ESC17-00223
| BMP Violation | 4/7/2017 | 4/10/2017 | 4/17/2017 4:35:18 PM | P | PART |
|
|
Mud and dirt has been removed from sidewalk. No new trackout.
Correction request to sweep street and change out DI bags at south end of Hacienda.
|
ESC17-00044
| BMP Violation | 4/7/2017 | 4/10/2017 | 4/17/2017 4:35:06 PM | P | PART |
|
|
Mud and dirt has been removed from sidewalk. No new trackout.
Correction request to sweep street and change out DI bags at south end of Hacienda.
|
ESC16-01455
| BMP Violation | 4/7/2017 | 4/10/2017 | 4/17/2017 4:34:51 PM | P | PART |
|
|
Mud and dirt has been removed from sidewalk. No new trackout.
Correction request to sweep street and change out DI bags at south end of Hacienda.
|
ESC17-00265
| General Inspection | 4/7/2017 | 4/10/2017 | 4/14/2017 3:43:15 PM | P | CANC |
|
|
|
ESC17-00257
| Site Preparation | 4/7/2017 | 4/10/2017 | 4/12/2017 10:54:10 AM | A | PASS |
|
|
Brett Phone #: ###-####
Permit sign posted. Down gradient storm drains at Sumpter have sediment protection installed. Active CBH homes in compliance. Approved.
|
ESC16-01513
| General Inspection | 4/7/2017 | 4/10/2017 | 4/12/2017 7:53:36 AM | P | CANC |
|
|
|
ESC15-00609
| Aging Inspection | 4/10/2017 | 4/10/2017 | 4/12/2017 7:50:21 AM | | PASS |
|
|
No activity, no pollutant generating construction activities remaining, site is stabilized and BLD finaled. ESC permit conditions satisfied.
|
ESC16-00955
| General Inspection | 4/10/2017 | 4/10/2017 | 4/11/2017 3:30:23 PM | P | PEND |
|
|
Onsite meeting with RP-GC. Discussed locations to install perimeter sediment controls. Two new retaining walls are to be installed along Collister sidewalk this week and next. Sidewalk has been swept. Will hold off on wattles in this area until after walls.
RP will install sediment control wattles along the SE corner or project area to capture runoff from this area. Will check next Tuesday for installation.
|
ESC17-00198
| Site Preparation | 4/7/2017 | 4/10/2017 | 4/11/2017 7:34:19 AM | P | PASS |
|
|
Inspection 4/10 PM. BMPs installed. Trackout from hauling operation has been cleaned. Permit sign posted.
|
ESC16-00434
| General Inspection | 4/10/2017 | 4/10/2017 | 4/11/2017 7:33:11 AM | | CANC |
|
|
|
ESC15-00094
| General Inspection | 4/10/2017 | 4/10/2017 | 4/11/2017 7:33:01 AM | | CANC |
|
|
|
ESC15-00811
| Aging Inspection | 4/10/2017 | 4/10/2017 | 4/10/2017 2:49:57 PM | | CANC |
|
|
Home complete, pool seperate, on further inspections on this permit.
|
ESC15-00811
| DOC - Permit Finaled | 4/10/2017 | 4/10/2017 | 4/10/2017 2:48:58 PM | P | PASS |
|
|
|
ESC17-00035
| Site Preparation | 4/10/2017 | 4/10/2017 | 4/10/2017 2:22:59 PM | P | PASS |
|
|
General Inspection, permit posted, no track out Check for new washout next inspection
|
ESC16-01354
| General Inspection | 4/10/2017 | 4/10/2017 | 4/10/2017 10:23:45 AM | P | PASS |
|
|
WIP on first and second levels of parking garage. No trackout from either entrance. RP on duty. Large lined concrete washout pit onsite. No corrections at this time, need to check construcrtion entrance on 11th next inspection. Parcel shared with Hilton Garden Inn, different contractor, see ESC16-01446.
|
ESC16-01446
| General Inspection | 4/10/2017 | 4/10/2017 | 4/10/2017 10:21:43 AM | A | PASS |
|
|
WIP on foundation and flat work. No trackout to to Myrtle or 13th. Permit sign and SWPPP info posted on 13th entrance. MS4 inlets have sediment protection installed. Parcel shared with Pioneer Crossing, see also ESC16-01354..
|
ESC16-00115
| Aging Inspection | 4/10/2017 | 4/10/2017 | 4/10/2017 10:02:26 AM | | PASS |
|
|
WIP. Driveway to backyard project area is paved. No trackout or sediment runoff. Approved. No activity on BLD since February 2016
|
ESC16-00405
| General Inspection | 4/10/2017 | 4/10/2017 | 4/10/2017 8:59:29 AM | | PASS |
|
|
Site work complete. Access roads and utilities are installed. Newly installed site stormwater system was fitted with DI filter bags.
Two seperate projects are now active at Emerald Station, Cascadia Healthcare ESC16-00676 and SARMC Emerald Clinic ESC16-01580, no further inspections required on this permit, permit finaled.
|
ESC16-00405
| DOC - Permit Finaled | 4/10/2017 | 4/10/2017 | 4/10/2017 8:55:14 AM | P | PASS |
|
|
|