ESC16-00156
| General Inspection | 2/27/2018 | 2/27/2018 | 3/1/2018 12:19:22 PM | | PASS |
|
|
No new SFH activity. Open lots still availaible. Subdivsion BMPs (DI bags, concrete washout) are still in place. No violations observed.
|
MIS17-00396
| ESC-Conference | 2/27/2018 | 2/27/2018 | 2/28/2018 11:59:40 AM | P | PEND |
|
|
Correction request to Brown Construction to clean up existing trackout, remove equipement, and close entrance to site. Any further work will require an ESC permit.
Matt 208.473.9948
|
ESC16-01446
| General Inspection | 2/27/2018 | 2/27/2018 | 2/27/2018 3:28:20 PM | | PASS |
|
|
No trackout or sediment runoff from perimeter. Strom drain inlet protection installed. No corrections requested.
|
ESC16-01706
| BMP Violation | 2/20/2018 | 2/27/2018 | 2/27/2018 2:29:44 PM | A | PASS |
|
|
check for construction entrance maintenance.
New rock has been installed on construction entrance. No new trackout. Site currently inactive. Permit sign posted on Irving at center of project.
|
ESC16-01354
| General Inspection | 2/27/2018 | 2/27/2018 | 2/27/2018 2:28:38 PM | | PASS |
|
|
BLD has temp. occupancy for parking garage and Chamber of Commerce tenant space. Two active projects on block, will keep this permit open for continued monitoring.
|
ESC17-00655
| Aging Inspection | 2/27/2018 | 2/27/2018 | 2/27/2018 2:18:57 PM | | PASS |
|
|
Earth disturbance complete, no stockpiles or loose materials on site that could runoff. No temporary BMPs installed. ESC permit finaled; BLD still open.
|
ESC17-00655
| DOC - Permit Finaled | 2/27/2018 | 2/27/2018 | 2/27/2018 2:17:53 PM | P | PASS |
|
|
|
ESC16-01710
| Aging Inspection | 2/27/2018 | 2/27/2018 | 2/27/2018 2:15:47 PM | | PASS |
|
|
Parking lot constructed and in uns by child care center. No loose materials or temporary BMPs left on site, ESC permit finaled.
|
ESC16-01710
| DOC - Permit Finaled | 2/27/2018 | 2/27/2018 | 2/27/2018 2:15:06 PM | P | PASS |
|
|
|
ESC17-00145
| Aging Inspection | 2/27/2018 | 2/27/2018 | 2/27/2018 2:02:54 PM | | PASS |
|
|
Duplex in progress. ESC permit sign posted, trash contained. No discharges or trackout. Approved.
|
ESC17-01346
| Site Preparation | 2/26/2018 | 2/27/2018 | 2/27/2018 1:47:27 PM | P | PASS |
|
|
1 PM site walk through
MS4 storm drains on 9th Street and on River Street have been fitted with new inlet sediment protection. Two construction entrances are installed for initial excavation phase. Requested that apron be checked every day to sweep sidewalk and make sure rocks are not in traffic lanes.Requested next rock needs to be angular. Employee parking and job trailer with SWPPP are located north of the site on corner of 9th Street and Fulton. Existing asphalt to be preserved.
Trash dumpster in staging yard, concrete washouts will be portable plastic containers placed in staging yard and around site for easy access.
Site to be inspected 2x monthly. ESC permit signs to be posted in job trailer and along fence on River Street.
|