ESC15-01343
| Site Final | 11/1/2016 | 11/4/2016 | | P | |
|
|
|
ESC15-01138
| General Inspection | 11/4/2016 | 11/8/2016 | 11/15/2016 7:46:22 AM | P | CANC |
|
|
|
ESC16-00276
| General Inspection | 11/8/2016 | 11/8/2016 | 11/10/2016 1:34:25 PM | | CANC |
|
|
|
ESC16-00242
| General Inspection | 11/8/2016 | 11/8/2016 | 11/10/2016 1:34:15 PM | | CANC |
|
|
|
ESC14-01063
| General Inspection | 11/8/2016 | 11/8/2016 | 11/9/2016 2:22:43 PM | | PASS |
|
|
No new subdivision activity or SFHs in progress. DI sediment bags recently maintained and reinstalled. No sediment runoff issues or hillside erosion rills observed. Concrete washout for EC #7 homes is in compliance with lined pit.
|
ESC16-00343
| General Inspection | 11/8/2016 | 11/8/2016 | 11/9/2016 2:00:30 PM | | PEND |
|
|
Hillside revegetation, grass not yet fully established. Home id occupied. Some minor erosion on uphill sideyard due to runoff from the vacant lot above home is still occuring. Lot is not owned by builder (Canyon Crest)
|
ESC15-01526
| Aging Inspection | 11/8/2016 | 11/8/2016 | 11/9/2016 9:02:50 AM | | PASS |
|
|
Construction complete and home now occupied. No ESC corrections required. All permits finaled.
|
ESC15-01552
| Site Final | 11/8/2016 | 11/8/2016 | 11/9/2016 7:50:48 AM | P | NR |
|
|
BLD permit for shell finaled. Some interior work remaining
|
ESC15-01588
| Aging Inspection | 11/8/2016 | 11/8/2016 | 11/8/2016 3:58:20 PM | | CANC |
|
|
|
ESC15-01532
| General Inspection | 11/8/2016 | 11/8/2016 | 11/8/2016 3:52:37 PM | | PEND |
|
|
|
ESC15-01204
| Aging Inspection | 11/8/2016 | 11/8/2016 | 11/8/2016 3:52:29 PM | | CANC |
|
|
rescheduled for site final
|
ESC15-00306
| General Inspection | 11/8/2016 | 11/8/2016 | 11/8/2016 3:51:57 PM | | CANC |
|
|
|
ESC15-01537
| Aging Inspection | 11/8/2016 | 11/8/2016 | 11/8/2016 3:51:48 PM | | PASS |
|
|
|
ESC15-01537
| DOC - Permit Finaled | 11/8/2016 | 11/8/2016 | 11/8/2016 3:51:41 PM | P | PASS |
|
|
|
ESC15-00688
| General Inspection | 11/8/2016 | 11/8/2016 | 11/8/2016 1:29:26 PM | | PASS |
|
|
Onsite storm drains have now had the filled silt filter sacks removed to properly handle stormwater runoff. Construction materials have been cleaned, no loose dirt or materials onsite.
ESC final correction requests and conditions have been satisfied. ESC permit for Falling Brook is now closed.
|
ESC16-00329
| General Inspection | 11/8/2016 | 11/8/2016 | 11/8/2016 1:18:36 PM | | PASS |
|
|
homeowner lansdcaping project and site improvements in progress. Permit sign posted, no trackout or other issues. No corrections needed
|
ESC16-00237
| Site Final | 11/2/2016 | 11/8/2016 | 11/8/2016 12:47:52 PM | A | PASS |
|
|
Blvd. townhome complete and landscaped. DI bags in area to be removed as blocks completed. BLD finaled, no ESC corrections needed. Active projects in compliance.
|
ESC16-00238
| Site Final | 11/2/2016 | 11/8/2016 | 11/8/2016 12:47:29 PM | A | PASS |
|
|
Blvd. townhome complete and landscaped. DI bags in area to be removed as blocks completed. BLD finaled, no ESC corrections needed. Active projects in compliance.
|
ESC16-01197
| Site Preparation | 11/7/2016 | 11/8/2016 | 11/8/2016 12:23:27 PM | A | PASS |
|
|
Austin Phone #: ###-####
First 3 units in Harris North, all 3 parcels adjacent. Portable concrete washout facility with regular servicing to be staged on open lot on Hoot Owl street with stabilized access. Subdivision inlets have sediment filter bags, lots pregraded to drain away from hillside back towards street; earthen berm along hillside edge. Permit signs posted for the 3 projects. Approved.
|
ESC16-01196
| Site Preparation | 11/7/2016 | 11/8/2016 | 11/8/2016 12:22:45 PM | A | PASS |
|
|
Austin Phone #: ###-####
First 3 units in Harris North, all 3 parcels adjacent. Portable concrete washout facility with regular servicing to be staged on open lot on Hoot Owl street with stabilized access. Subdivision inlets have sediment filter bags, lots pregraded to drain away from hillside back towards street; earthen berm along hillside edge. Permit signs posted for the 3 projects. Approved.
|
ESC16-01199
| Site Preparation | 11/7/2016 | 11/8/2016 | 11/8/2016 12:22:26 PM | A | PASS |
|
|
Austin Phone #: ###-####
First 3 units in Harris North, all 3 parcels adjacent. Portable concrete washout facility with regular servicing to be staged on open lot on Hoot Owl street with stabilized access. Subdivision inlets have sediment filter bags, lots pregraded to drain away from hillside back towards street; earthen berm along hillside edge. Permit signs posted for the 3 projects. Approved.
|
ESC16-01373
| Site Preparation | 11/7/2016 | 11/8/2016 | 11/8/2016 12:05:02 PM | A | PASS |
|
|
Call ten minutes to meet // Tom Phone #: ###-####
Project with vegetated yard. Stabilized access provided via existing driveway. Excess dirt to be kept in backyard for landscaping and gardening. Work to begin next week.
Approved
|
ESC15-01552
| Tracking Control | 11/8/2016 | 11/8/2016 | 11/8/2016 8:49:26 AM | P | CANC |
|
|
|
ESC16-01080
| Site Preparation | 10/19/2016 | 11/8/2016 | 11/8/2016 8:05:58 AM | A | CANC |
|
|
data entry error, rescheduled 11/9
|
ESC15-00033
| General Inspection | 11/8/2016 | 11/8/2016 | 11/8/2016 8:02:54 AM | | CANC |
|
|
|
ESC15-01627
| Aging Inspection | 11/8/2016 | 11/8/2016 | 11/8/2016 8:02:38 AM | | CANC |
|
|
|