ESC19-00574
| General Inspection | 3/3/2020 | 3/3/2020 | 3/4/2020 8:25:05 AM | | PASS |
|
|
Construction entrance, perimeter controls, concrete washout are all installed and in use. No trackout or fugitive dust occuring.
Dewatering in progress, next week they will be digging down further for the sewer lift station so dewatering activity will change.
SWPPP inspections, turbidity log, and grading and stabilization log are being completed.
Requests:
- add baffles to dewatering basin; have an extra pit for excavation water to not mix with the deep well point water
- move SWPPP sign and board to the front of the project, currently on the Lander side of site
Noified RP Dustin
|
ESC17-01088
| General Inspection | 3/3/2020 | 3/3/2020 | 3/4/2020 8:20:25 AM | | PASS |
|
|
No activity. 2 open lots remain. No active construction. Storm drains have sediment protection still installed. Going to request to developer to remove sign and storm drain bags
|
ESC19-00371
| General Inspection | 3/3/2020 | 3/3/2020 | 3/3/2020 2:42:07 PM | P | PASS |
|
|
Minor activity prepping sidwalk and gutter areas on upper section.
NO trackout or discharges from site. Dry conditions.
Corrections needed:
- repair/reinstall silt fence below main entrance & above phase 6 pond - pick up loose trash at the discharge point. Stuck in bushes - remove dewatering bag
|
ESC19-01083
| Site Final | 3/3/2020 | 3/3/2020 | 3/3/2020 10:44:26 AM | P | PASS |
|
|
Home complete and landscaped. No ESC requests
|
ESC19-00534
| Site Final | 3/3/2020 | 3/3/2020 | 3/3/2020 10:43:54 AM | P | PASS |
|
|
Home complete and landscaped. No ESC requests
|
ESC19-00935
| General Inspection | 3/3/2020 | 3/3/2020 | 3/3/2020 10:36:41 AM | P | PART |
|
|
No activity, no trackout. Dry conditions. No wind blown dust observed at time of construciton.
Corrections needed: - updated construction schedule - stabilize stockpile or become active. Beyond stockpile stabilization deadline - install new construction entrance prior to resuming grading activity
Notified RP John. He will provide updates and schedule on corrections.
Follow up inspection scheduled
|
ESC18-00659
| General Inspection | 3/3/2020 | 3/3/2020 | 3/3/2020 9:58:15 AM | | PEND |
|
|
BMPs installed on frontage lot; not yet stabilized
|
ESC19-00972
| DOC - Permit Finaled | 3/3/2020 | 3/3/2020 | 3/3/2020 8:02:11 AM | P | PASS |
|
|
see ESC18-00659 for rest of King Street/Fairview apartment inspections
|