ESC15-00717
| Aging Inspection | 11/25/2015 | 11/25/2015 | 11/27/2015 11:01:04 AM | | PASS |
|
|
Construction complete. No loose sediment or materials at occupied and landscaped home. Permit finaled.
|
ESC15-01424
| Site Preparation | 11/25/2015 | 11/25/2015 | 11/25/2015 3:47:22 PM | P | PASS |
|
|
Brett Phone #: ###-####
Dunham Commons BMPs installed. Current CBH projects in compliance. Approved for construction
|
ESC15-01426
| Site Preparation | 11/25/2015 | 11/25/2015 | 11/25/2015 3:47:05 PM | P | PASS |
|
|
Brett Phone #: ###-####
Dunham Commons BMPs installed. Current CBH projects in compliance. Approved for construction.
|
ESC14-00356
| General Inspection | 11/25/2015 | 11/25/2015 | 11/25/2015 3:38:40 PM | | PASS |
|
|
WIP on interior. No trackout, no sediment leaving site.
|
ESC15-00722
| Aging Inspection | 11/25/2015 | 11/25/2015 | 11/25/2015 3:35:39 PM | | CANC |
|
|
|
ESC15-00142
| General Inspection | 11/25/2015 | 11/25/2015 | 11/25/2015 2:35:03 PM | | PASS |
|
|
Framing now in progress. Earthwork and concrete work is complete. No trackout. No erosion issues currently below installed retaining wall. Approved.
|
ESC14-00886
| General Inspection | 11/25/2015 | 11/25/2015 | 11/25/2015 2:34:09 PM | | PASS |
|
|
Permit just issued. No activity occuring at site yet...will check back for site prep next week.
|
ESC14-00662
| General Inspection | 11/25/2015 | 11/25/2015 | 11/25/2015 2:19:17 PM | | PASS |
|
|
WIP on SFHs by Tahoe and Hunter. DIs have protection. No trackout or offsite discharges of turbid water. No corrections issued.
|
ESC15-00033
| General Inspection | 11/25/2015 | 11/25/2015 | 11/25/2015 2:15:28 PM | | CANC |
|
|
|
ESC15-01430
| Site Preparation | 11/25/2015 | 11/25/2015 | 11/25/2015 2:14:54 PM | P | PASS |
|
|
Clint Phone #: ###-####
Permit sign posted. DI bags installed and receiving storm drains and wattles at the southern limits of Tahoe Homes parcels in DH#12. Approved.
Need to clean ally between Shadywood and Brookridge once weather clears.
|
ESC15-00556
| General Inspection | 11/25/2015 | 11/25/2015 | 11/25/2015 2:03:59 PM | | PASS |
|
|
Recent site improvements and corrective actions requested have kept runoff onsite with no turbid discharges observed. Access to cleared area off Highland Valley road above Taboo is not restricted and no further citizen complaints received.
No corrections requested at this time. Site is currently in compliance.
|
ESC15-00894
| Complaint Inspection | 11/25/2015 | 11/25/2015 | 11/25/2015 1:59:40 PM | P | PART |
|
|
Trackout complaint and mention of lack of BMPs
Keith ###-####
DIs have sediment sack installed on both sides of Saxton at State Street. Construction entrance is not effectively preventing trackout.
Correction issued to remove compacted gravel & dirt access ramp and install stabilized rock entrance to access Radix job trailier. Road into site worked on by Knife River is scheduled to be paved first week of December, so will allow sweeping of significant trackout until then instead of installation of angular rock entrance . Once paved, Radix will install construction entrance off the new road.
Site perimeter along State Street is in process of being stabilized as well as road and stormwater improvements. See also ESC15-00893 and ESC15-00504 (main Kensington/North Pointe 22 acre disturbance permit)
Will reinspect next Tuesday.
Knife River contact Mike - ###-#### Radix contact Steve - ###-####
|
ESC15-00893
| Complaint Inspection | 11/24/2015 | 11/25/2015 | 11/25/2015 1:58:56 PM | A | PART |
|
|
Trackout complaint and mention of lack of BMPs
Keith ###-####
DIs have sediment sack installed on both sides of Saxton at State Street. Construction entrance is not effectively preventing trackout.
