MIS19-00074
| ESC-Conference | 3/28/2019 | 4/1/2019 | 4/3/2019 12:32:48 PM | P | PEND |
|
|
Todd Campbell construction is aware that the pile needs to be removed, but ground has been very wet and soft and not good for work to occur.
2 week follow up scheduled.
|
ESC18-00079
| General Inspection | 4/1/2019 | 4/1/2019 | 4/2/2019 1:51:11 PM | | PASS |
|
|
Needs landscaping on terrace areas above walls. BLD permit still active. No sediment runoff issues.
|
ESC18-01119
| Site Preparation | 3/29/2019 | 4/1/2019 | 4/2/2019 10:09:26 AM | A | PASS |
|
|
Review site to remove SWO. Permission granted for drywall work to occur this weekend.
SWO removed. Site cleaned up and fencing re-installed. Warning to not trespass into the open space easement.
|
ESC18-00983
| General Inspection | 4/1/2019 | 4/1/2019 | 4/1/2019 12:40:32 PM | P | FAIL |
|
|
Corrections needed: - sweep shoulder and entrance at Holcomb - repair barrow ditch erosion occuring at top portion of site (west boundary) that directs water down the corner of the cut slope. - maintain any loose or displaced wattles - remove or stabilize large stockpiles. - make sure that berm at top of slope is intact and level across the entirere length - smooth out tire ruts that channels and concentrates sheet flow - fix erosion at the northeast corner of site above the bend in Holcomb Road.
RP steve states that erosion repairs and wattle maintenance are to occur this week. Will schedule a follow up site walk. Verbal correction requests to Steve.
|
ESC17-01693
| BMP Violation | 4/1/2019 | 4/1/2019 | 4/1/2019 11:52:26 AM | P | FAIL |
|
|
Multiple violations: - trackout, dirt, and debris on sidewalk, gutter, and bike lane. - no regular housekeeping - no stabilized entrance
Correction Notice posted. Multiple failed inspections at this site, next Fail will result in a SWO.
VM to owner-RP left.
Follow Up Wednesday AM.
|
ESC17-01346
| General Inspection | 4/1/2019 | 4/1/2019 | 4/1/2019 11:17:17 AM | | PASS |
|
|
No trackout. Clean site. Storm drains have sediment protection.
|