ESC19-00303
| General Inspection | 3/11/2020 | 3/11/2020 | | P | |
|
|
|
ESC19-01138
| BMP Violation | 3/10/2020 | 3/12/2020 | 3/16/2020 2:14:47 PM | P | PASS |
|
|
Trash picked up, sidewalk and gutter have been cleaned. Crews parking on street. Placed gutter bag checks along Crestwood. Site conditions are much improved but will need daily monitoring and clean up by RP and onsite subcontractors.
|
ESC19-00156
| BMP Violation | 3/10/2020 | 3/12/2020 | 3/16/2020 2:14:26 PM | P | PASS |
|
|
3 PM no trash, mud out of gutter, DI bag fixed
Trash picked up, sidewalk and gutter have been cleaned. Crews parking on street. Placed gutter bag checks along Crestwood. Site conditions are much improved but will need daily monitoring and clean up by RP and onsite subcontractors.
|
ESC17-00842
| General Inspection | 3/12/2020 | 3/12/2020 | 3/16/2020 12:21:10 PM | | FAIL |
|
|
BMP maintenance needed on sediment bags.
Need to address erosion occuring on lot 3.
Syman doing inspections for Coleman Homes, CGP is not terminated, temporary BMPs still installed. Not all lot vegetated.
No response from Coleman Homes
Here is link to Syman Inspections:
https://drive.google.com/drive/folders/1bx88kw0IpNGE4OXKvzsSqfOQ7rwGtiQ5
|
ESC19-00529
| Aging Inspection | 3/12/2020 | 3/12/2020 | 3/12/2020 3:50:52 PM | | CANC |
|
|
rescheduled for site final
|
ESC17-01104
| General Inspection | 3/12/2020 | 3/12/2020 | 3/12/2020 8:24:57 AM | | CANC |
|
|
|