Inspections for the day of: Wednesday, November 2, 2016.
Number of inspections: 25
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC15-01138 General Inspection11/2/201611/2/201611/4/2016 2:33:41 PM CANC
rescheduled 11/8
ESC16-00319 General Inspection11/2/201611/2/201611/4/2016 2:33:08 PMPCANC
ESC14-00588 General Inspection11/2/201611/2/201611/4/2016 10:01:37 AM PASS
WIP on southeast portion of project. Frontage and swale are now landscaped. No trackout to Parkcenter. Trash and materials being contained. Unfinished areas of permeable pavers are protected. No corrections requested.
ESC16-01219 General Inspection10/31/201611/2/201611/3/2016 2:19:46 PMPCANC
ESC16-00557 General Inspection10/27/201611/2/201611/3/2016 2:19:22 PMACANC
rescheduled
ESC16-01308 General Inspection11/1/201611/2/201611/3/2016 2:18:55 PMACANC
ESC16-00088 General Inspection11/2/201611/2/201611/3/2016 2:18:42 PM CANC
ESC15-00468 General Inspection11/2/201611/2/201611/3/2016 2:18:35 PM CANC
ESC15-01483 General Inspection11/2/201611/2/201611/3/2016 10:20:35 AM PASS
WIP. Alley entrance now paved. No trackout or discharges. Some sweeping is needed on Bannock where a staging lane has been set up.

All inlets have sediment filter bags installed.
ESC15-00871 General Inspection11/2/201611/2/201611/3/2016 8:56:49 AM CANC
ESC16-00865 Site Preparation10/31/201611/2/201611/3/2016 8:54:25 AMPCANC
rescheduled
ESC16-01364 Site Preparation11/2/201611/2/201611/2/2016 2:32:43 PMPPASS
Just a question, do not see lot 71 in for esc inspections Inspection requested via web by Erby Gonzales

4 Plex Lot 71-74 approved for construction. Subdivision BMPs installed. RP onsite .
ESC16-01246 General Inspection10/31/201611/2/201611/2/2016 2:31:47 PMPCANC
ESC15-01308 General Inspection11/2/201611/2/201611/2/2016 2:31:39 PM CANC
ESC16-01348 Site Preparation11/1/201611/2/201611/2/2016 2:26:03 PMACANC
Saul ; Phone #: ###-####

rescheduled with GC
ESC16-00377 Aging Inspection11/2/201611/2/201611/2/2016 10:13:48 AM CANC
ESC15-01060 General Inspection11/2/201611/2/201611/2/2016 10:12:13 AM CANC
ESC16-00301 Aging Inspection11/2/201611/2/201611/2/2016 10:10:44 AM PASS
WIP. No violations observed.
ESC16-00237 Aging Inspection11/2/201611/2/201611/2/2016 10:10:24 AM CANC
rescheduled for site final 9/8
ESC16-00238 Aging Inspection11/2/201611/2/201611/2/2016 10:07:47 AM CANC
rescheduled for site final 9/8
ESC15-01420 General Inspection11/2/201611/2/201611/2/2016 10:04:36 AM CANC
ESC16-00203 Site Final11/2/201611/2/201611/2/2016 9:51:39 AMAPASS
Home complete, landscaped, and occupied. NO temp BMPs or construction materials remaining. All permits finaled.
ESC16-00525 Aging Inspection11/2/201611/2/201611/2/2016 9:46:40 AM PASS
WIP on home remodel. Access through paved alley way. No trackout. Front yard to Bannock undisturbed
GRD15-00078 GRD-Final11/1/201611/2/201611/2/2016 9:34:44 AMADEFR
Ray Phone #: ###-####

ESC permit finaled. Notified project is complete. Will forward to PW Drainage to see if they need final inspection.

No ESC corrections.
ESC16-00676 General Inspection10/19/201611/2/201611/2/2016 9:23:58 AMAPASS
WIP on grading, stormwater and utility work. No trackout or sediment runoff from site. Perimeter is clean, all receiving strorm drains have sediment filters installed. Street sweeper onsite. Site is in compliance.