ESC15-01050
| General Inspection | 11/16/2016 | 11/18/2016 | | A | |
|
|
drop off permit sign
|
ESC16-00414
| General Inspection | 11/21/2016 | 11/21/2016 | 11/23/2016 3:37:36 PM | | CANC |
|
|
|
ESC16-00435
| General Inspection | 11/21/2016 | 11/21/2016 | 11/23/2016 10:30:30 AM | | PART |
|
|
WIP. No trackout from site, no sediment runoff or dirt outside of silt fence perimeter. Permit sign and SWPPP info onsite.
Correction requests: - remove damaged section of silt fence on west boundary of fence (< 100 yards) - remove sagging fence sections in grass. Do not disturbe vegetation, will be adequate vegetative buffer. - need to pick up windblown trash around the site and perimter, as well as the parking lot across the street. Increase # of trash receptacles and train employees on proper disposal
|
ESC16-00384
| General Inspection | 11/21/2016 | 11/21/2016 | 11/23/2016 8:58:46 AM | | CANC |
|
|
|
ESC16-00759
| Site Preparation | 11/21/2016 | 11/21/2016 | 11/22/2016 2:24:46 PM | P | PASS |
|
|
John Phone #: ###-####
|
ESC15-01613
| General Inspection | 11/21/2016 | 11/21/2016 | 11/22/2016 11:47:26 AM | | PASS |
|
|
note: Phase III of Boise Centre Expansion to be covered under ESC16-01574.
|
ESC16-01410
| General Inspection | 11/21/2016 | 11/21/2016 | 11/21/2016 3:20:04 PM | A | PART |
|
|
ESC permit signs posted at bottom of hill in park and at 9th street staging area. No trackout, sediment runoff or other materials leaving work and staging area.
Silt fence installed be first rock wall of the chut stabilization project.
Corrections:
- install perimeter control at bottom of access road on back side. Need water bars or drainage to control to prevent concentrating runoff on the access road - provide erosion control wattle below new drainage outside of chute and/or mulch to cover the bare disturbed ground. - remove stockpiles off wire back fence along top of hill and/or install wattle along rim.
Notified RP via phone. No activity at time of inspection.
|
ESC16-00556
| General Inspection | 11/21/2016 | 11/21/2016 | 11/21/2016 1:49:07 PM | P | PASS |
|
|
WIP on South Fork subdivision grading. SWPPP information and City of Boise ESC sign posted at entrance on Chinook. No trackout or discharges to street. Silt fence perimeter installed on western limit of disturbance. Existing storm water swale protected. . No fugitive dust plumes observed or reported.
No corrections requested.
|
ESC16-00973
| General Inspection | 11/21/2016 | 11/21/2016 | 11/21/2016 1:16:49 PM | P | PASS |
|
|
WIP on new parking area. No trackout or discharges occuring. New onsite drainage has sediment protection. No corrections requested.
|
ESC15-00892
| Aging Inspection | 11/21/2016 | 11/21/2016 | 11/21/2016 1:06:54 PM | | CANC |
|
|
|
ESC16-01403
| General Inspection | 11/21/2016 | 11/21/2016 | 11/21/2016 1:04:39 PM | P | PASS |
|
|
WIP. Utility work in ROW now in progress. Will need to sweep road upon completion/stabilization. No MS4 in area. No fugitive dust issues observed. Approved.
|
ESC16-00744
| General Inspection | 11/21/2016 | 11/21/2016 | 11/21/2016 12:45:41 PM | P | PASS |
|
|
|
ESC16-00348
| General Inspection | 11/21/2016 | 11/21/2016 | 11/21/2016 12:42:47 PM | | PASS |
|
|
Site preparation inspection with RP Scott. RP to install straw along north border to keep sediment on site. Ground is mix of road mix and pavement, advised to weigh down wattles with sand bags to create seal. No MS4 protection requested. Approved for construction
|
ESC16-00655
| Site Preparation | 11/21/2016 | 11/21/2016 | 11/21/2016 12:41:00 PM | P | PASS |
|
|
Review ESC conditions and plan for cell phone tower work with RP Scott. Will install silt fence to protect onsite storm water swale. Approved for construction
|
ESC15-00688
| DOC - Permit Finaled | 11/21/2016 | 11/21/2016 | 11/21/2016 11:50:20 AM | P | PASS |
|
|
|
ESC15-00688
| Aging Inspection | 11/21/2016 | 11/21/2016 | 11/21/2016 11:49:46 AM | P | PASS |
|
|
|
ESC16-01354
| General Inspection | 11/21/2016 | 11/21/2016 | 11/21/2016 11:41:58 AM | P | PASS |
|
|
Perimeter sediment controls and trackout prevention access are installed. No discharges, trackout, or fugitve dust observed. RP onsite. Approved.
|
ESC15-00651
| Aging Inspection | 11/21/2016 | 11/21/2016 | 11/21/2016 10:07:52 AM | | CANC |
|
|
|
ESC16-00434
| General Inspection | 11/21/2016 | 11/21/2016 | 11/21/2016 10:04:42 AM | | CANC |
|
|
|
ESC16-00269
| Aging Inspection | 11/21/2016 | 11/21/2016 | 11/21/2016 10:04:34 AM | | CANC |
|
|
|
ESC14-01173
| Aging Inspection | 11/21/2016 | 11/21/2016 | 11/21/2016 10:04:22 AM | | CANC |
|
|
|
ESC13-01279
| General Inspection | 11/21/2016 | 11/21/2016 | 11/21/2016 10:04:10 AM | | CANC |
|
|
|
ESC16-01167
| Site Preparation | 11/21/2016 | 11/21/2016 | 11/21/2016 10:02:49 AM | A | PEND |
|
|
dewatering set up inspection
ESC permit sign posted. Shoring crew on site. No dewatering set or dewatering activity occuring. Sediment filter bags installed on receiving MS4 inlets. Lined concrete washout pit provided, no trackout, and permit sign posted at entrance.
VM left with RP Rock to provide update dewatering plan
|
ESC15-01118
| Aging Inspection | 11/21/2016 | 11/21/2016 | 11/21/2016 9:40:14 AM | | PASS |
|
|
Parking lot paved. WIP on interior. No sediment runoff or discharges. No activity at time of inspection.
|
ESC15-00142
| General Inspection | 11/21/2016 | 11/21/2016 | 11/21/2016 8:59:43 AM | | PASS |
|
|
WIP on interior and preparing base to install driveway pavers. No trackout issues, workers parked on street No construction acitivity on slope below retaining wall.
|