016 | 10/27/2016 | 10/27/2016 12:43:28 PM | P | PASS |
|
|
David Phone #: ###-####
BMPs installed; utilities and earthwork already completed under ESC15-00976 for main Idaho Street Townhomes project.
Approved for construction. 9 permits open, only 4 starting at this time..
|
ESC16-01321
| Site Preparation | 10/27/2016 | 10/27/2016 | 10/27/2016 12:43:15 PM | P | PASS |
|
|
David Phone #: ###-####
BMPs installed; utilities and earthwork already completed under ESC15-00976 for main Idaho Street Townhomes project.
Approved for construction. 9 permits open, only 4 starting at this time..
|
ESC16-01322
| Site Preparation | 10/27/2016 | 10/27/2016 | 10/27/2016 12:43:00 PM | P | PASS |
|
|
David Phone #: ###-####
BMPs installed; utilities and earthwork already completed under ESC15-00976 for main Idaho Street Townhomes project.
Approved for construction. 9 permits open, only 4 starting at this time..
|
ESC16-01325
| Site Preparation | 10/27/2016 | 10/27/2016 | 10/27/2016 12:42:44 PM | P | PASS |
|
|
David Phone #: ###-####
BMPs installed; utilities and earthwork already completed under ESC15-00976 for main Idaho Street Townhomes project.
Approved for construction. 9 permits open, only 4 starting at this time..
|
ESC16-01323
| Site Preparation | 10/27/2016 | 10/27/2016 | 10/27/2016 12:42:30 PM | P | PASS |
|
|
David Phone #: ###-####
BMPs installed; utilities and earthwork already completed under ESC15-00976 for main Idaho Street Townhomes project.
Approved for construction. 9 permits open, only 4 starting at this time..
|
ESC15-00976
| Conference | 10/27/2016 | 10/27/2016 | 10/27/2016 12:41:18 PM | P | PASS |
|
|
4 of 9 new Idaho Street Townhomes are to start. Onsite meeting for 9 new ESC permits for each parcel.
Wattles installed at east end of project. DI bag to be reinstall on Main Street at 17th. Concrete washout containment provided. See also site preps for ESC16-01317 to ESC16-01325
|
ESC15-00731
| General Inspection | 10/27/2016 | 10/27/2016 | 10/27/2016 11:22:43 AM | | CANC |
|
|
|
ESC16-00554
| General Inspection | 10/27/2016 | 10/27/2016 | 10/27/2016 11:20:33 AM | | CANC |
|
|
|
ESC16-00557
| General Inspection | 10/27/2016 | 10/27/2016 | 10/27/2016 11:13:00 AM | | CANC |
|
|
rescheduled to 9/2
|
ESC16-00556
| General Inspection | 10/27/2016 | 10/27/2016 | 10/27/2016 11:07:11 AM | | CANC |
|
|
rescheduled for 10/31
|
ESC16-01342
| General Inspection | 10/27/2016 | 10/27/2016 | 10/27/2016 11:06:29 AM | P | PASS |
|
|
Silt fence installed at bottom of site for perimeter control. No signiificant trackout, no sediment runoff occuring. Permit sign posted. WIP
|
ESC15-01288
| General Inspection | 10/27/2016 | 10/27/2016 | 10/27/2016 11:05:24 AM | P | PEND |
|
|
No change since prior inspection. Need to schedule repair and stabiliztion at lower end of drainage in sub near Warm Springs. No new issues...corrections pending.
|
ESC16-01229
| General Inspection | 10/27/2016 | 10/27/2016 | 10/27/2016 11:04:16 AM | P | PASS |
|
|
Staging area for Greenbelt re-surfacing project has been dismantled and rock entrance removed. Some minor work remaining. No corrections requested.
|
ESC16-00181
| DOC - Permit Finaled | 10/27/2016 | 10/27/2016 | 10/27/2016 10:59:46 AM | P | PASS |
|
|
Park Place unit complete. All permits finaled, no corrections needed.
|
ESC16-00143
| DOC - Permit Finaled | 10/27/2016 | 10/27/2016 | 10/27/2016 10:43:18 AM | P | PASS |
|
|
|
ESC15-01624
| Aging Inspection | 10/27/2016 | 10/27/2016 | 10/27/2016 10:22:06 AM | | PASS |
|
|
BLVD townhome complete and landscaped. Temp BMPs to remain during active construction of other units. No ESC corrections needed.
|
ESC15-01624
| DOC - Permit Finaled | 10/27/2016 | 10/27/2016 | 10/27/2016 10:21:30 AM | P | PASS |
|
|
|
ESC16-00319
| General Inspection | 10/27/2016 | 10/27/2016 | 10/27/2016 10:12:15 AM | | CANC |
|
|
|
ESC16-00257
| Aging Inspection | 10/27/2016 | 10/27/2016 | 10/27/2016 10:05:52 AM | | DEFR |
|
|
No issues observed by BLD inspector. No MS4 in area, vegetated buffer around construction
|
ESC16-00540
| Aging Inspection | 10/27/2016 | 10/27/2016 | 10/27/2016 10:03:59 AM | | CANC |
|
|
|
ESC16-00417
| Aging Inspection | 10/27/2016 | 10/27/2016 | 10/27/2016 10:03:36 AM | | CANC |
|
|
|
ESC16-00540
| DOC - Permit Finaled | 10/27/2016 | 10/27/2016 | 10/27/2016 9:59:26 AM | P | PASS |
|
|
pool complete within vegetated/established backyard
|
ESC16-00539
| Aging Inspection | 10/27/2016 | 10/27/2016 | 10/27/2016 9:52:26 AM | | CANC |
|
|
|
ESC16-00568
| General Inspection | 10/27/2016 | 10/27/2016 | 10/27/2016 9:47:10 AM | | CANC |
|
|
|
ESC16-01434
| Site Preparation | 10/20/2016 | 10/27/2016 | 10/27/2016 9:25:56 AM | P | PASS |
|
|
Permit sign posted. Initial BMPs installed. Existing hillsdie home with demo and addition/remodel. Silt fence at low corner is trenched in. Vegetation and retaining walls to be preserved. Work to begin next week. Approved.
|
ESC16-00311
| General Inspection | 10/27/2016 | 10/27/2016 | 10/27/2016 8:45:40 AM | | PASS |
|
|
|
ESC16-00312
| General Inspection | 10/27/2016 | 10/27/2016 | 10/27/2016 8:45:11 AM | | PASS |
|
|
|