Inspections for the day of: Tuesday, April 18, 2017.
Number of inspections: 20
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC17-00293 Site Preparation4/18/20174/18/20174/18/2017 3:58:49 PMPPASS
Brett Phone #: ###-####

Subdivision BMPs installed. Approved for excavation.
ESC16-01093 Site Final4/17/20174/18/20174/18/2017 3:08:16 PMPNR
Bill ###-####

Site in good condition. Not ready for ESC final. No violations at site. Site walk through with Bill

Remaining tasks:
- pull DI bags on Paso Fino
- remove stockpile of excess landscaping rock
- have installation of erosion control blanket inspected by ESC divivsion. ECB to be installed on slope between the landscapied portion of yard and the native vegetation that was preserved.

Wattle at limit of disturbance may remain and photodegrade.

Bill to call for re-inspection.
ESC17-00158 Complaint Inspection4/18/20174/18/20174/18/2017 11:55:27 AMPPART
Onsite meeting with RP Jason.

Permit sign posted, trackout observed last week was cleaned up after concrete work.

Correction:
- Sweep up section of gutter in front sites and install perimeter sediment control or create sediment trench at edge of pavement.

Will follow up
ESC17-00159 Complaint Inspection4/18/20174/18/20174/18/2017 11:54:56 AMPPART
Onsite meeting with RP Jason.

Permit sign posted, trackout observed last week was cleaned up after concrete work.

Correction:
- Sweep up section of gutter in front sites and install perimeter sediment control or create sediment trench at edge of pavement.

Will follow up
ESC17-00147 Complaint Inspection4/18/20174/18/20174/18/2017 11:52:45 AMPPASS
Site clean, trash contained, permit posted. Complaint more directed at Neff Street - Chesler Park developer and Odom Estates. Corrections in progress on related permits.
ESC16-00948 Complaint Inspection4/18/20174/18/20174/18/2017 11:40:06 AMPPART
Sweep up trackout from demolition activity that was left on Neff Street sidewalks.

Post Chesler Park SWPPP /City of Boise ESC sign.

ESC17-00366 Complaint Inspection4/18/20174/18/20174/18/2017 11:38:28 AMPPART
Demolition complete. No building materials on site.
Correction request:

Need to sweep dirt and debris on sidewalk and gutter from last weeks activity. Clear dirt above grade on parcels in Chesler Park
ESC16-01582 Complaint Inspection4/18/20174/18/20174/18/2017 11:32:17 AMPPASS
New storm drain inlets on 26th and on Neff side of Odom Estates have now had sediment filter bags installed this morning. Some minor trackout on Neff between two lots at entrance is to be swept later this week.

Excess stockpiles and tree debris from the irrigation ditch culvert will be removed end of this week or next depending on when the soil dries enough to get equipment on lots.

Talked to RP Dean via phone, met onsite superintendant Terrel.

Will check in next week.
ESC15-00853 General Inspection4/17/20174/18/20174/18/2017 9:39:41 AMPPEND
Uncontained trash piles have been hauled to dump, Hill Terrace was swept with vacuum sweeper.

Corrections in progress:
- finish installing trash containers, 1 per building
- DI bag maintenance on Hill Terrace drains - Posting site rules and SWPPP sign

Compliance deadline extended to 4/19 PM
Discussed details with developer Ron.
ESC16-01006 General Inspection4/18/20174/18/20174/18/2017 9:23:59 AM CANC
ESC15-01492 Aging Inspection4/18/20174/18/20174/18/2017 9:23:50 AM CANC
ESC15-00951 General Inspection4/17/20174/18/20174/18/2017 8:11:51 AMPCANC
ESC02-00609 DOC - Permit Finaled4/18/20174/18/20174/18/2017 8:07:32 AMPPASS
expired permit closed, no inspection
ESC16-01156 General Inspection4/18/20174/18/20174/18/2017 8:01:31 AM CANC
ESC16-00713 General Inspection4/18/20174/18/20174/18/2017 8:00:52 AM FAIL
Trackout all over road in front of home due to landscaping crew driving in muddy areas.

Verbal Correction Request to clean up all trackout. Follow 4/19
ESC16-00808 General Inspection4/18/20174/18/20174/18/2017 7:58:58 AM PEND
revegetation of access trail to retaining wall area in progress.
ESC16-00990 General Inspection4/18/20174/18/20174/18/2017 7:58:10 AM PASS
Inspected 4/17 PM

No activity. No sediement or other material running off site.
ESC16-00561 General Inspection4/18/20174/18/20174/18/2017 7:57:31 AM CANC
ESC16-01437 General Inspection4/7/20174/18/20174/17/2017 4:59:02 PMPPASS
WIP. Old building demolished, site work and excavation for new building ready to start. BMPs installed. Approved.
ESC16-00955 General Inspection4/11/20174/18/20174/17/2017 4:19:59 PMAPASS
follow up

Sediment control wattle installed in area of runoff on southeast corner of lot. Work to begin on retaining wall this week, afterwards another wattle or stabilization will be implemented. Approved.