ESC13-00655
| General Inspection | 3/20/2015 | 3/20/2015 | 3/20/2015 3:52:40 PM | P | PART |
|
|
Correction:
Do final sweep of parking lots with all unit finished.
Biltmore supervisor Pat stated that sweeping will be done on Monday concurrently with parking spot striping.
Streets and gutters are fairly clean, DIs have filter bags installed and with remaining capacity.
|
ESC14-00830
| DOC - Permit Finaled | 3/20/2015 | 3/20/2015 | 3/20/2015 3:36:48 PM | P | PASS |
|
|
Construction for carport is complete. Striping and final sweep up is to covered under ESC13-00655
|
ESC14-00829
| DOC - Permit Finaled | 3/20/2015 | 3/20/2015 | 3/20/2015 3:36:14 PM | P | PASS |
|
|
Construction for carport is complete. Striping and final sweep up is to covered under ESC13-00655
|
ESC14-00500
| General Inspection | 3/20/2015 | 3/20/2015 | 3/20/2015 3:27:25 PM | | PASS |
|
|
4-plex complete and surrounding areas are landscaped. Parking area in front of unit has been cleaned. WIP on adjacent unit so some sweep up will be required for that.
ESC permit conditions satisfied.
|
ESC14-00500
| DOC - Permit Finaled | 3/20/2015 | 3/20/2015 | 3/20/2015 3:27:09 PM | P | PASS |
|
|
|
ESC13-00344
| General Inspection | 3/20/2015 | 3/20/2015 | 3/20/2015 2:47:15 PM | | PASS |
|
|
Boulder Heights #5 has SFH projects in progress and final stormwater pond stabilization through vegetation. No correction at this. JH working on preparation for for phase #6 construction.
|
ESC13-01247
| General Inspection | 3/20/2015 | 3/20/2015 | 3/20/2015 1:37:41 PM | | PASS |
|
|
Hillside vegetation is growing well. Wattles still installed and containing sediment. Drop inlet is clean. Will soon be ready to final ESC permit.
|
ESC14-00969
| Aging Inspection | 3/20/2015 | 3/20/2015 | 3/20/2015 11:51:23 AM | | PASS |
|
|
WIP on townhome remodel. Materials stored on paved driveway; no trackout or runoff into street or gutter. No corrections.
|
ESC14-00938
| Aging Inspection | 3/20/2015 | 3/20/2015 | 3/20/2015 11:06:16 AM | | PASS |
|
|
Home construction is complete, but need to landscape and stabilize to close ESC permit.
No trackout or sediment leaving site and it is graded for landscaping to be installed.
Need to clean stucco waste collected on adjacent lot.
|
ESC14-00657
| Random Inspection | 3/20/2015 | 3/20/2015 | 3/20/2015 11:01:52 AM | A | PASS |
|
|
River Heights #6 has curbing and storm drains installed. Road base is ready for paving/asphalt next week.
Cement curb washout was done in 3 Eco-pan containers that are soon to be serviced.
Silt fence has been removed to install sidewalk/landscaping along Warm Springs. No trackout, windblown trash, or hillside erosion. Permit is posted and SWPPP is on site.
|
ESC14-00960
| Site Final | 3/19/2015 | 3/20/2015 | 3/20/2015 10:23:42 AM | A | FAIL |
|
|
Still need to remove inlet filter bag. Another request put into Brett at CBH to remove inlet. Site is clean and no sediment in gutter, but need to take out stormdrain inlets in Trailside Place II that are no longer necessary to catch construction site sediment.
|
ESC14-00514
| General Inspection | 3/20/2015 | 3/20/2015 | 3/20/2015 10:16:06 AM | | PART |
|
|
Construction complete and site has been landscaped and hard surfaces swept. Silt fence BMP has been removed and vegetation/sage brush was preserved on the hillside.
1 correction: Remove DI filter bags (2) on McGregor when removing EKC sign. Both bags are still in good condition.
|
ESC14-01030
| General Inspection | 3/20/2015 | 3/20/2015 | 3/20/2015 10:10:13 AM | A | PASS |
|
|
WIP on warehouse. Permit posted, BMPs installed included hillside silt fence, construciton entrance, concrete washout container, and DI protection on McGregor.
Trash is contained and materials consolidated. Very clean site, no trackout or discharges.
|
ESC15-00304
| Site Preparation | 3/19/2015 | 3/20/2015 | 3/20/2015 9:50:07 AM | A | PASS |
|
|
Zack-would like as early as possible Phone #: ###-####
Major home interior remodel - work in progress from prior permit with no building addition. Permit modified to add new kitchen space.
Permit clearly posted, trash container on site - stockpile. No MS4 inlet adjacent to site and work area is 30 ft from road with vegetative buffer. Site is clean, main BMP will be housekeeping. Approved.
|
ESC14-00752
| General Inspection | 3/20/2015 | 3/20/2015 | 3/20/2015 9:31:07 AM | | PASS |
|
|
|
ESC14-00966
| Aging Inspection | 3/20/2015 | 3/20/2015 | 3/20/2015 8:32:55 AM | | PASS |
|
|
Snake River Tearoom TI complete and business open. Construction materials and loose sediment removed from site. ESC permit finaled.
|
ESC14-00966
| DOC - Permit Finaled | 3/20/2015 | 3/20/2015 | 3/20/2015 8:32:06 AM | P | PASS |
|
|
|