Inspections for the day of: Tuesday, April 10, 2018.
Number of inspections: 14
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC17-01600 Site Preparation4/10/20184/10/20184/12/2018 2:53:08 PMPPEND
Site check for drainage concerns Phone #: ###-####

Luann - ###-#### adjacent property owner

Need to install roof drains
ESC17-00692 General Inspection4/6/20184/10/20184/12/2018 8:17:46 AMACANC
ESC18-00521 General Inspection4/3/20184/10/20184/12/2018 8:13:11 AMPCANC
ESC16-00489 General Inspection4/10/20184/10/20184/12/2018 8:12:22 AM CANC
ESC17-00063 General Inspection4/10/20184/10/20184/12/2018 8:12:10 AM CANC
ESC16-01232 General Inspection4/10/20184/10/20184/11/2018 4:04:02 PM PEND
revegetation still occuring @ back side along Shaw Mtn Road.
ESC18-00440 BMP Violation4/9/20184/10/20184/10/2018 4:35:06 PMAPEND
Onsite conference to reveiew ESC permit conditions and request installation of wattle below the stockpile. Stockpile is to be removed this week or next. Will be responsible for any post construction stabilization.
ESC18-00264 General Inspection3/29/20184/10/20184/10/2018 4:34:00 PMPPASS
WIP on hillside erosion controls. Check dams installed along unfinished driveway. DI bags down hill removed to capture all runoff from site in Sherman Hollow stormwater system.
ESC17-00072 Aging Inspection4/10/20184/10/20184/10/2018 10:58:34 AM PASS
ESC17-01701 General Inspection4/10/20184/10/20184/10/2018 10:28:08 AMACANC
duplicate entry
ESC17-01701 General Inspection4/10/20184/10/20184/10/2018 10:27:34 AMPPASS
WIP on Franklin Park. Sidwalk being poured, road is partially excavated for resurfacing. Concrete washout pan onsite and being used. No trackout or discharges observed.
ESC17-00842 Conference4/10/20184/10/20184/10/2018 8:26:25 AMPDONE
Site walk through with RP and Syman Company completed @ 2 PM Monday 4/9 to discuss corrective actions to prevent further sediment runoff and slow down runoff velocity. BMPs to be installed Tuesday PM and hydroseed on Wednesday.
ESC17-00591 General Inspection4/10/20184/10/20184/10/2018 8:08:40 AM CANC
ESC17-00779 Aging Inspection4/10/20184/10/20184/10/2018 8:08:03 AM CANC