ESC18-01235
| Conference | 11/20/2019 | 11/21/2019 | 11/21/2019 2:15:46 PM | P | DONE |
|
|
Met with Joey with Northern Construction and reviewed previous correction requests.
Corrections completed: - loose trash around front and back of house and across the street has been picked up. - entrances are being prepped with road mix to begin paver installation. Will require workers to park on street if we weather happens prior to paver installation.
Corrections to complete: - install perimter wattle, 2 ft in from sidewalk to preserve this existing strip of weeds/grasses down to the southeast corner with J-hooks. Request 1-2" trench and stakes every 5 ft
- slope below home needs to be re-tracked and then wattles installed, and then hydroseeding is scheduled for the second week in December.
Notified that a pool permit will be pulled and he will have pool contractor obtain their own ESC permit.
Additional correction request: - sweep gutter today and tomorrow
follow up next week
|
ESC16-01472
| General Inspection | 11/21/2019 | 11/21/2019 | 11/21/2019 1:59:50 PM | | PASS |
|
|
No recent precipitation. No issues. Silt fences still installed on alley.
|
ESC18-00754
| General Inspection | 11/21/2019 | 11/21/2019 | 11/21/2019 11:49:02 AM | | PASS |
|
|
No new activity. Parcel owner still building home in subdivsion. Some material is staged there. No ESC requests. Will continue to monitor.
|
ESC18-00023
| General Inspection | 11/21/2019 | 11/21/2019 | 11/21/2019 8:17:31 AM | | CANC |
|
|
|