Inspections for the day of: Wednesday, March 13, 2019.
Number of inspections: 15
Percentage of inspections complete: 80 %
Percentage of inspections not complete: 20 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC17-01749 General Inspection3/7/20193/7/2019   
ESC16-00225 General Inspection3/7/20193/7/2019 P 
ESC17-00791 General Inspection3/6/20193/7/2019 P 
ESC18-00558 General Inspection3/13/20193/13/20193/19/2019 2:26:21 PM PASS
Front yard landscaped. Backyard not yet stabilized.
ESC18-01071 General Inspection3/12/20193/13/20193/15/2019 3:21:13 PMPCANC
ESC18-01433 General Inspection3/13/20193/13/20193/14/2019 3:29:35 PMPCANC
ESC17-01680 Aging Inspection3/13/20193/13/20193/14/2019 3:24:46 PM CANC
ESC17-01656 Aging Inspection3/13/20193/13/20193/14/2019 3:24:28 PM CANC
ESC18-01506 General Inspection3/13/20193/13/20193/13/2019 5:29:56 PMPPART
No trackout or discharges from site. Posted new ESC permit on trash bin.

Corrections needed:

- pick up loose trash around site
- remove full concrete washout and other debris/material off of the canal/ditch ROW.
- provide new concrete washout containment
- sweep shoulder of Garden street in front of projects

Correction notice posted on garage door. Compliance date 3/19 12 PM. Follow up scheduled.
ESC18-01191 General Inspection3/13/20193/13/20193/13/2019 5:25:12 PMPPART
No trackout or discharges observed. Storm drain has sediment bag installed. Most trash is picked up.

Corrections needed:
- sweep gutter on Rim Street
- provide new concrete washout for upcoming flat work
- pick up any loose trash around site
- check storm drain bag for maintenance

Posted correction notice on adjacent project (same builder/RP). Compliance date Tuesday 3/19 12 PM
ESC19-00218 Site Preparation3/12/20193/13/20193/13/2019 9:54:28 AMAPASS
Brandon Phone #: ###-####

Onsite meeting with onsite project manager Doug. w/ Beniton (884.0027)

Two new ADA ramps and exterior sewer line trenching associated with new bathroom.

Project to begin tomorrow.
- Post ESC sign on Beniton sign.
- supress any significant demolition dust sources
-provide concrete washout
- protect storm drain in parking lot on NE side of building.
- call for site final when complete, cleaned, and stabilized.

Approved for construction.
ESC18-00597 General Inspection3/13/20193/13/20193/13/2019 8:16:09 AM CANC
ESC18-00596 General Inspection3/13/20193/13/20193/13/2019 8:15:52 AM CANC
ESC18-00596 DOC - Permit Finaled3/13/20193/13/20193/13/2019 8:15:46 AMPPASS
ESC18-00597 DOC - Permit Finaled3/13/20193/13/20193/13/2019 8:15:40 AMPPASS