Inspections for the day of: Monday, March 6, 2017.
Number of inspections: 14
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC16-01459 Site Preparation2/27/20173/6/20173/8/2017 7:45:46 AMACANC
Follow up concrete washout/slurry
ESC16-00096 General Inspection3/6/20173/6/20173/8/2017 7:45:17 AM CANC
ESC16-01645 Site Preparation3/3/20173/6/20173/7/2017 5:04:16 PMPCANC
ESC16-01487 General Inspection3/1/20173/6/20173/7/2017 4:38:08 PMAPEND
milwell phase 2 - this is the ESC permit for the previous home demolitiion by same developer.

Trackout to Saxton has been cleaned.

Corrections still needed:

- submit SWPPP for review and get ESC permit issued for prep and irrigation pipe installation.
- post CGP tracking # and info
ESC16-00168 General Inspection3/6/20173/6/20173/7/2017 8:00:51 AM CANC
No activity at site. Wetland area relocation complete, will check for re-establishment next inspection. No issues reported at site.
ESC16-00276 General Inspection3/6/20173/6/20173/6/2017 3:46:04 PM PEND
Working on corrections with SFH builder Eagle Energy Concepts and Wood Bros. excavation to get regular sweeping schedule on Tahiti. Subdivision development complete.
ESC15-01218 Aging Inspection3/6/20173/6/20173/6/2017 3:43:22 PM PASS
ESC17-00018 General Inspection3/6/20173/6/20173/6/2017 2:56:15 PMPPASS
Dewatering system for installation of stormwater ponds is now turned off. Remaining water draining into Walling Creek is clear. WIP by Higrade, who is dewatering into stormwater ponds with no offsite discharge. No violations observed, no corrections requested at this time.
ESC16-01561 General Inspection3/6/20173/6/20173/6/2017 2:49:21 PMPFAIL
Dewatering check up...

Dewatering stopped over weekend and has resumed today. Extra water onsite continues to overwhelm the land application & infliltration area. 3 discharges points occuring, the discharge outlet closest to construction area and away from Parkcenter Bridge has a turbid discharge with visible flume in Walling Creek wetland.

Notified RP to come onsite to superivise corrections. Notified Brown Consruction foreman of issue and requested to close off this outlet with issues and/or install extra filtering & damming BMPs . Brown stated turbidity samples were taken this morning...

Investigation and corrective actions in progress.
ESC16-01401 BMP Violation3/6/20173/6/20173/6/2017 1:50:34 PMPFAIL
Corrections needed:

- re-install perimeter sediment control
- clean loose dirt and mud accumulated in gutter and storm drain filter mat
- re-install sediment protection on storm drains
- sweep sidewalks & service trash receptacle.
ESC15-00977 Aging Inspection3/6/20173/6/20173/6/2017 1:39:27 PM CANC
ESC16-00945 General Inspection3/6/20173/6/20173/6/2017 12:19:30 PMAPASS
Site currently inactive to allow drying out. Retaining wall, stormwater facility and sewer installed. No roads or gutters. Silt fence perimeter is containing loose dirt and protecting properties below site. Wire back sitl fence was good choice. Lined concrete washout on site, permit sign posted on job trailer. No trackout or discharges. No corrections at this time.
ESC15-00306 General Inspection3/6/20173/6/20173/6/2017 9:03:39 AM PASS
No construction activity occuring. Unfinished area along river bank currently submerged due to high river levels.
ESC16-00522 General Inspection3/6/20173/6/20173/6/2017 8:09:22 AM CANC
rescheduled for site final