ESC14-00206
| General Inspection | 2/24/2016 | 3/1/2016 | 3/4/2016 2:51:51 PM | P | PASS |
|
|
WIP on SFHs in Sunnyridge. No discharges, resident complaints, or other violations. Subdivision storm drains have sediment protection. Designated washout is being utilized.
|
ESC15-00509
| General Inspection | 3/1/2016 | 3/1/2016 | 3/2/2016 2:01:36 PM | | PASS |
|
|
No trackout, sediment control BMPs installed below home, no windblown trash or loose material leaving site. No corrections.
|
ESC14-01083
| General Inspection | 3/1/2016 | 3/1/2016 | 3/1/2016 3:56:57 PM | | PASS |
|
|
BMPs installed and in good condition. No trackout or discharges from site. No corrections at this time.
|
ESC15-00785
| Aging Inspection | 3/1/2016 | 3/1/2016 | 3/1/2016 3:48:08 PM | | PASS |
|
|
Home is complete and occupied. Yard is to be landscaped by homeowner. No trackout or sediment leaving site to stormwater system. No further ESC inspections required. Conditions satisfied.
|
ESC15-00785
| DOC - Permit Finaled | 3/1/2016 | 3/1/2016 | 3/1/2016 3:46:21 PM | P | PASS |
|
|
|
ESC15-01288
| Site Preparation | 3/1/2016 | 3/1/2016 | 3/1/2016 3:39:47 PM | P | PASS |
|
|
Excavation for River Heights is to begin later this week. Site walk through conducted.
Over the next couple days Brighton and Syman Company will install BMPs such as perimeter sediment control wattles along Warm Springs, silt fence along the existing neighborhood to the southwest, and a heavy duty angular rock construction entrance.
The small drainage area is to be filled in for the development and run-on to the subdivision controlled by retaining ponds and diversion channels/pipes.
Approved to mobilize. Will monitor over the following week as work begins to check that all BMPs are installed as discussed.
|
ESC15-00719
| Aging Inspection | 3/1/2016 | 3/1/2016 | 3/1/2016 3:14:29 PM | | PART |
|
|
Home complete. Landscaping along Tao for multipile projects is in progress.
Need to sweeep up trackout and improve fugitve dust control on the haul road...CR issued to Tahoe.
|
ESC16-00111
| Site Preparation | 2/29/2016 | 3/1/2016 | 3/1/2016 3:10:42 PM | A | PART |
|
|
Clint Phone #: ###-####
Permit sign posted and new lined concrete washout has been installed for new phase of EV as requested.
Landscaping operation for getting topsoil is causing trackout and dust issues. Correction request to sweep affected streets and designated a rout that will limit disturbance.
|
ESC15-01513
| BMP Violation | 2/23/2016 | 3/1/2016 | 3/1/2016 2:24:12 PM | A | CANC |
|
|
follow up on dirty culdesac
compliance date extended to Thursday 3/3
|
ESC15-00699
| General Inspection | 3/1/2016 | 3/1/2016 | 3/1/2016 1:45:54 PM | | CANC |
|
|
|
ESC15-00581
| General Inspection | 3/1/2016 | 3/1/2016 | 3/1/2016 1:30:46 PM | | PASS |
|
|
WIP on hotel renovation. No trackout, discharges. MS4 on Sunrise Rim and private structures on site have sediment protection.
|
ESC13-00600
| DOC - Permit Finaled | 3/1/2016 | 3/1/2016 | 3/1/2016 11:15:19 AM | P | PASS |
|
|
|
ESC14-00983
| General Inspection | 3/1/2016 | 3/1/2016 | 3/1/2016 10:46:09 AM | | PASS |
|
|
WIP on finishing foundations for the two 28 plex buildings. No significant trackout, DI bag on MS4 on Opohonga is installed and has filtering capacity. Utility line not yet patched in street.
Provided both RPs Pat and Jeremy, who were on site a new yellow ESC sign to post.
Approved.
|
ESC14-00590
| Aging Inspection | 3/1/2016 | 3/1/2016 | 3/1/2016 9:52:14 AM | | PASS |
|
|
|
ESC14-00589
| Aging Inspection | 3/1/2016 | 3/1/2016 | 3/1/2016 9:52:05 AM | | PASS |
|
|
|
ESC13-00684
| General Inspection | 3/1/2016 | 3/1/2016 | 3/1/2016 9:32:30 AM | | PASS |
|
|
|
ESC15-00729
| General Inspection | 2/24/2016 | 3/1/2016 | 2/29/2016 2:31:19 PM | P | PASS |
|
|
Walk through inspection of Council Springs Creek area and inspection of slope stabilization with Syman Company foreman Andy.
Silt fence and vegetative buffer along Council Springs Creek has been maintained and no areas of disturbed area affecting the creek were observed.
It was noted that the culverts recently installed under the access road will need modification to allow water to flow through the culvert pipe instead of infiltraing and pool below the level of the flared entrance.
No active constuction around the creek crossing. Check dam and silt fence filter area appear to be working. Water entering and leaving the work area is visibly very clear with no change of turbidity detectable by the eye.
Slopes: - WIP on spreading topsoil, wattling at 20 foot intervals and applying a native grass seed mix with bonded fiber matrix hydomulch. Slopes will not need further grading have had BMPs applied. Grass seed is germinating and sprouting in some areas. No significant rill erosion or wattle failures observed.
No trackout at entrances and no stormwater related discharges from site. Staging area has secondary containment for fuel and other material containers. No windblown trash or fugitive dust issues at time of inspection.
No corrections issued at this time, site is currently in compliance and appears to be on schedule to handle spring time precipitation.
|