Inspections for the day of: Tuesday, March 26, 2019.
Number of inspections: 24
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC18-01432 General Inspection3/26/20193/26/20194/1/2019 12:51:43 PMPPASS
ESC19-00133 BMP Violation3/21/20193/26/20193/28/2019 5:18:07 PMPPASS
Site cleaned up.
ESC18-01515 BMP Violation3/18/20193/26/20193/28/2019 5:14:54 PMAPASS
Streets and sidewalks were swept. Inlet fabic installed on Hilton and trash has been picked up around sites.

Site is still on warning for more frequent housekeeping.
MIS19-00074 ESC-Conference3/20/20193/26/20193/28/2019 5:13:29 PMAFAIL
NO trash or demolition debris picked up as requested.
ESC18-01197 BMP Violation3/21/20193/26/20193/28/2019 5:10:40 PMAFAIL
follow up

No trash and demolition debris picked up.
ESC18-01228 General Inspection3/21/20193/26/20193/28/2019 4:35:59 PMPPASS
follow up

Trash picked up. Erosion issue not yet addressed. No new corrections.
ESC17-00954 General Inspection3/26/20193/26/20193/28/2019 3:56:05 PMPPEND
Corrections and report detailing corrective actions received. Inspection of subdivsion during rain event showed that changes were effective.

Full walk through inspeciton scheduled.
ESC18-01244 Complaint Inspection3/26/20193/26/20193/28/2019 3:54:21 PMPFAIL
Roof top runoff causing onsite erosion and offsite sediment runoff to street and gutter.

RP-GC needs to correct and schedule conference.
ESC18-00243 Aging Inspection3/26/20193/26/20193/28/2019 3:50:38 PM PASS
ESC18-00242 Aging Inspection3/26/20193/26/20193/28/2019 3:49:47 PM PASS
ESC18-00239 Aging Inspection3/26/20193/26/20193/28/2019 3:49:36 PM PASS
WIP. Trash contained. No trackout.
ESC16-00242 General Inspection3/26/20193/26/20193/28/2019 8:20:25 AM CANC
ESC17-01755 General Inspection3/26/20193/26/20193/26/2019 10:43:11 PM CANC
see ESC17-01754
ESC17-01200 General Inspection3/26/20193/26/20193/26/2019 10:41:46 PM CANC
ESC18-01179 Site Final3/26/20193/26/20193/26/2019 4:06:58 PMPPASS
Home complete and landscaped. Subdivisoin BMPs to remain installed. ESC permit finaled.
ESC18-00709 Site Final3/26/20193/26/20193/26/2019 3:48:06 PMPPASS
Home complete and landscaped. Subdivisoin BMPs to remain installed. ESC permit finaled.
ESC18-00649 Site Final3/25/20193/26/20193/26/2019 3:45:43 PMPPASS
Home complete and landscaped. Subdivsion BMPs to remain installed.
ESC18-00296 Site Final3/26/20193/26/20193/26/2019 2:50:32 PMPPASS
Home complete and landscaped. Subdivisoin DI bags to be removed once construction on Rivernest in Barber Junction is complete.
ESC18-00207 Site Final3/26/20193/26/20193/26/2019 2:50:20 PMPPASS
Home complete and landscaped. Subdivisoin DI bags to be removed once construction on Rivernest in Barber Junction is complete.
ESC18-00206 Site Final3/26/20193/26/20193/26/2019 2:50:07 PMPPASS
Home complete and landscaped. Subdivisoin DI bags to be removed once construction on Rivernest in Barber Junction is complete.
ESC18-01597 General Inspection3/19/20193/26/20193/26/2019 2:20:37 PMPPEND
follow up

corrections not completed. No new issues. Subdvision landscaping using stockpile and causing minor trackout from stockpile.
ESC18-00667 General Inspection3/26/20193/26/20193/26/2019 2:12:44 PMPFAIL
Landscapers driving equipment through open lots in subdivsion causing trackout and potential future erosion issues.

Alerted subdivsion RP. Appears could be for SFH project.
ESC18-01266 BMP Violation3/26/20193/26/20193/26/2019 12:37:08 PMPFAIL
Concrete washout dumped onto pile of loose trash. Trackout from site.

Multiple warning have been issued at this site.

Parcel hold and re-inspection fee issued.
ESC18-01020 BMP Violation3/26/20193/26/20193/26/2019 12:36:52 PMPFAIL
Concrete washout dumped onto pile of loose trash. Trackout from site.

Multiple warning have been issued at this site.