Inspections for the day of: Wednesday, December 12, 2018.
Number of inspections: 16
Percentage of inspections complete: 94 %
Percentage of inspections not complete: 6 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC16-00935 General Inspection12/12/201812/12/201812/12/2018 3:13:10 PMPPART
No muddy runoff. ESC BMPs installed.

correction needed:
pick up uncontained trash and debris pile in front of home. Provide a trash container.

Verbal correction to Roth Homes Kevin. Follow up next week.
ESC18-00920 General Inspection12/12/201812/12/201812/12/2018 3:11:58 PMPCANC
ESC18-00354 General Inspection12/12/201812/12/201812/12/2018 2:58:44 PM PASS
No disturbed area on site. No exterior construction. Project appears complete, BLD permit is still open.
ESC18-00354 DOC - Permit Finaled12/12/201812/12/201812/12/2018 2:58:10 PMPPASS
ESC15-01210 General Inspection12/12/201812/12/201812/12/2018 2:46:13 PM PASS
ESC18-00309 BMP Violation12/12/201812/12/201812/12/2018 2:28:47 PMPPEND
WIP on clean up. No new trackout or discharges. Trash has been picked up. Gatorguard wattles re-aligned.

Washout pit has been cleaned out and re-excavated. Will need secure the lining so it contains washout.
ESC18-00920 General Inspection12/12/201812/12/201812/12/2018 2:12:51 PMPPASS
No muddy runoff. No trackout, workers staying off the mud. Perimter wattles installed. Some more wattles to be installed once more thawing has occurred.
ESC18-00363 General Inspection12/12/201812/12/201812/12/2018 1:35:16 PM PASS
WIP. No trackout or discharges. Site is clean and existing hardscape and vegetatation has been preserved.
ESC16-01472 Conference12/12/201812/12/201812/12/2018 10:28:36 AMPDONE
Meeting with ACHD, public works, and neighbor to discuss issues with new road base of Logan alley as well as runoff from site.

Site needs to reinstall perimeter controls until landscaping and stabilization can occur.

Temporary silt fences will also need to be removed at end of project.

Meeting with RP-GC and ACHD will be scheduled.
ESC17-01552 Aging Inspection12/12/201812/12/201812/12/2018 8:44:55 AM CANC
rescheduled for site final
ESC17-01788 Aging Inspection12/12/201812/12/201812/12/2018 8:37:32 AM CANC
ESC17-01783 General Inspection12/12/201812/12/201812/12/2018 8:35:53 AM CANC
rescheduled for site final
ESC17-01773 Aging Inspection12/12/201812/12/201812/12/2018 8:35:09 AM CANC
rescheduled for site final
ESC17-01317 General Inspection12/12/201812/12/201812/12/2018 8:34:04 AM CANC
ESC17-01241 General Inspection12/3/201812/12/201812/12/2018 8:16:40 AMPCANC
ESC18-01285 General Inspection11/29/201812/12/2018 P