Inspections for the day of: Wednesday, November 21, 2018.
Number of inspections: 23
Percentage of inspections complete: 83 %
Percentage of inspections not complete: 17 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC17-00791 General Inspection11/20/201811/20/2018   
ESC17-01289 General Inspection11/20/201811/20/2018   
ESC17-01749 General Inspection11/20/201811/20/2018   
ESC18-01252 Site Final11/16/201811/20/2018 P 
ESC16-01561 General Inspection11/21/201811/21/201811/27/2018 12:33:02 PM CANC
ESC18-01527 Site Preparation11/19/201811/21/201811/23/2018 2:37:45 PMAPEND
ESC18-01036 BMP Violation11/21/201811/21/201811/23/2018 1:52:44 PMPPASS
Slurry from curb cutting was thoroughly cleaned up and dried materials swept out of gutter. Culprit was A-core, who has equipment and machinery to prevent slurry runoff and dumpings.

Site now has valid RP and reviewed ESC permit rules for foothills SFH construction. RP to install wattle between project and occupied home to prevent sediment runoff over their retaining wall.

Note: site special investigation fee removed due to the slurry not being actual concrete washout and the prompt response to clean up and get in compliance. Will follow up on wattles next week.
ESC17-01473 General Inspection11/21/201811/21/201811/23/2018 8:26:00 AM CANC
ESC17-01595 BMP Violation11/21/201811/21/201811/21/2018 3:51:19 PMPPASS
Road swept. Silt fence containment installed properly. RP on duty, will sweep up after last load hauled off.
ESC18-00498 General Inspection11/21/201811/21/201811/21/2018 1:41:47 PMPPEND
New section of Chardie is paved and curb gutter and storm drains are installed.

ECBs and slope interupting wattles have been installed. Will need to check some areas where staking and non-overlapping wattles were observed and why some patches of slope did not get ECBs.

No discharges, trackout, or fugitive dust. RP on duty. Will schedule site conference for next week.
ESC18-01244 General Inspection11/21/201811/21/201811/21/2018 1:23:36 PMPPEND
WIP pouring foundation. Small washout for chutes, no washout pit for pump truck. Requested RP to check on conditions and do any clean up if pump truck dumped.
ESC18-00946 General Inspection11/21/201811/21/201811/21/2018 1:19:54 PMPPASS
No activity. No trackout or sediment runoff observed. Perimeter wattle installed properly as well geotextile gutter guards installed in the gutter. Permit sign posted.
ESC18-01036 BMP Violation11/21/201811/21/201811/21/2018 10:41:07 AMPFAIL
Uncontained concrete washout dumped on site. Curb cutting slurry in gutter and street without cleanup.

No site preparation inspection was requested by RP.

Special investigation fee and parcel hold issued.
ESC18-00906 DOC - Permit Finaled11/21/201811/21/201811/21/2018 10:34:32 AMPPASS
see ESC18-01036
ESC17-01445 Aging Inspection11/21/201811/21/201811/21/2018 8:13:27 AM CANC
ESC13-00806 General Inspection11/21/201811/21/201811/21/2018 8:13:01 AM CANC
ESC16-01253 General Inspection11/21/201811/21/201811/21/2018 8:06:33 AM CANC
ESC17-01630 Aging Inspection11/21/201811/21/201811/21/2018 7:53:54 AM DONE
see ESC17-00111 for remaining ESC inspections for Colson Place. Project is near completion.
ESC17-01630 DOC - Permit Finaled11/21/201811/21/201811/21/2018 7:53:32 AMPPASS
ESC17-01634 Aging Inspection11/21/201811/21/201811/21/2018 7:53:22 AM DONE
see ESC17-00111 for remaining ESC inspections for Colson Place. Project is near completion.
ESC17-01634 DOC - Permit Finaled11/21/201811/21/201811/21/2018 7:53:14 AMPPASS
ESC17-01633 Aging Inspection11/21/201811/21/201811/21/2018 7:52:57 AM DONE
see ESC17-00111 for remaining ESC inspections for Colson Place. Project is near completion.
ESC17-01633 DOC - Permit Finaled11/21/201811/21/201811/21/2018 7:52:07 AMPPASS