ESC15-01210
| General Inspection | 3/27/2018 | 3/27/2018 | 3/29/2018 4:30:42 PM | P | PEND |
|
|
email request to developer to remove full DI bags from lower section of Shermn Hollow to prevent water flowing down into the Northend.
|
ESC16-01512
| General Inspection | 3/27/2018 | 3/27/2018 | 3/29/2018 1:44:52 PM | | CANC |
|
|
rescheduled
|
ESC17-01293
| General Inspection | 3/12/2018 | 3/27/2018 | 3/28/2018 10:09:00 AM | P | PASS |
|
|
Permit sign posted. WIP on foundation. No trackout. Stormwater is retained on site.
|
ESC17-00426
| BMP Violation | 3/26/2018 | 3/27/2018 | 3/27/2018 6:24:35 PM | P | PEND |
|
|
No overflowing trash bins or sites with no trash bin found in subdivsion. Warning email was sent on Friday 3/23.
Lots of loose dirt on sidewalks and streets due to mulitple sites landscaping at once. Will check for clean up at end of week.
|
ESC17-00954
| Conference | 3/27/2018 | 3/27/2018 | 3/27/2018 6:21:01 PM | P | PEND |
|
|
On site compliance conference and site walk through with RSCI project RP John.
Clean up efforts and earthwork for new erosion and sediment controls in progress.
Corrections discussed with project RP:
- continue to work with neighbor on clean up of mud and repair of front yard affected by silt and drying of crawl space. - reshaping and removal of dirt above retaining wall is in progress. A interception diversion trench will direct water to the temporary holding pond. - bottom temporary holding pond containment berm is being lined with geotextile and increased in height - change out DI bags installed @ Winsome and Bogus Basin. Clean up around drains. - install larger rock check dams on the road to slow down runoff. Must runoff water causing issues is from the roadway. - dig trench to upper pond to reduce amount of water going to lower temporary pond
- a meeting is to be scheduled April 2-6 with Public Works Hillside & Drainage and neighbors to discuss the permanent drainage plan and controls to prevent further flooding.
|
ESC18-00163
| BMP Violation | 3/26/2018 | 3/27/2018 | 3/27/2018 6:13:04 PM | P | PEND |
|
|
No trash issues. Trash has been emptied.
Permit sign posted.
Landscaping projects in progress so lots of dirt on Portsmouth.
Need to get Asbury to have their own RP.
|
ESC16-00955
| Complaint Inspection | 3/27/2018 | 3/27/2018 | 3/27/2018 5:48:11 PM | P | FAIL |
|
|
Sediment runoff from unstabilized yard.
Corrections requested to Urban Nuance construction at site:
- complete job of sweeping loose dirt on sidewalk and gutter adjacent to parcel - install perimeter wattle along the corner section of lot at Hill Road & Collister. - install energy dissipation or water containment on gutter down spouts to prevent erosion. Find temporary solution until rain harvesting barrels have arrived for installation. - clean up dirt accumulated behind gator guard wattle
Note: - ACHD ped ramp contractor dumped washout on adacent lot. - lot is source of muddy runoff as well, need to request site improvements to prevent further erosion in this area.
|
ESC17-01319
| BMP Violation | 3/27/2018 | 3/27/2018 | 3/27/2018 5:48:10 PM | P | CANC |
|
|
|
ESC17-01527
| BMP Violation | 3/27/2018 | 3/27/2018 | 3/27/2018 4:10:17 PM | P | FAIL |
|
|
Trash box is clean.
Violations: - no ESC permit sign posted - dirty sidewalk and gutter
|
ESC17-01107
| DOC - Permit Finaled | 3/27/2018 | 3/27/2018 | 3/27/2018 4:09:18 PM | P | PASS |
|
|
|
ESC17-00660
| Site Final | 3/27/2018 | 3/27/2018 | 3/27/2018 4:06:36 PM | P | PASS |
|
|
Home complete, landscaped, and occupied.
|
ESC17-00140
| General Inspection | 3/27/2018 | 3/27/2018 | 3/27/2018 4:06:10 PM | | PASS |
|
|
No trackout, no sediment runoff from site. Site is clean.
|
ESC17-00473
| DOC - Permit Finaled | 3/27/2018 | 3/27/2018 | 3/27/2018 3:45:57 PM | P | PASS |
|
|
demo complete, active construction site by Syringa, see ESC17-00836
|
ESC17-00490
| Aging Inspection | 3/27/2018 | 3/27/2018 | 3/27/2018 1:03:44 PM | | PASS |
|
|
|
ESC17-00490
| DOC - Permit Finaled | 3/27/2018 | 3/27/2018 | 3/27/2018 1:03:39 PM | P | PASS |
|
|
|