Inspections for the day of: Thursday, March 31, 2016.
Number of inspections: 23
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC15-00033 General Inspection3/23/20163/31/20164/1/2016 10:15:52 AMPPASS
Check if Gratz needs sweeping and parking lot is done....

WIP on final grading prep for asphalt. Sweeping will be next week. No trackout outside of auto mall area, minor trackout within. DIs have sediment protection.
ESC15-01532 General Inspection3/31/20163/31/20163/31/2016 4:42:09 PMPPASS
WIP on path. Bridge & tunnel work on Fairview and Main has clean staging areas with no discharges or trackout. DIs have inlet protect.

Silt fence is still installed between path and river. No corrections issued at this time.
ESC15-00468 General Inspection3/31/20163/31/20163/31/2016 4:30:16 PM PASS
Foundation and slab is in progress. Street, sidewalk, & gutter clean. No corrections at this time.
ESC15-00541 Random Inspection3/31/20163/31/20163/31/2016 4:01:17 PMPPASS
New construction entrance has been installed. No trackout observed. Corrections were made as requested.

The cut hillsides have been hydroseeded. Utilities installed, but no road yet.
ESC15-00853 General Inspection3/31/20163/31/20163/31/2016 3:55:01 PM PASS
WIP. No trackout or discharges. BMPs are installed, permit sign posted. Very clean site with good stockpile management.

No corrections at this time.
ESC14-01063 General Inspection3/31/20163/31/20163/31/2016 3:54:10 PM PASS
BMPs installed. No significant acitivity. Lots to be re-graded where damaged and tested for proper compaction per PW hillside. Retention & diversion berms are to remain.
ESC15-00857 General Inspection3/31/20163/31/20163/31/2016 3:52:25 PM PASS
No significant construction at site has occured. In process of getting highway district approval to finish roads. Slopes a re-vegetating well. No violations observed.

Correction to be discussed with RP next week is fixing the slope drain inlet at the end of Arrow Villa to connect runoff to the temporary retention pond/ sediment trap.
ESC15-01060 General Inspection3/31/20163/31/20163/31/2016 3:15:46 PMPPASS
Silt fence around home is re-installed properly. Numerous wattle and rock check dam have been installed on the cut area where water is running down hill.

Need to install roof top gutters and drainage system to prevent future problems.

Deposited sediment and sand has been swept up. Some erosion on access road below driveway entrance has pre-existing erosion rills and lack of stormwater conveyance.
ESC15-01193 General Inspection3/31/20163/31/20163/31/2016 3:12:02 PMPPASS
WIP on frame. Permit sign posted. Existing vegetation has been preserved around home footprint. No trackout. Approved.
ESC15-00957 Random Inspection3/31/20163/31/20163/31/2016 2:59:21 PMPPASS
WIP on SFHs by Zach Evans Construction and Tahoe. Lined washouts being used, trash contained, and DI bags are installed. No major trackout. No spills or discharges.
ESC16-00084 Site Preparation3/31/20163/31/20163/31/2016 2:58:12 PMPPASS
Access driveway for 2 parcels installed, can be used for parking and staging to limit trackout. Foundation has been dug. Warning given to contractor regarding trackout prior to permit being issued and picked up.

No violations. Approved to continue. Flat, low risk site.
ESC15-00509 General Inspection3/31/20163/31/20163/31/2016 2:30:14 PM PART
WIP on large home interior. Need to sweep up gravel from unfinished driveway that is in round about. No other issues observed.
ESC14-01011 General Inspection3/31/20163/31/20163/31/2016 2:02:19 PM PASS
WIP on interior. Yard and driveway not yet complete. Pool in progress as well. Most contractors parking on street, limited trackout. Down gradient DIs have sediment filter bags installed. Approved.
ESC14-00588 General Inspection3/31/20163/31/20163/31/2016 12:41:50 PMPPASS
Conference inspection requested to inspect area where swale and water feature is to be installed conducted. Irrigation water will start to flow through this area this weeked due to early strart of season.

To limit the disturbance by the flow, requested that the piped irrigation outlet discharge into a section of rip rap before entering the the swale currently being excavated. The swale will infiltrate and settle some of the water and overflow from swale will going into a river-rocked spillway to the vegetated bank and flow into Logger's Creek. I requested that the initial flow be monitored to check for turbidity issues and possible corrections.

RP stated that Parkcenter gutters in both directions will be swept by a street sweeper tomorrow.

Will check back early next week to check on the swale area
ESC15-01397 General Inspection3/31/20163/31/20163/31/2016 12:33:49 PMPPASS
WIP on school remodel. No trackout to Parkcenter observed, staging area is cleab,

No corrections issued.
ESC13-00684 General Inspection3/31/20163/31/20163/31/2016 11:11:46 AM PASS
ESC16-00255 Site Preparation3/30/20163/31/20163/31/2016 10:31:54 AMAPASS
Inspection requested via web by Kyle Buzzell

Approved for construction.

Storm drain inlets have filter bags that are in good condition. A new lined washout box has bee provided for new foundations on southwest side of Frontrunner.

Walked the swale in the park, no windblown trash or debris issues, outlets from the site's stormwater treatment system are fairly clean.

Weekly sweeping and frequent trash haul off should continue.
ESC16-00274 Site Preparation3/30/20163/31/20163/31/2016 10:30:59 AMAPASS
Inspection requested via web by Kyle Buzzell

Approved for construction.

Storm drain inlets have filter bags that are in good condition. A new lined washout box has bee provided for new foundations on southwest side of Frontrunner.

Walked the swale in the park, no windblown trash or debris issues, outlets from the site's stormwater treatment system are fairly clean.

Weekly sweeping and frequent trash haul off should continue.
ESC16-00275 Site Preparation3/30/20163/31/20163/31/2016 10:30:34 AMAPASS
Inspection requested via web by Kyle Buzzell

Approved for construction.

Storm drain inlets have filter bags that are in good condition. A new lined washout box has bee provided for new foundations on southwest side of Frontrunner.

Walked the swale in the park, no windblown trash or debris issues, outlets from the site's stormwater treatment system are fairly clean.

Weekly sweeping and frequent trash haul off should continue.
ESC15-01299 General Inspection3/31/20163/31/20163/31/2016 10:01:07 AMPPASS
WIP. No trackout. Trash and materials contained. No corrections.issued, site in compliance.
ESC15-01183 Aging Inspection3/31/20163/31/20163/31/2016 9:56:23 AM PASS
SFH demo complete and associated permit finaled. New SFH in progress under ESC15-01299
ESC15-01183 DOC - Permit Finaled3/31/20163/31/20163/31/2016 9:55:16 AMPPASS
ESC15-00543 General Inspection3/31/20163/31/20163/31/2016 8:50:16 AM PASS
WIP on interior. No violations. Many contractors on site - project near completion.