ESC14-00719
| General Inspection | 10/5/2015 | 10/5/2015 | 10/5/2015 4:44:57 PM | | CANC |
|
|
rescheduled
|
ESC15-00016
| DOC - Permit Finaled | 10/5/2015 | 10/5/2015 | 10/5/2015 4:44:23 PM | P | PASS |
|
|
|
ESC15-00916
| General Inspection | 10/5/2015 | 10/5/2015 | 10/5/2015 4:25:19 PM | P | FAIL |
|
|
Some minor trackout to Cloverdale observed.
No permit sign posted, no SWPPP information posted, and no site prep or contact with ESC division has been conducted by contractor.
Corrections: - increase sweeping until Mt. Hood St. is paved - post City of Boise yellow ESC permit sign with contact information - post SWPPP information per CGP requirements
Called Nampa Paving to issue correction.
|
ESC15-00261
| General Inspection | 10/5/2015 | 10/5/2015 | 10/5/2015 4:15:50 PM | P | PASS |
|
|
WIP at Rocket Expresss Washout. No trackout to Cloverdale or Fairview. Site is utilizing staging area for material containment and concrete washout pit. Water truck is on site to help with dust and compaction. Approved.
|
ESC13-00924
| General Inspection | 10/5/2015 | 10/5/2015 | 10/5/2015 3:27:46 PM | | PASS |
|
|
All construction in Pine Tree Village is complete. Streets have been swept, garbage and construction materials collected, cleaned and removed. DI bags have been taken out of storm drains as previously requested.
ESC permit conditions satisfied. Permit finaled. No futher active ESC permits in Pine Tree Village.
|
ESC13-00924
| DOC - Permit Finaled | 10/5/2015 | 10/5/2015 | 10/5/2015 3:26:00 PM | P | PASS |
|
|
|
ESC15-00955
| General Inspection | 10/5/2015 | 10/5/2015 | 10/5/2015 3:18:30 PM | P | PASS |
|
|
Molenaar Park WIP. Permit posted at entrance, no significant trackout or fugitive dust observed. Water trucks are on site for dust control and construction entrance is installed. No issues observed and no complaints received recently. Approved
|
ESC12-01148
| Aging Inspection | 10/5/2015 | 10/5/2015 | 10/5/2015 3:17:00 PM | | PASS |
|
|
Long term project, no activity on BLD since February. Work not complete, but no further earthwork needed to finish. No activity at time of inspection and on prior inspections. Yard is small and vegetated with weeds, no sediment runoff. No further ESC inspections at this site under this permit, BLD still open
|
ESC12-01148
| DOC - Permit Finaled | 10/5/2015 | 10/5/2015 | 10/5/2015 3:07:05 PM | P | PASS |
|
|
|
ESC15-00923
| Tracking Control | 10/5/2015 | 10/5/2015 | 10/5/2015 2:55:49 PM | P | FAIL |
|
|
Loose sediment tracked out from site without regular site clean up and sweeping. Backyard was accessed from parcel behind home and tracked out Ardyce
Corrections:
Sweep up trackout and loose sediment on sidewalk, street, and gutter. Inform employees not to drive across open lots. Check DI bags for mainteance.
|
ESC15-01115
| Site Preparation | 10/5/2015 | 10/5/2015 | 10/5/2015 2:25:10 PM | P | PASS |
|
|
Brett Phone #: ###-####
Permit sign posted. CBH BMP installations in Dropzone Sub are adequate, active sites mostly clean. Approved to start.
|
ESC15-01116
| Site Preparation | 10/5/2015 | 10/5/2015 | 10/5/2015 2:24:54 PM | P | PASS |
|
|
Brett Phone #: ###-####
Permit sign posted. CBH BMP installations in Dropzone Sub are adequate, active sites mostly clean. Approved to start.
|
ESC12-00130
| General Inspection | 10/5/2015 | 10/5/2015 | 10/5/2015 1:57:10 PM | P | PASS |
|
|
Final landscaping WIP at west end of apartment complex. The apartments are now open and occupied. ACHD inspector assisted with removal of 2 DIs at south side of Royal and La Pointe (unclear on exact responsible party due to multiple projects) and reqeust /reminder issued to Mike Wilson of McAlvain to remove DI bags on north side or Royal in front of and to the east & west of project.
Will re-inspect for final once all work complete.
|
ESC15-00942
| Site Preparation | 10/5/2015 | 10/5/2015 | 10/5/2015 12:18:13 PM | P | PASS |
|
|
Note - ESC site walk through and conference initially conducted prior to permit issue...
WIP. Permit sign posted, water truck on site to control dust and for complaction. Very flat site - BMPs currently include stabilized entrance, DI bag on 13th & River St. and keeping exisiting sidewalks above grade of loose dirt with preservation of buffer as much as possible.
|
ESC14-01083
| General Inspection | 10/5/2015 | 10/5/2015 | 10/5/2015 11:18:12 AM | | PASS |
|
|
WIP on Park Place (MA Williams Park townhomes) at east end of development area. Site has perimeter chain link fence installed to contorl access and wind blown trash/material wrappings. SWPPP and permit information posted. Wattles installed at south side of project to protect drainage swale/wetland area
No trackout, storm drains have inlet bags installed, no spills or discharges observed. No concrete work currently but lined washout box is on site.
No corrections issued.
|
ESC15-00023
| General Inspection | 10/5/2015 | 10/5/2015 | 10/5/2015 11:09:19 AM | | PASS |
|
|
WIP on frame work. Workers parked on street, wattle installed but removed in area where workers are accessing site with equipment. No corrections, no recent complaints or issues. Still need to pay re-inspection fee prior Site Final.
|
ESC14-00989
| General Inspection | 10/5/2015 | 10/5/2015 | 10/5/2015 10:46:35 AM | | PASS |
|
|
WIP on foundation and site work. Excavation complete and distrubed area contained by existing curbing & paving, as well as perimeter wattles. No trackout, no discharges, and trash & materials contained. No corrections issued.
|
ESC12-00842
| Aging Inspection | 10/5/2015 | 10/5/2015 | 10/5/2015 10:04:42 AM | | PASS |
|
|
|
ESC15-00022
| General Inspection | 10/5/2015 | 10/5/2015 | 10/5/2015 9:47:40 AM | | PASS |
|
|
Project complete, distrubed area stabilized and materials cleaned up. ESC permit finaled.
|
ESC15-00022
| DOC - Permit Finaled | 10/5/2015 | 10/5/2015 | 10/5/2015 9:47:04 AM | P | PASS |
|
|
|
ESC15-00016
| General Inspection | 10/5/2015 | 10/5/2015 | 10/5/2015 8:43:42 AM | | PASS |
|
|
|