Inspections for the day of: Wednesday, March 28, 2018.
Number of inspections: 16
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC17-00406 General Inspection3/28/20183/28/20184/4/2018 2:54:24 PM CANC
rescheduled
ESC13-01279 General Inspection3/27/20183/28/20184/2/2018 2:41:12 PMAPASS
trash etc

Trash in drain area and wooded area at NE corner of project has been picked up.
ESC17-00102 General Inspection3/26/20183/28/20183/30/2018 2:10:08 PMPPART
Site condiitions have not gotten worse.

WIP on pouring sidewalks. Still significant amout of loose dirt and dirt piles on perimeter of Bird STreet. All DIs have sediment bags installed.

Correction request:
- pick up trash next to ESC permit sign board
- sweep north end of Bird STreet and push dirt back towards site. Clean around sediment bags in storm drain.
ESC17-00748 Tracking Control3/26/20183/28/20183/30/2018 1:46:05 PMPPART
New rock installed at entrance. Rock is round and not angular, unable to tell if fabric is underneath.

Trackout from apron and loose dirt in the gutter.

Warned about stockpiles being source of dust. Need to stabilize or move. Stated they need to be screened and dirt will be reused.

ESC17-00026 Site Final3/7/20183/28/20183/30/2018 9:48:44 AMAPASS
Temporary sediment bag in receiving storm drain removed. ESC permit conditions satisfied.
ESC18-00264 Tracking Control3/27/20183/28/20183/29/2018 5:06:45 PMAPASS
Trackout cleaned up. Permit sign posted. Crews onsite.

Reviewed next step of hillside erosion installment and placement of check dams on the driveway to slow velocity of runoff.

Approved for now

ESC16-01553 Conference3/28/20183/28/20183/29/2018 4:29:23 PMPDONE
1:30 Discuss erosion occruing along lot line

RP Bobby has cleaned up loose dirt on sidewalk. Trench to deliver water has been filled in with rock. Correction request to install hillside wattles to slow velocity of runoff before entering the rock channel.
ESC17-00441 Aging Inspection3/28/20183/28/20183/28/2018 1:16:44 PM CANC
ESC17-01362 Conference3/28/20183/28/20183/28/2018 1:13:52 PMPDONE
RP called to notify that intial excavation for sewer and water has some dewatering required. Onsite infiltration pit has been dug to remove water. Plans for offsite discharge are not yet confirmed.

Notified him about ACHD dewatering permit and turbidity standards in going offsite. Inspection scheduled to review dewatering plans onsite either today or tomorrow.
ESC17-00954 Conference3/28/20183/28/20183/28/2018 12:40:57 PMPDONE
Neighbor at 3317 Winsome below the subdivsion notified ESC Inspectors he would hold the City liable if his basement is flooded due to runoff from this site.

Follow up ESC inspection schedule to make sure RSCI is continuing work on site to increase retention of water on site, slow down runoff velocity, and allow settling to discharge clean water to gutter and not neighboring properties.
ESC16-01553 General Inspection3/28/20183/28/20183/28/2018 11:11:42 AM CANC
ESC17-00149 Conference3/28/20183/28/20183/28/2018 11:03:54 AMPCANC
ESC17-00149 Conference3/28/20183/28/20183/28/2018 10:54:32 AMPPEND
Request to stabilize adjacent lot and pull 1st down stream DI bag from site. Notified that ESC permit is still open and needs site final.
ESC17-01527 BMP Violation3/27/20183/28/20183/28/2018 10:44:56 AMAPEND
Correction request left on RP voicemail to post ESC permit signs on Core Building sites in Millwell.
ESC17-00383 General Inspection3/28/20183/28/20183/28/2018 10:10:54 AM PASS
Construction complete, BLD finaled. No ESC issues. Permit finaled.
ESC17-00383 DOC - Permit Finaled3/28/20183/28/20183/28/2018 10:10:16 AMPPASS