Inspections for the day of: Tuesday, November 21, 2017.
Number of inspections: 18
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC16-01475 Site Final11/17/201711/21/201711/22/2017 2:24:16 PMPPASS
Site landscaped, BLD finaled. No ESC corrections. 1 remaining home out of 4 on Melrose is still active, See ESC16-01479
ESC16-01478 Site Final11/17/201711/21/201711/22/2017 2:24:02 PMAPASS
Site landscaped, BLD finaled. No ESC corrections. 1 remaining home out of 4 on Melrose is still active, See ESC16-01479
MIS17-00396 ESC-Conference11/21/201711/21/201711/22/2017 9:40:48 AMPCANC
rescheduled
ESC17-00954 Random Inspection11/21/201711/21/201711/22/2017 8:38:21 AMPPASS
Temporary onsite stormwater retention basins have beeen constructed as requested. Rock entrance is still in good condition. Some minor trackout the first 10-20 yds down Winsome. Will need sweeping this week or early next week.
ESC16-01423 Aging Inspection11/21/201711/21/201711/21/2017 1:28:05 PM DONE
Demolition permit finaled. Need ESC permit for the minor land division. See MIS17-00397
MIS17-00397 ESC-Conference11/21/201711/21/201711/21/2017 1:27:09 PMPPEND
marmuth@hubblehomes
ESC16-01423 DOC - Permit Finaled11/21/201711/21/201711/21/2017 1:25:44 PMPPASS
ESC16-01423 Conference11/21/201711/21/201711/21/2017 1:25:21 PMPDONE
No work at site. Demolition complete, but no permit was obtained by Hubble Homes . This ESC permit finaled, see MIS17-00397 for follow up
ESC16-00159 General Inspection11/21/201711/21/201711/21/2017 1:12:56 PM CANC
ESC16-00437 General Inspection11/21/201711/21/201711/21/2017 1:12:44 PM CANC
ESC16-00436 General Inspection11/21/201711/21/201711/21/2017 1:12:38 PM CANC
ESC17-00842 Complaint Inspection11/21/201711/21/201711/21/2017 1:11:45 PMAPART
No significant evidence of excessive trackout or muddy discharge. No mud in gutters in front of homes as reported. Some sandy trackout does extend through the center of the road and around the concrete washout bin.

Corrections:
- street sweeper to visit Lancaster today or tomorrow.
- have crew with shovels and brooms clean up in the gutters where the new gutter will meet up with the old gutter. (due next week)
- empty concrete washout (due next week)
ESC16-01612 Site Final11/21/201711/21/201711/21/2017 12:10:02 PMANR
Not ready for final. Some onsite landscaping work still in progress. Dumpster, concrete washout, job trailer still onsite.

MS4 DI bags have been removed due to onsite stormwater retention and parking lot stabilization. Will check back for Site Final in December.
ESC15-00306 General Inspection11/16/201711/21/201711/21/2017 11:04:37 AMAPASS
In channel work for river bank repairs has started. Turbidimeter provided to monitor turbidity downstream from work areas and to test any visible plumes. Will use to document 404 monitoring requirements.

Meter provided yesterday 11/20 and setup by Inspector Zawacki.

Permit info posted, site has multiple RPs on duty.
ESC17-01132 Tracking Control11/21/201711/21/201711/21/2017 10:48:12 AMAPART
Trackout onto Jefferson. Round river rock access is plenty long and deep but is not scraping the tires adequately. Sweeeper has visited site this morning. Material is wet sand material and is sticking to tires. RP Chase on site.

Request for frequent sweeping until rock can be replaced or the new entrance installed. DI bag installed at Whitewater & Jefferson, receives runoff from dirty part of street.

Will check back tomorrow
- minimize and clean up trackout
- post green Boise ESC permit sign
- post proper CGP- SWPPP info.
ESC16-01603 General Inspection11/21/201711/21/201711/21/2017 8:03:29 AM CANC
ESC16-01432 General Inspection11/21/201711/21/201711/21/2017 8:03:15 AM PASS
Near completion, some final clean up and DI bag below needs to be reomved.
ESC16-01189 General Inspection11/17/201711/21/201711/20/2017 8:15:25 AMPCANC