Inspections for the day of: Thursday, December 6, 2018.
Number of inspections: 12
Percentage of inspections complete: 83 %
Percentage of inspections not complete: 17 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC17-00302 Site Final11/30/201811/30/2018 P 
ESC18-01102 Conference11/30/201812/3/2018 A 
ESC18-00184 General Inspection12/6/201812/6/201812/11/2018 11:24:29 AM PASS
DI bag replaced as requested.

Driveway just poured used a washout containment. Notified RP Clayton that extra rock can be placed on ground, it is the washout rinse water that should be collected into the containment.
ESC17-01595 General Inspection12/6/201812/6/201812/10/2018 4:10:26 PM PASS
WIP on excavation. No trackout. Site is cleaning up at end of day. Wintery/frozen conditions.
ESC18-00180 General Inspection12/6/201812/6/201812/7/2018 2:19:57 PM PASS
ESC17-01767 Aging Inspection12/6/201812/6/201812/7/2018 2:04:27 PM CANC
ESC17-01441 Aging Inspection12/6/201812/6/201812/7/2018 8:26:41 AM PASS
ESC18-01333 Site Preparation12/6/201812/6/201812/6/2018 9:28:37 AMAPASS
Please call me 20min. Thanks Phone #: ###-#### Inspection requested via web by Ken Litzinger

RP-GC notified that some activity has started. Perimeter wattle is installed and may start excavating site access today or tomorrow. Request to post ESC permit sign that is visible from road.

Approved to activate site. Follow up site meeting scheduled for Monday 12/10.
ESC18-00020 General Inspection11/27/201812/6/201812/6/2018 8:55:02 AMPPEND
compliance time extended due to wintery/frozen conditions.
ESC18-00221 General Inspection12/6/201812/6/201812/6/2018 8:51:13 AM CANC
rescheduled for site final
ESC17-00761 Aging Inspection12/6/201812/6/201812/6/2018 8:50:02 AM CANC
ESC16-01253 General Inspection12/6/201812/6/201812/6/2018 8:47:43 AM CANC