ESC17-00519
| Aging Inspection | 11/5/2018 | 11/5/2018 | 11/8/2018 8:29:19 AM | | CANC |
|
|
|
ESC17-00936
| General Inspection | 11/5/2018 | 11/5/2018 | 11/6/2018 11:10:08 AM | | CANC |
|
|
rescheduled for site fInal
|
ESC18-01022
| Conference | 11/2/2018 | 11/5/2018 | 11/5/2018 4:42:56 PM | A | PASS |
|
|
1030 site walk though to review next steps after grading.
Site access will be blocked off to prevent incidental track out and trespassing. If access is required, rock construciton entrances will be needed.
Earthwork is nearly complete, on minor work remaining. Slopes have been horizontally tracked, parcels have retention berms installed to allow water to infiltrate on lots rather than runoff.
Slope interupting wattles are to be installed on the north facing slope on south side of entrance at Eyrie Way. 3-4 sections of wattles installed along contour, trench 2-3 ", and staked every 5 ft. Slope wattles are also required at the top of the site on the northwest side of Eyrie Way and Winter Camp. After wattle installation, hydroseed application will be completed on all disturbed areas including parcels. Both of these steps are to be implemented before the end of the week of Nov. 12-16th.
Runoff control berms will be installed on roadways approximately every 150 feet to slow down and retain runoff.
RP Jill to inspect and add additional wattles along the graded ridge in a few areas where the berm is not clearly above the parcel grade.
No trackout, discharges or other violations. Concrete washout for phase #9 SFHs is installed within the phase #10 footprint
|
ESC18-00998
| BMP Violation | 11/5/2018 | 11/5/2018 | 11/5/2018 10:17:23 AM | A | FAIL |
|
|
No clean up of conrete washout completed. Investigation conducted with Sunroc, Brundage Bone, and Rainbow Constructuion.
No sediment protection installed on storm drain.
Not approved for inspections
|