PDS Online
Making
Boise
the most livable city in the country.
Home
Permits
Search by Permit Number
How to search by permit number
Search by Address
Search by Customer Number
Search by Current Planning Number
Search in Project by Permit Number
Search by Project Name
Inspections
Search by Permit Number
Search by Request Date
Search by Company Name
Fees
Impact Fees Estimate Calculator
Other Searches
Search for Licensed Contractors
Search Parcel by Address
Search Historical Surveys
Reports
Daily Reports
Weekly Reports
Monthly Reports
Home
/
Inspections
/
Inspector Activity
Inspections for the day of:
Wednesday, October 30, 2019
.
Number of inspections:
12
Percentage of inspections complete:
100 %
Percentage of inspections not complete:
0 %
Contact Information
Inspector
Andy J. Long
Title
EROSION INSPECTOR
Phone #
794-8996
Permit Number
Description
Received
Requested
Completed
AM/PM
Disposition
ESC18-01121
General Inspection
10/30/2019
10/30/2019
11/1/2019 3:49:19 PM
PASS
ESC18-01667
General Inspection
10/30/2019
10/30/2019
10/30/2019 4:26:05 PM
P
PASS
Vertical construction in progress. No trackout, no fugitive dust, no discharges observed.
ESC19-00351
General Inspection
10/30/2019
10/30/2019
10/30/2019 4:25:19 PM
P
PASS
No activity. Site work complete. Storm drains has sediment protection. No trash or debris left behind. SW corner has perimeter sediment control wattle installed.
ESC19-00910
Site Preparation
10/30/2019
10/30/2019
10/30/2019 4:21:05 PM
P
PASS
Perimter sediment control wattles are installed, rock construction entrance and trackpad installed on south boundary.
Grading crew has water truck on site for any dust control needed. For now, will wait to see where stormwater flows to see if we should install inlet protection at allumbaugh and whisperwood roundabout.
Plan is to use ecopan washouts for concrete washout, and to get paving done after foundation and prior to going vertical.
RP Ben onsite, provide ESC permit signs for posted. Issued warning/reminder regarding scheduling ESC site preparation inspections at start of project.
ESC17-00847
Site Final
10/30/2019
10/30/2019
10/30/2019 3:52:10 PM
P
NR
on site contact: Jeremy Smith ###-####
Need to pull 3 temporary DI bags (Fairview & 25th, Fairview and 24th, and on the 24th street diagnol parking area)
ESC18-00429
Site Final
10/30/2019
10/30/2019
10/30/2019 3:36:47 PM
P
PASS
All temporary BMPs have been removed. Disturbed areas are stabilized. ESC permit finaled.
ESC17-01132
General Inspection
10/30/2019
10/30/2019
10/30/2019 3:27:35 PM
P
PASS
ESC18-01586
Aging Inspection
10/30/2019
10/30/2019
10/30/2019 2:31:42 PM
PASS
WIP on digging out area underneath relocated home. No corrections at this time. No dirt on street.
ESC16-01457
General Inspection
10/30/2019
10/30/2019
10/30/2019 2:30:46 PM
PASS
No new activity. Grass seeded in upper areas has good growth. No material leaving site. BMPs installed.
ESC19-00041
General Inspection
10/30/2019
10/30/2019
10/30/2019 9:14:45 AM
CANC
rescheduled
ESC18-01227
General Inspection
10/30/2019
10/30/2019
10/30/2019 9:14:02 AM
CANC
ESC18-01310
Aging Inspection
10/30/2019
10/30/2019
10/30/2019 9:13:54 AM
CANC