Inspections for the day of: Friday, April 29, 2016.
Number of inspections: 27
Percentage of inspections complete: 100 %
Percentage of inspections not complete: 0 %
Contact Information
InspectorAndy J. Long
TitleEROSION INSPECTOR
Phone #794-8996
Permit NumberDescriptionReceivedRequestedCompletedAM/PMDisposition 
ESC15-00142 General Inspection4/29/20164/29/20165/2/2016 5:10:12 PM CANC
rescheduled
ESC16-00402 Site Preparation4/29/20164/29/20165/2/2016 10:00:25 AMPPASS
Inspection requested via web by Kyle Buzzell


BMPs installed. RP on site. Active townhomes in compliance. Approved.
ESC16-00415 Site Preparation4/29/20164/29/20165/2/2016 10:00:03 AMPCANC
Inspection requested via web by Kyle Buzzell


BMPs installed. RP on site. Active townhomes in compliance. Approved.
ESC16-00416 Site Preparation4/29/20164/29/20165/2/2016 9:59:38 AMPPASS
Inspection requested via web by Kyle Buzzell

BMPs installed. RP on site. Active townhomes in compliance. Approved.
ESC15-01395 Random Inspection4/29/20164/29/20164/29/2016 4:30:11 PMPPASS
Walk through BMP inspection with project management team member Bradden.

No significant trackout around site perimeter, leak proof designated concrete washout is provided in staging area. Stormwater DIs have inlet bags installed.

Correction requests:
- sweep up corner of 5th & Broad (started while on site)
- next week after concrete pouring activities and materials can be removed, street sweeping truck will be scheduled either Thursday or Friday.


Note- the stormdrain at 5th and Myrtle is not draining due system issue not related to construction.

Note: Site is seperating waste streams and designating materials suitable for recycling/re-use.
ESC15-01324 Aging Inspection4/29/20164/29/20164/29/2016 4:21:49 PM CANC
rescheduled for site final next week. Project is complete.
ESC14-01083 General Inspection4/29/20164/29/20164/29/2016 4:21:04 PM PASS
BMPs installed. No discharges or trackout. RP on site keeping crews clean. No corrections issued.
ESC14-00888 General Inspection4/29/20164/29/20164/29/2016 4:20:08 PM CANC
rescheduled for 5/4
ESC15-01311 Aging Inspection4/29/20164/29/20164/29/2016 4:19:33 PM PASS
Project complete. All permits finaled. ESC conditions satisfied.
ESC15-01311 DOC - Permit Finaled4/29/20164/29/20164/29/2016 4:19:12 PMPPASS
ESC15-00306 General Inspection4/29/20164/29/20164/29/2016 4:18:39 PM CANC
rescheduled for tuesday 5/3
ESC15-00019 General Inspection4/29/20164/29/20164/29/2016 4:18:11 PM CANC
rescheduled for tuesday 5/3
ESC15-01325 Aging Inspection4/29/20164/29/20164/29/2016 4:17:32 PM CANC
ESC15-01579 Conference4/29/20164/29/20164/29/2016 4:17:21 PMPPEND
check dewatering plan setup

Dewatering plan not set up per approved plan. Site is still under water in many areas due to slower than expeceted infiltration rates.

Approved to dewatering existing surface water using low volume pump skimming water from top and discharging through hose to sediment filter bag and grassy vegetated buffer between the sewer lift station and Parkcenter.

Requested that if dewatering occurs over weekend, it should be monitored regularly to check that discharge is in compliance with visible standards ( no visible plume)

Will check back on Monday
ESC15-01144 Aging Inspection4/29/20164/29/20164/29/2016 4:13:38 PM PASS
Skate park completed and open for public use. All construction materials, loose sediment swept, and DI bags removed.
ESC15-01144 DOC - Permit Finaled4/29/20164/29/20164/29/2016 4:12:20 PMPPASS
ESC15-00360 General Inspection4/29/20164/29/20164/29/2016 4:12:01 PM PASS
ESC15-00853 Random Inspection4/29/20164/29/20164/29/2016 2:06:26 PMPPASS
WIP on retaining wall. RP on site, no trackout, no discharges. No corrections requested at this time.
ESC15-01395 BMP Violation4/29/20164/29/20164/29/2016 2:04:27 PMPCANC
data entry error
ESC16-00588 Site Preparation4/28/20164/29/20164/29/2016 2:04:12 PMAPASS
Gene Phone #: ###-####-please call with an approx meet time

Large flat lot with preservation of exisiting driveway and landscaping. Low risk. RP familiar with ESC condtions. Apprvoed.
ESC15-00378 General Inspection4/29/20164/29/20164/29/2016 1:41:45 PM CANC
ESC15-00453 General Inspection4/29/20164/29/20164/29/2016 1:41:25 PM CANC
ESC15-00221 General Inspection4/29/20164/29/20164/29/2016 1:41:04 PM CANC
ESC15-01309 Aging Inspection4/29/20164/29/20164/29/2016 1:39:15 PM PASS
Demo complete. New SFH in progress. Now covered by ESC15-01189
ESC15-01309 DOC - Permit Finaled4/29/20164/29/20164/29/2016 1:37:08 PMPPASS
ESC15-01182 DOC - Permit Finaled4/29/20164/29/20164/29/2016 12:36:03 PMPPASS
ESC16-00343 Site Preparation4/28/20164/29/20164/29/2016 12:31:58 PMAPART
Dave Phone #: ###-####

Permit sign posted, storm drain has sediment filter bag installed previously, perimeter wattles in place.

Correction request:
- provide improved trash containment for foundation workers
- check that inlet bags have been maintained.