PDS Online
Making
Boise
the most livable city in the country.
Home
Permits
Search by Permit Number
How to search by permit number
Search by Address
Search by Customer Number
Search by Current Planning Number
Search in Project by Permit Number
Search by Project Name
Inspections
Search by Permit Number
Search by Request Date
Search by Company Name
Fees
Impact Fees Estimate Calculator
Other Searches
Search for Licensed Contractors
Search Parcel by Address
Search Historical Surveys
Reports
Daily Reports
Weekly Reports
Monthly Reports
Home
/
Inspections
/
Inspector Activity
Inspections for the day of:
Monday, December 7, 2015
.
Number of inspections:
20
Percentage of inspections complete:
100 %
Percentage of inspections not complete:
0 %
Contact Information
Inspector
Andy J. Long
Title
EROSION INSPECTOR
Phone #
794-8996
Permit Number
Description
Received
Requested
Completed
AM/PM
Disposition
ESC15-00024
General Inspection
12/7/2015
12/7/2015
12/10/2015 4:22:11 PM
FAIL
Sediment control wattles and DI bag captured some of the sediment runoff but still evidence of failure and prohibited discharge to DI.
1. Clean collected mud in gutter
2. Empty out and reinstall sediment bag
3. Conduct maintenance on wattles, install more wattles along left side of house.
4. Provide schedule for stabilization/landscaping - permanent or temporary.
ESC15-01210
Stop Work Order
12/7/2015
12/7/2015
12/8/2015 7:49:53 AM
P
DONE
SWO posted. Corrections disclosed. Reinspection required before approval to proceed.
ESC15-01210
BMP Violation
12/7/2015
12/7/2015
12/7/2015 4:25:23 PM
P
FAIL
Continued BMP failure and sediment runoff down Sheran and discharging into inlet on Ada just past 7th Street.
ESC15-00709
BMP Violation
12/7/2015
12/7/2015
12/7/2015 4:24:09 PM
P
FAIL
Muddy runoff still leaving site. Wattle was installed and gutter cleaned but there is still significant amount of sediment running off site, down Sherman to 6th street and then to Ada draining into MS4 on Ada & 7th
ESC15-00822
General Inspection
12/2/2015
12/7/2015
12/7/2015 3:40:26 PM
A
PASS
Follow up inpseciton after sweeping CN
Surrounding roads were swept and landscaping/stabilization of hotel parking lot & grounds is near completion. All private and MS4 inlets has sediment filter bag inserts installed. No new corrections at this time. Pasadena Street is much cleaner.
Once conditions are dry all DI bags should be checked for maintenance.
ESC15-00556
Random Inspection
12/7/2015
12/7/2015
12/7/2015 3:27:24 PM
P
PASS
BMPs and stormwater management improvements along Highland Valley Road have prevent erosion and sediment runoff.
Approved.
ESC15-01044
Site Final
12/4/2015
12/7/2015
12/7/2015 3:06:26 PM
P
NR
Adam Phone #: ###-####
Not yet landscaped/stabilized. No violations at site. Discussed final requirements with RP Adam, and he will let me know when home is occupied. Sale currently pending
ESC15-00709
BMP Violation
12/7/2015
12/7/2015
12/7/2015 2:09:05 PM
P
FAIL
No BMPs implemented. Roadway has uncleaned trackout. Multiple violations.
RP notified to come on site today. Will re-inspect and determine if SWO is necessary.
ESC15-01210
BMP Violation
12/7/2015
12/7/2015
12/7/2015 2:08:50 PM
P
FAIL
Muddy runoff flowing off site. Inadequate BMPS and housekeeping.
Correction:
- Install check dams and additional filter fabric rolls to treat runoff.
- Tracked muddy flow to 7th & Ada DI. No DI bag installed. Need to clean inlet and install DI bag.
SWO issued until BMPs can be installed and inspected.
ESC15-00080
General Inspection
12/7/2015
12/7/2015
12/7/2015 2:01:55 PM
CANC
ESC15-00079
General Inspection
12/7/2015
12/7/2015
12/7/2015 2:01:33 PM
CANC
ESC15-00078
General Inspection
12/7/2015
12/7/2015
12/7/2015 2:01:17 PM
CANC
ESC15-00077
General Inspection
12/7/2015
12/7/2015
12/7/2015 2:01:04 PM
CANC
ESC15-00076
General Inspection
12/7/2015
12/7/2015
12/7/2015 2:00:44 PM
CANC
ESC15-00094
Random Inspection
12/7/2015
12/7/2015
12/7/2015 1:59:35 PM
P
PASS
BMPs and site grading practice has worked well to keep sediment and slopes stabile in BH#6. No BMP failures identified. No significant rills or gullies observed. Wattles and sediment trenches installed incrementally on slopes has helped considerably. Approved.
ESC15-01266
Random Inspection
12/7/2015
12/7/2015
12/7/2015 1:38:18 PM
P
PASS
Stabilized entrance provided. Site access designated. No trackout or muddy discharges during rain. Approved
ESC15-00035
General Inspection
12/7/2015
12/7/2015
12/7/2015 12:01:51 PM
PASS
ESC15-00044
Aging Inspection
12/7/2015
12/7/2015
12/7/2015 10:35:58 AM
PASS
WIP on interior. No active earth work occuring. Permeable paving parking on Broad Street now installed. No turbid runoff from site and leakproof washot onsite.
Note - muddy runoff from unpaved alley in between 3rd and 2nd street south of site, not apparently related to construction. DI has sediment bag but is currently backed up.
ESC15-01143
Site Final
12/7/2015
12/7/2015
12/7/2015 9:41:23 AM
P
PASS
Initial grading for Afton is complete. Vertical construction to be covered under ESC15-01184 and see also main ESC permit for project under ESC15-00789.
No trackout or discharges from site. All perimeter MS4 DIs have inlet filter bags. Site surrounded by security fence to control access and construction traffic.
ESC15-00004
Aging Inspection
12/7/2015
12/7/2015
12/7/2015 8:46:35 AM
PASS