Inspections for the day of: Friday, November 4, 2016.
Number of inspections: 27
Percentage of inspections complete: 96 %
Percentage of inspections not complete: 4 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC15-00857 General Inspection11/2/201611/4/201611/9/2016 2:31:17 PMAPASS
No rencent acitivity. Too early to tell if recent hydroseed along road shoulders application has been successful. Sediment controls wattles and DI bags have been installed.

No current issues requiring correction, but recommend removing caputured sediment and hydomulch material from behind wattles at the bottom of Arrow Villa in phase 9
ESC16-00559 Aging Inspection11/4/201611/4/201611/8/2016 1:40:19 PM CANC
rescheduled for site final
ESC16-00497 Aging Inspection11/4/201611/4/201611/8/2016 1:33:52 PM CANC
ESC16-00561 General Inspection11/4/201611/4/201611/8/2016 1:22:31 PM PASS
ESC16-01168 Site Final11/4/201611/4/201611/4/2016 2:34:55 PMPPASS
Demolition work complete. New SFH with seperate ESC permit now in progress. All permits finaled
ESC16-00414 General Inspection11/4/201611/4/201611/4/2016 2:34:11 PM CANC
ESC16-01348 General Inspection11/2/201611/4/201611/4/2016 2:34:03 PMAPEND
ESC16-00578 General Inspection11/4/201611/4/201611/4/2016 2:32:50 PM CANC
ESC16-01369 Site Preparation11/4/201611/4/201611/4/2016 2:30:31 PMPPASS
Ryan Phone #: ###-####

Lot previously cleared for demo work under seperate permit. No MS4 on block. Flat lot with low runoff potential. Approved for construction.
ESC16-01407 Site Preparation11/4/201611/4/201611/4/2016 1:38:34 PMPPASS
John Phone #: ###-####

Subdivision BMPs installed. Permit sign posted. RP-GC on site for supervision. First SFH of DHE #15
ESC16-01429 Site Preparation11/2/201611/4/201611/4/2016 11:46:16 AMAPASS
Cary Phone #: ###-####

ESC permit sign posted and wattles staged for installation once the access through yard is created. RP familiar with ESC conditions. Approved.
ESC16-01394 Site Preparation11/3/201611/4/201611/4/2016 10:45:38 AMAPASS
Ben Phone #: ###-####

Antelope Springs subdivision BMPs installed. Yellow permit sign posted. DI bags in front site have remaining capacity. Reviewed concrete washout rules with RP. Approved for construction.
ESC13-01279 General Inspection11/4/201611/4/201611/4/2016 10:35:38 AM PASS
WIP on new excavation in central area. Stockpiles currently in process of removal/relocation. Some trackout within in subdivision.

Concrete washout facility with two containment bins provided. Inlets has sediment protection.

Approved
ESC16-00416 Aging Inspection11/4/201611/4/201611/4/2016 10:23:17 AM PASS
Townhome complete, BLD finaled. Active work and ESC permits in effect. No corrections/violations
ESC16-00416 DOC - Permit Finaled11/4/201611/4/201611/4/2016 10:23:08 AMPPASS
ESC16-00415 Aging Inspection11/4/201611/4/201611/4/2016 10:23:01 AM PASS
Townhome complete, BLD finaled. Active work and ESC permits in effect. No corrections/violations
ESC16-00415 DOC - Permit Finaled11/4/201611/4/201611/4/2016 10:22:20 AMPPASS
ESC14-01083 Random Inspection11/4/201611/4/201611/4/2016 10:21:50 AMPPART
construction activity (staging, irrigation line trenching, employee parking) occuring on area not covered under existing ESC permits.

Correction request to provide new ESC plan and get permit for construction activities along Barber Valley Drive.
ESC14-00657 General Inspection11/4/201611/4/201611/4/2016 10:04:33 AM CANC
ESC16-00437 General Inspection11/4/201611/4/201611/4/2016 10:04:23 AM PASS
Silt fence perimeter installed and in good condtion. No significant trackout, no discharges observed. No windblown trash; spill prevention practices implemented in staging areas. No corrections requested for the Arboretum projects (3 buildings, 1 site permit)
ESC16-00435 General Inspection11/4/201611/4/201611/4/2016 10:04:11 AM PASS
Silt fence perimeter installed and in good condtion. No significant trackout, no discharges observed. No windblown trash; spill prevention practices implemented in staging areas. No corrections requested for the Arboretum projects (3 buildings, 1 site permit)
ESC16-00436 General Inspection11/4/201611/4/201611/4/2016 10:03:58 AM PASS
Silt fence perimeter installed and in good condtion. No significant trackout, no discharges observed. No windblown trash; spill prevention practices implemented in staging areas. No corrections requested for the Arboretum projects (3 buildings, 1 site permit)
ESC16-00036 General Inspection11/4/201611/4/201611/4/2016 9:15:10 AM PASS
ESC16-01428 Site Preparation11/3/201611/4/201611/4/2016 8:53:54 AMAPASS
Brian Phone #: ###-####

Flat lot. No gutter/MS4 adjacent to project. Permit sign posted. RP available and in good compliance standing. Approved
ESC16-00555 Aging Inspection11/4/201611/4/201611/4/2016 8:18:34 AM PASS
Pool in backyard complete. All permits finaled. Site cleaned & stabilized
ESC16-00555 DOC - Permit Finaled11/4/201611/4/201611/4/2016 8:18:03 AMPPASS
ESC15-01343 Site Final11/1/201611/4/2016 P