Inspections for the day of: Thursday, March 10, 2016.
Number of inspections: 30
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC15-01532 General Inspection3/9/20163/10/20163/16/2016 8:35:02 AMPPART
Need to address trackout on Americana Terrace.
Limited activity currently. Vegetative buffer and sediment controls are installed and have not been disturbed.
ESC15-00789 General Inspection3/10/20163/10/20163/15/2016 7:55:57 AM PASS
Inspection performed 3/14.

No significant trackout, trackout being cleaned regularly. Site has traffic control through site so that rock construction entrance are used.

Storm drains have inlet protection, no accumulation of dirt and debris from site in gutters or at inlets.

No corrections at this time.
ESC15-00826 Aging Inspection3/10/20163/10/20163/11/2016 1:12:28 PM CANC
ESC15-00306 General Inspection3/10/20163/10/20163/11/2016 1:12:20 PM CANC
rescheduled
ESC15-00904 Aging Inspection3/10/20163/10/20163/11/2016 1:11:52 PM CANC
ESC16-00175 Site Preparation3/10/20163/10/20163/10/2016 3:55:17 PMPCANC
data entry error
ESC15-01583 Site Preparation3/10/20163/10/20163/10/2016 3:53:52 PMPPASS
Zack Phone #: ###-####


WIP. Reviewed ESC site prep requirements with Matt with Evans contsruction. No other corrections needed. BMPs for Belmar installed and sites clean.
ESC16-00167 Site Preparation3/10/20163/10/20163/10/2016 3:53:42 PMPPASS
Zack Phone #: ###-####


WIP. Reviewed ESC site prep requirements with Matt with Evans contsruction. No other corrections needed. BMPs for Belmar installed and sites clean.
ESC16-00108 Site Preparation3/10/20163/10/20163/10/2016 3:53:33 PMPPASS
Zack Phone #: ###-####

WIP. Reviewed ESC site prep requirements with Matt with Evans contsruction. No other corrections needed. BMPs for Belmar installed and sites clean.
ESC15-00885 BMP Violation3/10/20163/10/20163/10/2016 3:51:59 PMPFAIL
Subcontractor crane leaked significant amount of fluid (hydraulic oil?) on Blue Ribbon.

Requested that soil spread around spill area be swept immediately and disposed of properly to not mix with the storm water from today's afternoon precipitaion.

Both Brighton Corp. & Brighton Homes are working on case. Kyle stated he will give crane operator a warning to bring spill prtection and cleanup materials. Company is AM Crane, which I was unable to contact.

Corrections in progress
ESC14-01083 General Inspection3/10/20163/10/20163/10/2016 3:48:13 PMPPART
Subcontractor crane leaked significant amount of fluid (hydraulic oil?) on Blue Ribbon.

Requested that soil spread around spill area be swept immediately and disposed of properly to not mix with the storm water from today's afternoon precipitaion.

Both Brighton Corp. & Brighton Homes are working on case. Kyle stated he will give crane operator a warning to bring spill prtection and cleanup materials. Company is AM Crane, which I was unable to contact.
ESC15-00789 General Inspection3/10/20163/10/20163/10/2016 3:37:33 PMPCANC
data entry error
ESC16-00159 General Inspection3/10/20163/10/20163/10/2016 3:25:26 PMPPASS
Inspection conducted to observe the phase 1 implementation of the dewatering/creek bypass plan at DHE #14.

Warm Springs Creek is dammed and water flows into a 12 " pipe that conveys the water over the disturbed and not yet stabilized creek bed that was widened before north of the existing box culvert. Water discharge out of the pipe is clear and system appears to be working well.

Syman Company will reinstall the silt fence to keep construction work and sediment out of the new creek bed.

Approved. Phase 2 for utilitiy/sewer installation to begin next week.

ESC14-00657 General Inspection3/10/20163/10/20163/10/2016 3:20:52 PM PART
WIP on SFHs and off haul of dirt from lower section retaining walls. Significant trackout within subdivision. Storm drains have sediment filter bags installed.

Brighton Homes RP Erbie stated streets will swept this weekend and inlet bags maintained/emptied.
ESC14-00719 General Inspection3/10/20163/10/20163/10/2016 3:19:45 PM PART
WIP. No major trackout. Strom drains have sediment bags. Need to sweep gutters on Myrtle to east of construction area entrance by the JUMP.
ESC15-00762 General Inspection3/10/20163/10/20163/10/2016 3:16:34 PM PASS
WIP on foundation. BMPs installed include DI sediment filter mats, consrtuction entrance, and lined washout pit. No trackout or loose sediment on streets or in gutters around perimeter. No loose trash or spills observed. Approved.
ESC14-01052 General Inspection3/10/20163/10/20163/10/2016 3:12:11 PM PASS
WIP on painting, landscaping, finishing interior touches, and carports at Asheville. Single 4-plex permits finaled. No corrections at this time. Many units already occupied.
ESC15-00930 Aging Inspection3/10/20163/10/20163/10/2016 2:12:40 PM PASS
Structural and earth work for project complete. No loose dirt or disturbed area on site. ESC permit conditions satisfied. No further inspections.
ESC15-00930 DOC - Permit Finaled3/10/20163/10/20163/10/2016 2:11:56 PMPPASS
ESC15-00801 General Inspection3/10/20163/10/20163/10/2016 2:05:54 PM CANC
ESC15-00975 Aging Inspection3/10/20163/10/20163/10/2016 2:02:12 PM PASS
Work complete. No disturbed area or loose sediment. All permits finaled.
ESC15-00975 DOC - Permit Finaled3/10/20163/10/20163/10/2016 2:01:13 PMPPASS
ESC15-01628 Random Inspection3/10/20163/10/20163/10/2016 1:59:08 PMPPASS
WIP on frame and interior. No earthwork. No trackout. Permit posted. Employees parking on street as directed. No corrections.
ESC15-00947 Aging Inspection3/10/20163/10/20163/10/2016 1:56:46 PM PASS
WIP on accesory structure. No trackout or sediment runoff. Permit sign posted. Approved.
ESC11-00525 Site Final3/10/20163/10/20163/10/2016 1:40:54 PMPPASS
All subdivision work complete. Well over 70% of the total disturbed area is now stabilzed with new residential homes. Brighton Homes to remove remaining DI bags once work is completed on the SFHs. No further ESC inspections necessary on this permit, no outstanding corrections. Permit conditions satisfied.
ESC11-00525 DOC - Permit Finaled3/10/20163/10/20163/10/2016 1:37:37 PMPPASS
ESC15-00805 General Inspection3/10/20163/10/20163/10/2016 1:37:15 PM PASS
Work complete. All permits finaled. No ESC corrections issued. Tenant space now occupied.
ESC15-00805 DOC - Permit Finaled3/10/20163/10/20163/10/2016 1:35:44 PMPPASS
ESC16-00161 General Inspection3/9/20163/10/20163/10/2016 9:56:01 AMAPASS
Mike ###-####

Permit sign posted. Workers parking on street to prevent trackout. Vegetative buffer kept around house backfill. To be backfill tomorrow or early next week.

No corrections needed, site is in compliance.
ESC15-00320 General Inspection3/10/20163/10/20163/10/2016 9:06:08 AM PASS