Correction issued to remove compacted gravel & dirt access ramp and install stabilized rock entrance to access Radix job trailier. Road into site worked on by Knife River is scheduled to be paved first week of December, so will allow sweeping of significant trackout until then instead of installation of angular rock entrance . Once paved, Radix will install construction entrance off the new road.
Site perimeter along State Street is in process of being stabilized as well as road and stormwater improvements. See also ESC15-00894 and ESC15-00504 (main Kensington/North Pointe 22 acre disturbance permit)
Will reinspect next Tuesday.
Knife River contact Mike - ###-#### Radix contact Steve - ###-####
|
ESC15-00331
| DOC - Permit Finaled | 11/25/2015 | 11/25/2015 | 11/25/2015 1:10:10 PM | P | PASS |
|
|
|
ESC15-01493
| Site Preparation | 11/24/2015 | 11/25/2015 | 11/25/2015 12:56:33 PM | A | PASS |
|
|
Brad Phone #: ###-####
Permit sign posted and a silt fence installed to control access.
Excavation to begin next week. Requested that RP-GC install DI bag and sand bag block to stop water from flowing in the inlet without going through silt sack.
Approved. Will check for bag next inspection scheduled for 12/8.
|
ESC15-00857
| Tracking Control | 11/24/2015 | 11/25/2015 | 11/25/2015 12:42:23 PM | A | PASS |
|
|
Trackout has been cleaned yesterday. Verified by ACHD ESC Inspector. No violations/corrections at this time.
|
ESC15-00659
| General Inspection | 11/25/2015 | 11/25/2015 | 11/25/2015 11:38:37 AM | | CANC |
|
|
|
ESC15-00358
| General Inspection | 11/25/2015 | 11/25/2015 | 11/25/2015 11:33:08 AM | | PART |
|
|
Pool is installed and landscaping and site work around pool is in progress. There is some trackout from active hauling of dirt with a bobcat.
Verbal correction issued to Visser construction contractor to make sure crews sweep up mud clud and loose dirt on roadway and to install sand bag check dam at west edge of property line to trap silts. The DI that drains the street is currently clogged
|
ESC15-00423
| Site Preparation | 11/24/2015 | 11/25/2015 | 11/25/2015 11:16:31 AM | A | PASS |
|
|
Barry Phone #: ###-####
Approved for construction. Concrete to be poured weather permitting next week. Central designated concrete washouts provided. RP Barry with Bach Homes will add angular rock to construction entrance(s). DI bags on Gary and Saxton are installed. Will install additional control on south side of Saxton . Approved. See also main site ESC permit ESC15-00504. 6 of the individual building unit ESC permits are now issued. There is a total of 31.
|
ESC15-00422
| General Inspection | 11/25/2015 | 11/25/2015 | 11/25/2015 11:16:11 AM | | PASS |
|
|
Approved for construction. Concrete to be poured weather permitting next week. Central designated concrete washouts provided. RP Barry with Bach Homes will add angular rock to construction entrance(s). DI bags on Gary and Saxton are installed. Will install additional control on south side of Saxton . Approved. See also main site ESC permit ESC15-00504. 6 of the individual building unit ESC permits are now issued. There is a total of 31.
|
ESC15-00427
| Site Preparation | 11/24/2015 | 11/25/2015 | 11/25/2015 11:14:45 AM | A | PASS |
|
|
Barry Phone #: ###-####
Approved for construction. Concrete to be poured weather permitting next week. Central designated concrete washouts provided. RP Barry with Bach Homes will add angular rock to construction entrance(s). DI bags on Gary and Saxton are installed. Will install additional control on south side of South Saxton . Approved. See also main site ESC permit ESC15-00504
|
ESC15-00721
| Aging Inspection | 11/25/2015 | 11/25/2015 | 11/25/2015 8:48:26 AM | | PASS |
|
|
|