Inspections for the day of: Wednesday, November 22, 2017.
Number of inspections: 13
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC17-00078 General Inspection11/22/201711/22/201711/24/2017 1:17:25 PM CANC
ESC16-01108 General Inspection11/17/201711/22/201711/24/2017 8:00:53 AMAPEND
check for new wash out and some green signs posted.
ESC17-01088 Complaint Inspection11/22/201711/22/201711/24/2017 7:59:54 AMPPEND
extreme trackout reported.
ESC16-01604 General Inspection11/22/201711/22/201711/22/2017 4:16:33 PM CANC
ESC16-01479 General Inspection11/22/201711/22/201711/22/2017 4:16:22 PMPPASS
WIP on interior. Remove dumpster & sweep gutter upon completion. No corrections requested.
ESC17-01417 Site Preparation11/22/201711/22/201711/22/2017 2:21:10 PMPPASS
Grading has started for new Skywest concrete apron for airplane parking. BMPs installed include heavy duty construction entrance and sediment control wattles in barrow ditch leading to onsite retention swale.

RP onsite. Provided ESC permit signs to post at fence at end of construction entrance of Skywest parking lot
ESC17-00203 Random Inspection11/22/201711/22/201711/22/2017 2:18:41 PMPPASS
Consruction entrance has been improved. Muddy areas have been blocked off to prevent trackout. Elite is free of mud or gravel trackout.
ESC17-00021 Site Final11/17/201711/22/201711/22/2017 1:49:17 PMAPASS
Work complete. No disturbed area or loose materials. ESC conditions satisfied.
MIS17-00397 ESC-Conference11/21/201711/22/201711/22/2017 1:02:47 PMACANC
rescheduled
ESC17-00422 Tracking Control11/22/201711/22/201711/22/2017 1:02:07 PMAFAIL
Significant trackout to Canal and south bound Vista due to heavy dump truck traffic unloading foundation backfill. Original rock entrance is compacted too much and no lining was installed under rock.

Sweeper unit at work upon arrival, focusing on west bound Canal and southbound Vista. Lots of gravel and rocks kicked up on sidewalk on Vista.

Corrections issued to Tom with CM and Matt with Lurre.

- continue frequent sweeping until entrane can be correctly installed.
- install geotextilve lining and additional angular rock at entrance.
- install inlet sediment bag @ SW corner of Vista and Canal. NE corner has sediment bag already installed.

Follow up scheduled for Friday. 11/24
ESC17-00404 Complaint Inspection11/22/201711/22/201711/22/2017 11:46:08 AMAPEND
concern about the parcel west of Comfort Inn that has had stockpile removed will drain stormwater to residences.

Stockpile removal is complete. No stabilization initiated on this cleared area and is source of mud where vehicles are turning around.

Vegetative buffer exist between disturbed area and homes, site countours are similiar to pre-existring drainage pattern to the southwest corner of parcel.

Corrections:
- schedule date for stabililzation (hydromulch, tacifier, seed)
- prevent access to this area to stop mud trackout to Elder.
- clean up construction entrance to the staging yard and trackout on Elder to Comfort Inn.

Site paving,curbing and perimeter landscaping is complete. Stormwater from hotel parcel retained onsite.
ESC16-01551 Aging Inspection11/22/201711/22/201711/22/2017 8:36:33 AM PASS
ESC16-01551 DOC - Permit Finaled11/22/201711/22/201711/22/2017 8:36:28 AMPPASS